Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyHAYS
Highway US0290
From CALDWELL HAYS
To AND TRAVIS COUNTIES
CSJ 6256-60-001
Proj ID RMC - 625660001
Work Type MOWING HIGHWAY RIGHT OF WAY
 
1.000 810945.05 0.00 474839.23 59.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-17-13
Work Began 07-22-13
Work Completed  
Time Computed 07-22-13
Contract Working Days 247
Addl Days Granted 0
Working Days Charged 82
Percent Time Used 33
Contractor(s)
DEANGELO BROTHERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6256-60-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05134016
Totals 810945.05 0.00 474839.23 59.0

CountyBURNET
Highway US0281
From VAR LOCATIONS BURNET, LLANO, GILLESPIE
To WILLIAMSON, BLANCO, HAYS AND KENDALL
CSJ 6256-71-001
Proj ID RMC - 625671001
Work Type MOWING HIGHWAY RIGHT OF WAY
 
0.001 444034.00 0.00 328010.50 73.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-08-13
Work Began 07-15-13
Work Completed  
Time Computed 07-15-13
Contract Working Days 140
Addl Days Granted 0
Working Days Charged 65
Percent Time Used 46
Contractor(s)
JASCO
SUBCONTRACTOR(S) FOR CCSJ: 6256-71-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05134017
Totals 444034.00 0.00 328010.50 73.8

CountyWILLIAMSON
Highway US0183
From VARIOUS LOCATIONS IN WILLIAMSON AND
To TRAVIS AND BASTROP COUNTIES
CSJ 6256-96-001
Proj ID RMC - 625696001
Work Type MOWING HIGHWAY ROW
 
0.001 892794.00 0.00 456568.94 51.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-16-13
Work Began 07-22-13
Work Completed  
Time Computed 07-23-13
Contract Working Days 149
Addl Days Granted 0
Working Days Charged 61
Percent Time Used 40
Contractor(s)
DEANGELO BROTHERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6256-96-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05134008
Totals 892794.00 0.00 456568.94 51.9

CountyTRAVIS
Highway IH0035
From FROM VARIOUS LOCATIONS ON IH 35, LP 1
To TO US 183, US 290, ETC.
CSJ 6262-18-001
Proj ID RMC - 626218001
Work Type VARIOUS ROADSIDE MAINTENANCE
 
0.010 11375544.00 357296.55 2507197.94 22.0
Work Order 03-03-14
Work Began 00-00-00
Work Completed  
Time Computed 04-01-14
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 153
Percent Time Used 20
Contractor(s)
ISI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6262-18-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12134012
Totals 11375544.00 357296.55 2507197.94 22.0

CountyWILLIAMSON
Highway SH0029
From VARIOUS LOCATIONS IN TRAVIS AND
To WILLIAMSON COUNTIES
CSJ 6264-29-001
Proj ID RMC - 626429001
Work Type TREE REMOVAL AND TREE & BRUSH TRIMMING
 
0.001 198919.75 0.00 199577.65 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 01-14-14
Work Completed  
Time Computed 01-13-14
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 52
Percent Time Used 86
Contractor(s)
T.F.R. ENTERPRISES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6264-29-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11134017
Totals 198919.75 0.00 199577.65 99.9

CountyHAYS
Highway FM0012
From SOUTH OF DRIPPING SPRINGS
To NORTH OF WIMBERLEY
CSJ 6264-56-001
Proj ID RMC - 626456001
Work Type REPAIR AND THIN OVERLAY
 
13.216 991818.47 210730.00 1389272.89 99.9
Work Order 05-02-14
Work Began 04-12-14
Work Completed  
Time Computed 05-12-14
Contract Working Days 30
Addl Days Granted 12
Working Days Charged 57
Percent Time Used 135
Contractor(s)
RAMMING PAVING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6264-56-001
N-LINE TRAFFIC MAINTENANCE, L.P. (1.48%)
TEX OP CONSTRUCTION, LP(0.57%)
TRP CONSTRUCTION GROUP, LLC( 20.04%)
ALLEN KELLER COMPANY (0.00%)
Contract # 03144035
Totals 991818.47 210730.00 1389272.89 99.9

CountyLEE
Highway US0077
From VARIOUS LOCATIONS IN LEE
To AND BASTROP COUNTIES
CSJ 6264-57-001
Proj ID RMC - 626457001
Work Type SPOT REPAIR, LEVELUP AND TOM OVERLAY
 
0.001 792647.86 479369.49 707318.51 89.8
Work Order 00-00-00
Work Began 07-14-14
Work Completed  
Time Computed 07-14-14
Contract Working Days 17
Addl Days Granted 0
Working Days Charged 25
Percent Time Used 147
Contractor(s)
RAMMING PAVING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6264-57-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03144026
Totals 792647.86 479369.49 707318.51 89.8

CountyBLANCO
Highway US0281
From VARIOUS LOCATIONS IN BURNET AND
To BLANCO COUNTIES
CSJ 6264-95-001
Proj ID RMC - 626495001
Work Type MILL, SEAL AND OVERLAY
 
1.930 620476.99 0.00 653118.55 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 05-02-14
Work Completed  
Time Computed 05-01-14
Contract Working Days 51
Addl Days Granted 0
Working Days Charged 50
Percent Time Used 98
Contractor(s)
CLARK CONSTRUCTION OF TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6264-95-001
INTERSTATE BARRICADES & MARKINGS, INC. (4.83%)
S.A. CONCEPTS CONSTRUCTION (5.80%)
Contract # 02144006
Totals 620476.99 0.00 653118.55 99.9

CountyGILLESPIE
Highway SH0016
From VARIOUS LOCATIONS IN MASON &
To GILLESPIE COUNTIES
CSJ 6264-96-001
Proj ID RMC - 626496001
Work Type THIN OVERLAY
 
3.233 570434.32 0.00 581789.11 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 07-08-14
Work Completed  
Time Computed 00-00-00
Contract Working Days 34
Addl Days Granted 0
Working Days Charged 25
Percent Time Used 73
Contractor(s)
RAMMING PAVING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6264-96-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02144034
Totals 570434.32 0.00 581789.11 99.9

CountyWILLIAMSON
Highway RM1869
From RM 1174
To LOOP 332
CSJ 6264-97-001
Proj ID RMC - 626497001
Work Type LEVEL UP, SEAL COAT
 
6.864 687770.48 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 34
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6264-97-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07144209
Totals 687770.48 0.00 0.00 0.0

CountyBURNET
Highway SH0071
From 0.114 MI W OF US 281
To TRAVIS COUNTY LINE
CSJ 6264-99-001
Proj ID RMC - 626499001
Work Type SEAL COAT
 
12.350 799999.99 0.00 55864.01 6.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 07-23-14
Work Completed  
Time Computed 07-23-14
Contract Working Days 34
Addl Days Granted 0
Working Days Charged 7
Percent Time Used 20
Contractor(s)
BLACKTOPPER TECHNOLOGY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6264-99-001
D. I. J. CONSTRUCTION, INC.( 28.48%)
HIGHWAY INFRASTRUCTURE SAFETY SERVICES, INC. (0.62%)
Contract # 03144009
Totals 799999.99 0.00 55864.01 6.9

CountyBURNET
Highway SH0029
From VARIOUS LOCATIONS IN BURNET AND LLANO
To COUNTIES
CSJ 6265-00-001
Proj ID RMC - 626500001
Work Type SEAL COAT, LEVEL UP IN BURNET AND LLANO
 
12.930 1736017.85 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 51
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ANGEL BROTHERS ENTERPRISES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6265-00-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09144007
Totals 1736017.85 0.00 0.00 0.0

CountyWILLIAMSON
Highway SH0095
From CR 452
To TRAVIS COUNTY LINE
CSJ 6265-29-001
Proj ID RMC - 626529001
Work Type LEVEL UP & SEAL COAT
 
9.344 784851.51 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 37
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
RAMMING PAVING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6265-29-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07144211
Totals 784851.51 0.00 0.00 0.0

CountyWILLIAMSON
Highway US0183
From VARIOUS LOCATIONS IN WILLIAMSON COUNTY
To .
CSJ 6265-31-001
Proj ID RMC - 626531001
Work Type TREE TRIMMING & TREE / BRUSH REMOVAL
 
0.001 370278.03 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 90
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ANALYTICAL TECHNOLOGY CONSULTANTS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6265-31-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07144007
Totals 370278.03 0.00 0.00 0.0

CountyCALDWELL
Highway FM0020
From US 183
To CALDWELL COUNTY LINE
CSJ 6265-46-001
Proj ID RMC - 626546001
Work Type PAVEMENT REPAIR, SEAL AND OVERLAY
 
8.457 878009.24 78616.65 935866.28 99.9
Work Order 00-00-00
Work Began 07-08-14
Work Completed  
Time Computed 07-08-14
Contract Working Days 21
Addl Days Granted 3
Working Days Charged 24
Percent Time Used 100
Contractor(s)
RAMMING PAVING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6265-46-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03144008
Totals 878009.24 78616.65 935866.28 99.9

CountyTRAVIS
Highway IH0035
From VARIOUS LOCATIONS IN THE AUSTIN DISTRICT
To .
CSJ 6266-62-001
Proj ID RMC - 626662001
Work Type PAVEMENT MARKINGS AND MARKERS
 
0.001 2060650.00 0.00 1474198.78 71.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-10-14
Work Began 03-11-14
Work Completed  
Time Computed 03-17-14
Contract Working Days 480
Addl Days Granted 0
Working Days Charged 43
Percent Time Used 8
Contractor(s)
D. I. J. CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6266-62-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02144024
Totals 2060650.00 0.00 1474198.78 71.5

CountyTRAVIS
Highway IH0035
From VARIOUS LOCATIONS DISTRICTWIDE
To VARIOUS LOCATIONS DISTRICTWIDE
CSJ 6273-73-001
Proj ID RMC - 627373001
Work Type SIGNAL INSTALLATION - MODIFICATION
 
0.001 939630.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 6273-73-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09144006
Totals 939630.00 0.00 0.00 0.0

page 1 | page 2