Monthly State Let Construction Report For Wichita Falls District As Of Feb 09, 2018 Page 1 Of 2

Last Update: Friday, February 09, 2018
FTP Icon
page 1 | page 2

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyMONTAGUE
HighwayUS 81
From0.410 MI N OF SS 511
ToWISE CO LINE
CSJ0013-05-060
Proj IDSTP 1702(123)HES
Work TypeHAZARD ELIMINATION SAFETY
 
2.3623439171.432537161.5473.7
Work Order06-14-17
Work Began07-14-17
Work Completed
Time Computed07-14-17
Contract Working Days100
Addl Days Granted6
Working Days Charged86
Percent Time Used81
Contractor(s)
DUININCK, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0013-05-060
ANALYTICAL TECHNOLOGY CONSULTANTS, INC. (6.32)
W.S. CONSTRUCTION COMPANY (1.34)
PRIMATE CONSTRUCTION, INC. (0.79)
LINDAMOOD CONSTRUCTION COMPANY, INC. (0.28)
THE LANE CONSTRUCTION CORPORATION (12.55)
DUSTROL, INC. (0.84)
COX PAVING OF TEXAS, INC. (2.33)
BOWMAN ENGINEERING & CONSULTING, INC (1.10)
TOTAL HIGHWAY MAINTENANCE, LLC (0.99)
WOLFE CONSTRUCTION GROUP, INC. (0.28)
Contract #05173027
Totals3439171.43111907.962537161.5473.7

CountyWILBARGER ETC
HighwayUS 287 ETC
FromUS 287
ToAT FM 432 (PARK ROADS)
CSJ0043-05-106
Proj IDNH 2018(247)
Work TypeSEAL COAT
 
198.8996016230.1232845.390.5
Work Order01-10-18
Work Began00-00-00
Work Completed
Time Computed02-09-18
Contract Working Days62
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
RONALD R. WAGNER & CO., LP
SUBCONTRACTOR(S) FOR CCSJ: 0043-05-106
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11173204
Totals6016230.1232845.3932845.390.5

CountyWILBARGER
HighwayUS 287
FromUS 287 NB
ToAT PEASE RIVER
CSJ0043-05-107
Proj IDBR 2018(349)
Work TypeBRIDGE MAINTENANCE
 
0.4041842668.480.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-25-18
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days102
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
GIBSON & ASSOCIATES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0043-05-107
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12173003
Totals1842668.480.000.000.0

CountyWILBARGER
HighwayUS 70
FromFM 433
ToAT US 70/287
CSJ0043-06-084
Proj IDBR 1702(470)
Work TypeBRIDGE REHABILITATION OR WIDENING
 
0.5303149693.50430255.0813.6
Work Order08-08-17
Work Began10-17-17
Work Completed
Time Computed09-07-17
Contract Working Days204
Addl Days Granted0
Working Days Charged61
Percent Time Used29
Contractor(s)
SCR CIVIL CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0043-06-084
ALTUS TRAFFIC MANAGEMENT LLC (0.54)
MCL CONTRACTING, LLC (0.52)
A. L. HELMCAMP, INC. (10.96)
S & S BRIDGE PAINTING, INC. (7.88)
DUSTIN ALLEN, INC. (5.35)
SOUTHEAST GRINDING & GROOVING, LLC (0.15)
LLOYD D. NABORS DEMOLITION LLC (1.58)
BARRICADES UNLIMITED (1.47)
TEXOP CONSTRUCTION (0.44)
NELSON INDUSTRIAL SERVICES, INC. (0.15)
Contract #07173229
Totals3149693.5051743.53430255.0813.6

CountyWILBARGER
HighwayUS 287
FromNEAR SH 240
ToNEAR BU 287H
CSJ0043-07-109
Proj IDNH 2017(140)
Work TypeREHABILITATION OF EXISTING ROAD
 
3.4022490919.292492421.7399.9
Work Order11-22-16
Work Began04-20-17
Work Completed
Time Computed12-22-16
Contract Working Days102
Addl Days Granted10
Working Days Charged95
Percent Time Used84
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0043-07-109
CONTRACTORS SERVICE COMPANY (0.48)
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC. (4.30)
STRIPING TECHNOLOGY, L.P. (1.50)
W.S. CONSTRUCTION COMPANY (1.42)
ZACK BURKETT CO. (54.49)
STRIPING SYSTEMS, INC. (0.00)
Contract #10163025
Totals2490919.290.002492421.7399.9

CountyWICHITA
HighwayUS 287
FromAT WELLINGTON LANE
To.
CSJ0043-09-126
Proj IDBR 1602(577)
Work TypeBRIDGE REPLACEMENT
 
0.3112454758.602291754.8593.3
Work Order10-12-16
Work Began12-20-16
Work Completed
Time Computed11-11-16
Contract Working Days185
Addl Days Granted0
Working Days Charged179
Percent Time Used96
Contractor(s)
HODGES AND SON CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0043-09-126
COMEN ENTERPRISE LLC (2.39)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (2.33)
MARCOM"S MOWING SERVICE, LLC (1.21)
ZACK BURKETT CO. (6.28)
TOTAL HIGHWAY MAINTENANCE, LLC (1.43)
A BROTHERS MILLING, LLC (0.61)
Contract #08163208
Totals2454758.600.002291754.8593.3

CountyWICHITA
HighwayUS 287
FromAT RIFLE RANGE ROAD
To.
CSJ0043-09-130
Proj IDBR 1702(594)
Work TypeBRIDGE REPLACEMENT
 
0.3482398060.27664603.9227.7
Work Order08-11-17
Work Began11-02-17
Work Completed
Time Computed09-10-17
Contract Working Days214
Addl Days Granted0
Working Days Charged41
Percent Time Used19
Contractor(s)
COPPELL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0043-09-130
MORRIS COUNTY CONTRACTORS, LLC (3.20)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (2.65)
WOLFE CONSTRUCTION GROUP, INC. (1.31)
STRIPING TECHNOLOGY, L.P. (0.65)
STRIPING SYSTEMS, INC. (0.00)
ZACK BURKETT CO. (11.24)
MICA CORPORATION (3.08)
TEXOP CONSTRUCTION (1.47)
ALTUS TRAFFIC MANAGEMENT LLC (0.63)
BOWMAN ENGINEERING & CONSULTING, INC (0.18)
Contract #07173249
Totals2398060.2710974.00664603.9227.7

CountyWICHITA
HighwaySL 11
FromLOOP 11 AT WICHITA RIVER
To.
CSJ0043-14-024
Proj IDBR 2017(880)
Work TypeUPGRADE BRIDGE AND APPROACH RAILING
 
0.076351296.40343762.9397.8
Work Order04-12-17
Work Began06-05-17
Work Completed
Time Computed05-12-17
Contract Working Days51
Addl Days Granted0
Working Days Charged50
Percent Time Used98
Contractor(s)
COPPELL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0043-14-024
DUSTIN ALLEN, INC. (4.26)
ALTUS TRAFFIC MANAGEMENT LLC (0.45)
Contract #03173004
Totals351296.400.00343762.9397.8

CountyWICHITA
HighwayBU 287J
FromJOHNSON ROAD.
ToFM 368/ YOSEMITE ST.
CSJ0043-17-030
Proj IDNH 2017(399)
Work TypeOVERLAY
 
7.6283440613.521814986.6653.4
Work Order01-17-17
Work Began08-22-17
Work Completed
Time Computed02-16-17
Contract Working Days51
Addl Days Granted0
Working Days Charged77
Percent Time Used150
Contractor(s)
ZACK BURKETT CO.
SUBCONTRACTOR(S) FOR CCSJ: 0043-17-030
W.S. CONSTRUCTION COMPANY (3.09)
TEXAS ALTERNATIVE GRASSER, INC. (0.29)
DUSTROL, INC. (4.84)
STRIPE-A-ZONE, INC. (3.32)
HJC FARMS, INC. (1.42)
CONTRACTORS SERVICE COMPANY (0.51)
Contract #12163012
Totals3440613.520.001814986.6653.4

CountyCLAY
HighwayUS 82 ETC
FromUS 82 EASTBOUND AT DUCK CREEK
To.
CSJ0044-02-079
Proj IDBR 2016(355)
Work TypeUPGRADE BRIDGE AND APPROACH RAILING
 
24.6745938095.151288107.8721.6
Work Order03-31-16
Work Began06-05-17
Work Completed
Time Computed05-01-16
Contract Working Days197
Addl Days Granted14
Working Days Charged142
Percent Time Used67
Contractor(s)
ZACK BURKETT CO.
SUBCONTRACTOR(S) FOR CCSJ: 0044-02-079
W.S. CONSTRUCTION COMPANY (14.24)
COTHRAN TRUCKING, LLC (0.95)
WOLFE CONSTRUCTION GROUP, INC. (0.42)
DUSTROL, INC. (17.02)
HALL BROTHERS, INC. (7.12)
DUSTIN ALLEN, INC. (4.55)
TOTAL HIGHWAY MAINTENANCE, LLC (1.83)
ALTUS TRAFFIC MANAGEMENT LLC (0.47)
Contract #01163022
Totals5938095.15104129.611288107.8721.6

CountyCOOKE
HighwayUS 82
FromNEAR WEBER DRIVE
ToNEAR IH 35
CSJ0044-08-067
Proj IDNH 2016(693)
Work TypeREHABILITATION OF EXISTING ROAD
 
7.3214684274.465493395.4199.9
Work Order05-18-16
Work Began08-29-16
Work Completed
Time Computed06-17-16
Contract Working Days192
Addl Days Granted149
Working Days Charged298
Percent Time Used87
Contractor(s)
JAGOE-PUBLIC COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0044-08-067
DALLAS LIGHT & BARRICADES (0.87)
MARCOM"S MOWING SERVICE, LLC (0.43)
DUSTROL, INC. (1.65)
DRILL TECH DRILLING & SHORING, INC. (4.89)
METRO CUTTING AND SEALING, INC. (3.55)
STRIPING TECHNOLOGY, L.P. (2.00)
NORTH TEXAS TRAFFIC SYSTEMS CONSTRUCTION, LTD. (7.31)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.88)
W.O.E. CONSTRUCTION (0.59)
FARR FOUNDATION, INC. (5.72)
JSS BORI GROUP, LLC (3.56)
OSCAR ORDUNO, INC. (6.19)
JND & SONS BARRIER, LLC (2.01)
DALLAS FOUNDATION DRILLING CO., INC. (0.00)
Contract #02163209
Totals4684274.46180377.445493395.4199.9

CountyCOOKE
HighwayUS 82
FromFAIR AVENUE
ToGRAYSON COUNTY LINE
CSJ0045-01-061
Proj IDNH 2018(556)
Work TypeOVERLAY
 
10.6472124211.950.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days50
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
JAGOE-PUBLIC COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0045-01-061
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02183025
Totals2124211.950.000.000.0

CountyWILBARGER
HighwayUS 183
FromBEAVER CREEK
ToNEAR FM 2585
CSJ0124-04-031
Proj IDSTP 2017(141)
Work TypeREHABILITATION OF EXISTING ROAD
 
6.0976688994.614050865.0560.5
Work Order11-22-16
Work Began01-03-17
Work Completed
Time Computed12-22-16
Contract Working Days208
Addl Days Granted22
Working Days Charged200
Percent Time Used86
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0124-04-031
CONTRACTORS SERVICE COMPANY (0.23)
HJC FARMS, INC. (1.75)
W.S. CONSTRUCTION COMPANY (11.63)
TOTAL HIGHWAY MAINTENANCE, LLC (1.21)
WEST TEXAS RUMBLE STRIP (0.13)
ZACK BURKETT CO. (45.77)
Contract #10163005
Totals6688994.61522587.624050865.0560.5

CountyTHROCKMORTON
HighwayUS 183
FromNORTH CITY LIMITS OF THROCKMORTON
ToCOLLEGE STREET
CSJ0125-02-033
Proj IDSTP 2018(350)
Work TypeOVERLAY
 
8.3251743252.560.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-10-18
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days48
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ZACK BURKETT CO.
SUBCONTRACTOR(S) FOR CCSJ: 0125-02-033
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12173217
Totals1743252.560.000.000.0

CountyTHROCKMORTON
HighwayUS 283
FromONE MILE NORTH OF FM 2584
ToFM 209
CSJ0125-03-046
Proj IDSTP 2018(185)
Work TypeREHABILITATION OF EXISTING ROAD
 
3.1961720296.45209050.1612.1
Work Order11-10-17
Work Began12-06-17
Work Completed
Time Computed12-10-17
Contract Working Days136
Addl Days Granted0
Working Days Charged28
Percent Time Used20
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0125-03-046
ANTIGO CONSTRUCTION, INC. (1.00)
CONTRACTORS SERVICE COMPANY (0.39)
HJC FARMS, INC. (0.31)
TOTAL HIGHWAY MAINTENANCE, LLC (1.24)
Contract #10173215
Totals1720296.4581903.50209050.1612.1

CountyYOUNG
HighwaySH 114
FromFM 2178 NORTH
ToSL 132/S AVE M
CSJ0133-08-035
Proj IDNH 2018(249)
Work TypeREHABILITATION OF EXISTING ROAD
 
2.7101069536.550.000.0
Work Order12-08-17
Work Began00-00-00
Work Completed
Time Computed01-07-18
Contract Working Days54
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
THE LANE CONSTRUCTION CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 0133-08-035
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11173203
Totals1069536.550.000.000.0

CountyARCHER
HighwayUS 277
From2.083 MILES WEST OF FM 2846
To1.69 MILES WEST OF FM 368
CSJ0156-05-049
Proj IDNH 1302(006)
Work TypeWIDEN NON-FREEWAY
 
4.00514393280.5713775202.6196.5
Work Order06-05-15
Work Began06-18-15
Work Completed
Time Computed06-21-15
Contract Working Days313
Addl Days Granted33
Working Days Charged439
Percent Time Used126
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0156-05-049
W.S. CONSTRUCTION COMPANY (11.44)
ALTUS TRAFFIC MANAGEMENT LLC (0.19)
BARRICADES UNLIMITED (0.94)
MARCOM"S MOWING SERVICE, LLC (0.39)
WEST TEXAS RUMBLE STRIP (0.02)
ZACK BURKETT CO. (24.93)
SPIRES LANDSCAPING, INC. (0.40)
ANALYTICAL TECHNOLOGY CONSULTANTS, INC. (2.95)
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC. (0.07)
Contract #04153007
Totals14393280.5726338.0713775202.6196.5

CountyWICHITA
HighwayIH 44
From0.023 MI. S OF SH 240
ToOKLAHOMA STATE LINE
CSJ0156-07-109
Proj IDSTP 1702(401)HES
Work TypeHAZARD ELIMINATION SAFETY
 
2.5001167403.50686032.5058.7
Work Order07-20-17
Work Began10-11-17
Work Completed
Time Computed08-19-17
Contract Working Days85
Addl Days Granted0
Working Days Charged52
Percent Time Used61
Contractor(s)
HJC FARMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0156-07-109
CONTRACTORS SERVICE COMPANY (0.85)
AARON CONCRETE CONTRACTORS, L.P. (6.60)
W.S. CONSTRUCTION COMPANY (12.69)
Contract #06173038
Totals1167403.50226312.00686032.5058.7

CountyMONTAGUE
HighwaySH 59
FromFM 1758
ToMILL STREET
CSJ0239-02-037
Proj IDSTP 2018(557)
Work TypeREHABILITATION OF EXISTING ROAD
 
1.8671182793.980.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days60
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
THE LANE CONSTRUCTION CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 0239-02-037
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02183006
Totals1182793.980.000.000.0

CountyCOOKE
HighwayFM 51
FromELM FORK TRINITY RIVER
ToONE HORSE LANE
CSJ0312-01-078
Proj IDSTP 2017(403)
Work TypeREHABILITATION OF EXISTING ROAD
 
0.467706189.82543711.2876.9
Work Order05-18-17
Work Began09-21-17
Work Completed
Time Computed06-17-17
Contract Working Days102
Addl Days Granted10
Working Days Charged42
Percent Time Used37
Contractor(s)
JAGOE-PUBLIC COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0312-01-078
WOLFE CONSTRUCTION GROUP, INC. (1.85)
COMEN ENTERPRISE LLC (4.99)
TOTAL HIGHWAY MAINTENANCE, LLC (1.05)
NORTH TEXAS TRAFFIC SYSTEMS CONSTRUCTION, LTD. (8.47)
ALTUS TRAFFIC MANAGEMENT LLC (0.63)
GOLDEN TREE MAINTENANCE (0.84)
W.O.E. CONSTRUCTION (0.60)
Contract #04173233
Totals706189.82104665.63543711.2876.9

page 1 | page 2