Monthly State Let Construction Report For Wichita Falls District As Of Feb 09, 2018 Page 2 Of 2

Last Update: Friday, February 09, 2018
FTP Icon
page 1 | page 2

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyCLAY
HighwayFM 810
FromFM 171
ToSH 79
CSJ0391-02-018
Proj IDSTP 1702(124)
Work TypeREHABLITATION OF EXISTING ROAD
 
15.9031895820.801383264.5972.9
Work Order06-14-17
Work Began08-21-17
Work Completed
Time Computed07-14-17
Contract Working Days170
Addl Days Granted0
Working Days Charged83
Percent Time Used48
Contractor(s)
BEAR CREEK CONTRACTING, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0391-02-018
ODUM SERVICES, L.P. (4.46)
ALTUS TRAFFIC MANAGEMENT LLC (0.11)
Contract #05173003
Totals1895820.80347371.941383264.5972.9

CountyYOUNG
HighwayFM 61
FromUS 380
ToFM 3003
CSJ0529-01-023
Proj IDSTP 1602(001)
Work TypeOVERLAY
 
8.7974288948.684299118.0799.9
Work Order06-24-16
Work Began08-03-16
Work Completed
Time Computed07-24-16
Contract Working Days186
Addl Days Granted19
Working Days Charged254
Percent Time Used123
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0529-01-023
W.S. CONSTRUCTION COMPANY (10.39)
DALLAS LITE AND BARRICADE INC. (0.41)
BARRICADES UNLIMITED (2.30)
HJC FARMS, INC. (1.63)
ZACK BURKETT CO. (29.82)
Contract #04163003
Totals4288948.683550.894299118.0799.9

CountyWILBARGER
HighwayFM 91
FromFM 91 AT WANDERERS CREEK
To.
CSJ0702-01-014
Proj IDBR 2016(928)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.7672458571.502537658.1799.9
Work Order06-02-16
Work Began09-13-16
Work Completed
Time Computed07-02-16
Contract Working Days187
Addl Days Granted15
Working Days Charged241
Percent Time Used119
Contractor(s)
EARTH BUILDERS, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0702-01-014
M & D FOUNDATION DRILLING INDUSTRIES, INC. (7.47)
DALLAS LITE AND BARRICADE INC. (0.76)
BARRICADES UNLIMITED (1.40)
HOUSTON SAWING & DRILLING (0.30)
LANCO TURF & SEEDING, INC. (2.01)
MCL CONTRACTING, LLC (0.57)
RK HALL, LLC (5.01)
Contract #04163019
Totals2458571.500.002537658.1799.9

CountyWICHITA
HighwayFM 369
FromNEAR US 82/277
ToLP 473/ SH 79 INTERCHANGE
CSJ0802-02-066
Proj IDNH 1602(002)
Work TypeREHABILITATION OF EXISTING ROAD
 
6.9412496814.422336734.3293.5
Work Order09-20-16
Work Began12-06-16
Work Completed
Time Computed10-20-16
Contract Working Days268
Addl Days Granted20
Working Days Charged249
Percent Time Used86
Contractor(s)
O. TREVINO CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0802-02-066
ALTUS TRAFFIC MANAGEMENT LLC (0.95)
W.O.E. CONSTRUCTION (0.38)
TRP CONSTRUCTION GROUP, LLC (11.76)
PEACHTREE CONSTRUCTION, LTD. (7.19)
LANCO TURF & SEEDING, INC. (1.23)
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC. (25.12)
DOUBLE S CONSTRUCTION (0.52)
Contract #07163033
Totals2496814.4214000.002336734.3293.5

CountyWICHITA
HighwayVA
FromVARIOUS LOCATIONS DISTRICTWIDE
ToVARIOUS LOCATIONS DISTRICTWIDE
CSJ0903-00-083
Proj IDSTP 1702(126)
Work TypeTRAFFIC MANAGEMENT
 
1.000938930.00631613.8267.2
Work Order06-08-17
Work Began10-25-17
Work Completed
Time Computed10-06-17
Contract Working Days68
Addl Days Granted0
Working Days Charged50
Percent Time Used73
Contractor(s)
MICA CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 0903-00-083
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05173214
Totals938930.00159139.79631613.8267.2

CountyWICHITA
HighwayCS
FromON MAPLEWOOD AVENUE SOUTH BOUND AT
ToDRAINAGE DITCH
CSJ0903-03-083
Proj IDBR 2006(550)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.2001293885.000.000.0
Work Order07-20-17
Work Began00-00-00
Work Completed
Time Computed08-19-17
Contract Working Days123
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
EARTH BUILDERS, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0903-03-083
LANCO TURF & SEEDING, INC. (0.99)
ALTUS TRAFFIC MANAGEMENT LLC (0.31)
PREMIER PAVING, LTD. (6.75)
Contract #06173206
Totals1293885.000.000.000.0

CountyYOUNG
HighwayFM 209
FromFM 578
To3.69 MI WEST OF SH 67
CSJ1076-02-040
Proj IDSTP 2017(881)
Work TypeRESTORATION
 
14.0332333357.95644596.5927.6
Work Order04-19-17
Work Began06-16-17
Work Completed
Time Computed05-19-17
Contract Working Days213
Addl Days Granted6
Working Days Charged138
Percent Time Used63
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1076-02-040
W.S. CONSTRUCTION COMPANY (40.00)
ALTUS TRAFFIC MANAGEMENT LLC (0.72)
COMEN ENTERPRISE LLC (3.42)
TOTAL HIGHWAY MAINTENANCE, LLC (1.43)
WOLFE CONSTRUCTION GROUP, INC. (0.80)
NIXON ENGINEERING (0.12)
Contract #03173036
Totals2333357.9519456.95644596.5927.6

CountyMONTAGUE
HighwayFM 455
From1.056 MI WEST OF FM 730
To0.056 MI WEST OF FM 730
CSJ1352-02-021
Proj IDSTP 1702(127)HES
Work TypeHAZARD ELIMINATION SAFETY
 
1.000554791.65263115.2947.4
Work Order06-08-17
Work Began11-27-17
Work Completed
Time Computed07-08-17
Contract Working Days103
Addl Days Granted0
Working Days Charged29
Percent Time Used28
Contractor(s)
THE LANE CONSTRUCTION CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 1352-02-021
TOTAL HIGHWAY MAINTENANCE, LLC (1.04)
WOLFE CONSTRUCTION GROUP, INC. (1.89)
SOUTHERN CROSS CONTRACTORS, LLC (1.59)
TOTAL HIGHWAY MAINTENANCE, LLC (2.53)
Contract #05173205
Totals554791.65165907.25263115.2947.4

CountyCOOKE
HighwayFM 1201
FromCR 406 NORTH OF MOSS LAKE
ToFM 1200
CSJ1356-01-027
Proj IDSTP 2017(273)
Work TypeRESTORATION
 
15.9171250025.001347209.1399.9
Work Order12-12-16
Work Began01-31-17
Work Completed
Time Computed01-11-17
Contract Working Days82
Addl Days Granted48
Working Days Charged142
Percent Time Used109
Contractor(s)
HODGES AND SON CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1356-01-027
TOTAL HIGHWAY MAINTENANCE, LLC (1.68)
PEACHTREE CONSTRUCTION, LTD. (5.22)
TEXAS ALTERNATIVE GRASSER, INC. (0.29)
COMEN ENTERPRISE LLC (3.02)
MASSEY CONTRACTORS, LLC (2.60)
LONE STAR HIGHWAY PRODUCTS, INC. (0.83)
Contract #11163017
Totals1250025.0038687.891347209.1399.9

CountyCOOKE
HighwayFM 678
FromFM 3164
To0.339 MILES SOUTH OF US 82.
CSJ1357-02-012
Proj IDSTP 1602(201)
Work TypeREHABILITATION OF EXISTING ROADWAY
 
2.5451677816.781660214.1298.9
Work Order08-17-16
Work Began10-24-16
Work Completed
Time Computed09-16-16
Contract Working Days125
Addl Days Granted0
Working Days Charged124
Percent Time Used99
Contractor(s)
THE LANE CONSTRUCTION CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 1357-02-012
ALTUS TRAFFIC MANAGEMENT LLC (0.49)
W.S. CONSTRUCTION COMPANY (12.10)
TOTAL HIGHWAY MAINTENANCE, LLC (1.19)
MARCOM"S MOWING SERVICE, LLC (0.52)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (8.99)
TEXAS ALTERNATIVE GRASSER, INC. (0.52)
OSCAR ORDUNO, INC. (2.62)
Contract #06163009
Totals1677816.780.001660214.1298.9

CountyYOUNG
HighwayFM 1769
FromSH 114
ToUS 380
CSJ1711-01-029
Proj IDSTP 2017(404)
Work TypeREHABILITATION OF EXISTING ROAD
 
7.9863310004.480.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-10-18
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days153
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
JAGOE-PUBLIC COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1711-01-029
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12173209
Totals3310004.480.000.000.0

CountyCLAY
HighwayFM 2393
FromN OF WESTBOUND FRONTAGE ROAD
ToRR ROW
CSJ2405-01-012
Proj IDSTP 2018(558)
Work TypeREHABILITATION OF EXISTING ROAD
 
2.7042307479.200.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days95
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2405-01-012
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02183209
Totals2307479.200.000.000.0

CountyWICHITA
HighwayFM 2650
FromFM 369
ToARCHER COUNTY LINE
CSJ2644-01-010
Proj IDSTP 2013(623)
Work TypeREHABILITATION OF EXISTING ROADWAY
 
3.4934231186.984200470.9699.2
Work Order07-22-15
Work Began01-18-16
Work Completed
Time Computed08-07-15
Contract Working Days149
Addl Days Granted80
Working Days Charged222
Percent Time Used96
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2644-01-010
ALTUS TRAFFIC MANAGEMENT LLC (0.18)
BARRICADES UNLIMITED (0.80)
HJC FARMS, INC. (1.87)
ZACK BURKETT CO. (33.52)
W.S. CONSTRUCTION COMPANY (5.56)
Contract #05153050
Totals4231186.980.004200470.9699.2

page 1 | page 2