Monthly Local Let Maintenance Report For Tyler District As Of Jan 10, 2018 Page 2 Of 4

Last Update: Wednesday, January 10, 2018
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyRUSK
HighwaySH0064
FromHENDERSON MTCE. SECTION
ToRUSK CO.
CSJ6303-86-001
Proj IDSUP - 630386001
Work TypeLITTER PICK UP
 
0.001373499.73145551.6338.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-16
Work Completed
Time Computed00-00-00
Contract Working Days1,095
Addl Days Granted0
Working Days Charged487
Percent Time Used44
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6303-86-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07161045
Totals373499.730.00145551.6338.9

CountyCHEROKEE
HighwayUS0069
FromCROSS STRUCTURE TRM 398+1.551 US 69
ToCROSS STRUCTURE TRM 322+1.041 FM 59
CSJ6305-76-001
Proj IDRMC - 630576001
Work TypeCULVERT REPAIR
 
0.00160270.0053650.0090.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-19-17
Work Completed
Time Computed00-00-00
Contract Working Days38
Addl Days Granted0
Working Days Charged40
Percent Time Used105
Contractor(s)
HIGHWAY 19 CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 6305-76-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07171001
Totals60270.000.0053650.0090.9

CountyVAN ZANDT
HighwaySH0064
FromVARIOUS LOCATIONS IN
ToVAN ZANDT COUNTY
CSJ6307-33-001
Proj IDRMC - 630733001
Work TypeTREE REMOVAL
 
0.001209992.00184851.0088.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began03-08-17
Work Completed
Time Computed00-00-00
Contract Working Days255
Addl Days Granted255
Working Days Charged210
Percent Time Used41
Contractor(s)
CATOCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6307-33-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09161002
Totals209992.0051064.00184851.0088.0

CountyCHEROKEE
HighwayUS0079
FromVARIOUS ROADWAYS IN
ToCHEROKEE COUNTY
CSJ6307-34-001
Proj IDRMC - 630734001
Work TypeTREE REMOVAL
 
0.001215004.00281651.0099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began01-03-17
Work Completed
Time Computed00-00-00
Contract Working Days255
Addl Days Granted255
Working Days Charged261
Percent Time Used51
Contractor(s)
SG COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6307-34-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09161003
Totals215004.0022225.00281651.0099.9

CountySMITH
HighwayUS0069
FromVARIOUS LOCATIONS IN
ToTHE TYLER DISTRICT
CSJ6307-37-001
Proj IDRMC - 630737001
Work TypeILLUMINATION MAINTENANCE
 
0.00177577.7550267.8164.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began02-21-17
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted365
Working Days Charged334
Percent Time Used45
Contractor(s)
TEXAS TRAFFIC CONTROL SYSTEMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6307-37-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10161001
Totals77577.752750.0050267.8164.7

CountySMITH
HighwayUS0271
From.041 MILES NORTH OF FM 14
ToUS 271
CSJ6308-56-001
Proj IDRMC - 630856001
Work TypeHEADWALL EXTENSION
 
0.040126538.22126546.7899.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began03-27-17
Work Completed
Time Computed00-00-00
Contract Working Days64
Addl Days Granted0
Working Days Charged58
Percent Time Used90
Contractor(s)
WEST TEXAS REBAR PLACERS INC.
SUBCONTRACTOR(S) FOR CCSJ: 6308-56-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12161010
Totals126538.220.00126546.7899.9

CountySMITH
HighwaySH0110
FromVARIOUS ROADWAYS
ToIN SMITH COUNTY
CSJ6308-85-001
Proj IDRMC - 630885001
Work TypeROW MOWING
 
0.001201465.23146712.5772.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began06-12-17
Work Completed
Time Computed00-00-00
Contract Working Days51
Addl Days Granted0
Working Days Charged79
Percent Time Used154
Contractor(s)
THE GUARANTEE COMPANY OF NORTH AMERICA USA
SUBCONTRACTOR(S) FOR CCSJ: 6308-85-001
SERVIN MOWING (32.37)
JHE LANDSCAPES, INC. (43.25)
JASCO (25.31)
Contract #12161001
Totals201465.230.00146712.5772.8

CountySMITH
HighwaySH0031
FromVARIOUS LOCATIONS IN
ToSMITH AND CHEROKEE COUNTIES
CSJ6309-40-001
Proj IDRMC - 630940001
Work TypeCURB INLET REPAIR
 
0.001172719.00107850.6483.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began04-03-17
Work Completed
Time Computed00-00-00
Contract Working Days84
Addl Days Granted0
Working Days Charged145
Percent Time Used172
Contractor(s)
IIPL USA LLC
SUBCONTRACTOR(S) FOR CCSJ: 6309-40-001
SJ&J CONSTRUCTION, LLC (12.96)
Contract #12161014
Totals172719.000.00107850.6483.2

CountyRUSK
HighwayFM0225
FromHENDERSON MTCE SECTION OFFICE
ToFM 225 RUSK CO
CSJ6311-48-001
Proj IDSUP - 631148001
Work TypeLAWN MTCE.
 
0.01010352.363984.2138.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began11-02-16
Work Completed
Time Computed00-00-00
Contract Working Days669
Addl Days Granted0
Working Days Charged426
Percent Time Used63
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6311-48-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10161030
Totals10352.36280.033984.2138.4

CountyRUSK
HighwayUS0259
FromUS 259 AND SH 79
ToUS 259 AND SH 322
CSJ6311-49-001
Proj IDSUP - 631149001
Work TypeLANDSCAPE MAINTENANCE
 
0.00139600.009240.0023.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began12-01-16
Work Completed
Time Computed00-00-00
Contract Working Days669
Addl Days Granted0
Working Days Charged426
Percent Time Used63
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6311-49-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10161031
Totals39600.000.009240.0023.3

CountyRUSK
HighwaySH0064
FromSH 64W, US 259N, US 259S, SH 43N
ToHENDERSON MTCE SECTION
CSJ6311-50-001
Proj IDSUP - 631150001
Work TypePICNIC AREA MTCE.
 
0.01053472.0042850.1680.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began11-01-16
Work Completed
Time Computed00-00-00
Contract Working Days669
Addl Days Granted0
Working Days Charged426
Percent Time Used63
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6311-50-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10161032
Totals53472.002789.4442850.1680.1

CountyRUSK
HighwayFM0225
FromHENDERSON MTCE. OFFICE
ToRUSK CO
CSJ6311-51-001
Proj IDSUP - 631151001
Work TypeJANITORIAL MTCE.
 
0.01019113.7210454.8254.6
Work Order11-30-16
Work Began12-01-16
Work Completed
Time Computed12-01-16
Contract Working Days639
Addl Days Granted0
Working Days Charged396
Percent Time Used61
Contractor(s)
TIBH INDUSTRIES, INC.
WOODCREEK OUTREACH REHABILITATION DEVELOPMENT
SUBCONTRACTOR(S) FOR CCSJ: 6311-51-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11161031
Totals19113.72641.4010454.8254.6

CountyGREGG
HighwaySL0281
FromLONGVIEW MTCE.
ToLONGVIEW AO OFFICE
CSJ6311-52-001
Proj IDSUP - 631152001
Work TypeJANITORIAL MTCE.
 
0.00156956.8630968.7154.3
Work Order11-30-16
Work Began12-01-16
Work Completed
Time Computed12-01-16
Contract Working Days639
Addl Days Granted0
Working Days Charged396
Percent Time Used61
Contractor(s)
TIBH INDUSTRIES, INC.
WOODCREEK OUTREACH REHABILITATION DEVELOPMENT
SUBCONTRACTOR(S) FOR CCSJ: 6311-52-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11161030
Totals56956.864072.5730968.7154.3

CountyHENDERSON
HighwaySH0031
FromVARIOUS ROADWAYS IN
ToHENDERSON COUNTY
CSJ6312-91-001
Proj IDRMC - 631291001
Work TypeDEBRIS REMOVAL
 
0.01055017.0038832.0070.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began06-15-17
Work Completed
Time Computed00-00-00
Contract Working Days255
Addl Days Granted0
Working Days Charged146
Percent Time Used57
Contractor(s)
CROSS PLUS CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6312-91-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03171001
Totals55017.003201.0038832.0070.5

CountyHENDERSON
HighwaySH0031
FromVARIOUS ROADWAYS IN
ToHENDERSON AND ANDERSON COUNTIES
CSJ6314-34-001
Proj IDRMC - 631434001
Work TypeGUARDRAIL REPAIR
 
0.010128034.0027450.0021.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began10-19-17
Work Completed
Time Computed00-00-00
Contract Working Days255
Addl Days Granted0
Working Days Charged73
Percent Time Used28
Contractor(s)
CATOCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6314-34-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06171001
Totals128034.005890.0027450.0021.4

CountyGREGG
HighwayUS0259
FromVARIOUS ROADWAYS IN
ToGREGG AND RUSK COUNTIES
CSJ6314-35-001
Proj IDRMC - 631435001
Work TypeGUARDRAIL REPAIR
 
0.010183430.0035795.0019.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-08-17
Work Completed
Time Computed00-00-00
Contract Working Days255
Addl Days Granted0
Working Days Charged83
Percent Time Used32
Contractor(s)
IIPL USA LLC
SUBCONTRACTOR(S) FOR CCSJ: 6314-35-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06171002
Totals183430.00980.0035795.0019.5

CountyWOOD
HighwayUS0080
FromVARIOUS ROADWAYS IN
ToWOOD AND VAN ZANDT COUNTIES
CSJ6314-36-001
Proj IDRMC - 631436001
Work TypeGUARDRAIL REPAIR
 
0.01079896.002900.003.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days255
Addl Days Granted0
Working Days Charged78
Percent Time Used30
Contractor(s)
IIPL USA LLC
SUBCONTRACTOR(S) FOR CCSJ: 6314-36-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06171003
Totals79896.002900.002900.003.6

CountySMITH
HighwayUS0069
FromVARIOUS ROADWAYS IN
ToSMITH AND CHEROKEE COUNTIES
CSJ6314-37-001
Proj IDRMC - 631437001
Work TypeGUARDRAIL REPAIR
 
0.010198195.0055394.0027.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-22-17
Work Completed
Time Computed00-00-00
Contract Working Days255
Addl Days Granted0
Working Days Charged75
Percent Time Used29
Contractor(s)
IIPL USA LLC
SUBCONTRACTOR(S) FOR CCSJ: 6314-37-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06171004
Totals198195.0016565.0055394.0027.9

CountySMITH
HighwaySL0323
FromSPEC. JOBS OFFICE
ToFORMERLY N. TYLER OFFICE
CSJ6317-70-001
Proj IDSUP - 631770001
Work TypeLAWN MTCE.
 
0.00112800.001575.0012.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-17
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged122
Percent Time Used16
Contractor(s)
TIBH INDUSTRIES, INC.
ANDREWS DIVERSIFIED INDUSTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6317-70-001
ANDREWS DIVERSIFIED INDUSTRIES (100.00)
Contract #07171030
Totals12800.000.001575.0012.3

CountySMITH
HighwayIH0020
FromVAN ZANDT, SMITH & GREGG CO.
ToIH 20
CSJ6317-71-001
Proj IDSUP - 631771001
Work TypeLITTER REMOVAL
 
0.001163060.445913.703.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-17
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged122
Percent Time Used16
Contractor(s)
TIBH INDUSTRIES, INC.
ANDREWS DIVERSIFIED INDUSTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6317-71-001
ANDREWS DIVERSIFIED INDUSTRIES (100.00)
Contract #07171031
Totals163060.440.005913.703.6

page 1 | page 2 | page 3 | page 4