Monthly State Let Maintenance Report For Amarillo District As Of Apr 12, 2024 Page 3 Of 3

Last Update: Friday, April 12, 2024
FTP Icon
page 1 | page 2 | page 3

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyCARSON
HighwayUS0060
FromVARIOUS LOCATIONS ~ SEE PLAN SHEETS
ToVARIOUS LOCATIONS ~ SEE PLAN SHEETS
CSJ6446-80-001
Proj IDMMC - 644680001
Work TypeASPHALT
 
0.0102240881.20200753.688.9
Work Order00-00-00
Work Began10-16-23
Work Completed
Time Computed10-12-23
Contract Working Days120
Addl Days Granted120
Working Days Charged168
Percent Time Used70
Contractor(s)
ERGON ASPHALT & EMULSIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6446-80-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08234004
Totals2240881.2027642.66200753.688.9

CountyPOTTER
HighwayIH0040
FromVARIOUS LOCATIONS ~ SEE PLAN SHEETS
ToVARIOUS LOCATIONS ~ SEE PLAN SHEETS
CSJ6446-82-001
Proj IDMMC - 644682001
Work TypeHYDRAULIC CEMENT
 
0.010429380.0056648.1313.1
Work Order00-00-00
Work Began10-12-23
Work Completed
Time Computed10-12-23
Contract Working Days120
Addl Days Granted120
Working Days Charged183
Percent Time Used76
Contractor(s)
AKA-MATERIALS
SUBCONTRACTOR(S) FOR CCSJ: 6446-82-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08234005
Totals429380.000.0056648.1313.1

CountyRANDALL
HighwayIH0027
FromVARIOUS LOCATIONS ~ SEE PLAN SHEETS
ToVARIOUS LOCATIONS ~ SEE PLAN SHEETS
CSJ6446-84-001
Proj IDMMC - 644684001
Work TypeFLEXIBLE BASE
 
0.0101816521.84650170.2535.7
Work Order00-00-00
Work Began10-10-23
Work Completed
Time Computed09-27-23
Contract Working Days120
Addl Days Granted120
Working Days Charged174
Percent Time Used72
Contractor(s)
VOLCANIC STONE CO.
SUBCONTRACTOR(S) FOR CCSJ: 6446-84-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08234203
Totals1816521.8422246.97650170.2535.7

CountyRANDALL
HighwayIH0027
FromVARIOUS LOCATIONS ~ SEE PLAN SHEETS
ToVARIOUS LOCATIONS ~ SEE PLAN SHEETS
CSJ6446-86-001
Proj IDMMC - 644686001
Work TypeSNOW AND ICE CONTROL
 
0.010116953.2526729.1922.8
Work Order00-00-00
Work Began11-06-23
Work Completed
Time Computed09-27-23
Contract Working Days120
Addl Days Granted120
Working Days Charged152
Percent Time Used63
Contractor(s)
NSG LOGISTICS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6446-86-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08234204
Totals116953.250.0026729.1922.8

CountyHUTCHINSON
HighwaySH0207
FromVARIOUS LOCATIONS ~ SEE PLAN SHEETS
ToVARIOUS LOCATIONS ~ SEE PLAN SHEETS
CSJ6446-88-001
Proj IDMMC - 644688001
Work TypeDE-ICING SALT
 
0.0101979894.50437400.5722.0
Work Order00-00-00
Work Began10-10-23
Work Completed
Time Computed09-27-23
Contract Working Days120
Addl Days Granted120
Working Days Charged174
Percent Time Used72
Contractor(s)
NSG LOGISTICS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6446-88-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08234205
Totals1979894.500.00437400.5722.0

CountyHANSFORD
HighwaySH0015
FromVARIOUS LOCATIONS ~ SEE PLAN SHEETS
ToVARIOUS LOCATIONS ~ SEE PLAN SHEETS
CSJ6446-90-001
Proj IDMMC - 644690001
Work TypeWINTER WEATHER MATERIAL
 
0.010772453.00216134.2927.9
Work Order00-00-00
Work Began10-11-23
Work Completed
Time Computed09-27-23
Contract Working Days120
Addl Days Granted120
Working Days Charged174
Percent Time Used72
Contractor(s)
VOLCANIC STONE CO.
SUBCONTRACTOR(S) FOR CCSJ: 6446-90-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08234206
Totals772453.000.00216134.2927.9

CountyCARSON
HighwayUS0060
FromVARIOUS LOCATIONS ~ SEE PLAN SHEETS
ToVARIOUS LOCATIONS ~ SEE PLAN SHEETS
CSJ6461-55-001
Proj IDMMC - 646155001
Work TypeAGGREGATE
 
0.0101429382.40284644.2519.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began03-07-24
Work Completed
Time Computed00-00-00
Contract Working Days120
Addl Days Granted0
Working Days Charged26
Percent Time Used21
Contractor(s)
HOWELL SAND COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6461-55-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01244002
Totals1429382.40284644.25284644.2519.9

CountyMOORE
HighwayUS0087
FromVARIOUS LOCATIONS ~ SEE PLAN SHEETS
ToVARIOUS LOCATIONS ~ SEE PLAN SHEETS
CSJ6461-56-001
Proj IDMMC - 646156001
Work TypeAGGREGATE
 
0.010225718.000.000.0
Work Order00-00-00
Work Began03-06-24
Work Completed
Time Computed03-06-24
Contract Working Days120
Addl Days Granted0
Working Days Charged26
Percent Time Used21
Contractor(s)
HOWELL SAND COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6461-56-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01244003
Totals225718.000.000.000.0

CountyGRAY
HighwayUS0060
FromVARIOUS LOCATIONS ~ SEE PLAN SHEETS
ToVARIOUS LOCATIONS ~ SEE PLAN SHEETS
CSJ6461-77-001
Proj IDRMC - 646177001
Work TypeTREE REMOVAL
 
0.010459000.640.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed03-01-24
Contract Working Days60
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ALLIES LAND CLEARING
SUBCONTRACTOR(S) FOR CCSJ: 6461-77-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01244202
Totals459000.640.000.000.0

CountyPOTTER
HighwayIH0040
FromVARIOUS LOCATIONS ~ SEE PLAN SHEETS
ToVARIOUS LOCATIONS ~ SEE PLAN SHEETS
CSJ6462-58-001
Proj IDRMC - 646258001
Work TypeTOTAL MAINTENANCE
 
0.0106977100.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed04-01-24
Contract Working Days730
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6462-58-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02244231
Totals6977100.000.000.000.0

CountyMOORE
HighwayUS0087
FromVARIOUS LOCATIONS- SEE PLAN SHEETS
ToVARIOUS LOCATIONS-SEE PLAN SHEETS
CSJ6462-69-001
Proj IDRMC - 646269001
Work TypeMETAL BEAM GUARD FENCE REPAIR
 
0.010326375.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed04-01-24
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
E.V.G. ENTERPRISE
SUBCONTRACTOR(S) FOR CCSJ: 6462-69-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02244232
Totals326375.000.000.000.0

CountyHARTLEY
HighwayUS0087
FromVARIOUS LOCATIONS ~ SEE PLAN SHEETS
ToVARIOUS LOCATIONS ~ SEE PLAN SHEETS
CSJ6462-85-001
Proj IDMMC - 646285001
Work TypeHOT MIX
 
0.010600000.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days120
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
BIG CREEK SAND & GRAVEL, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6462-85-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03244001
Totals600000.000.000.000.0

CountyHUTCHINSON
HighwaySH0207
FromVARIOUS LOCATIONS- SEE PLAN SHEETS
ToVARIOUS LOCATIONS-SEE PLAN SHEETS
CSJ6463-47-001
Proj IDRMC - 646347001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.010362972.800.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days40
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TEXAS BLACKTOPS LLC
SUBCONTRACTOR(S) FOR CCSJ: 6463-47-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04244022
Totals362972.800.000.000.0

CountyPOTTER
HighwayIH0040
FromVARIOUS LOCATIONS- SEE PLAN SHEETS
ToVARIOUS LOCATIONS-SEE PLAN SHEETS
CSJ6463-61-001
Proj IDRMC - 646361001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.010223267.600.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days20
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
RISE UP CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 6463-61-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04244024
Totals223267.600.000.000.0

CountyHEMPHILL
HighwayUS0060
FromVARIOUS LOCATIONS- SEE PLAN SHEETS
ToVARIOUS LOCATIONS-SEE PLAN SHEETS
CSJ6463-68-001
Proj IDRMC - 646368001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.010360004.600.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days45
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
BERT WHITAKER
SUBCONTRACTOR(S) FOR CCSJ: 6463-68-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04244025
Totals360004.600.000.000.0

CountyCARSON
HighwayIH0040
FromVARIOUS LOCATIONS- SEE PLAN SHEETS
ToVARIOUS LOCATIONS-SEE PLAN SHEETS
CSJ6463-69-001
Proj IDRMC - 646369001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.010434933.100.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days56
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
BERT WHITAKER
SUBCONTRACTOR(S) FOR CCSJ: 6463-69-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04244026
Totals434933.100.000.000.0