Monthly Local Let Maintenance Report For Tyler District As Of Nov 22, 2017 Page 1 Of 4

Last Update: Wednesday, November 22, 2017
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyHENDERSON
HighwayUS0175
FromVARIOUS ROADWAYS IN THE
ToATHENS MAINTENANCE SECTION
CSJ6272-05-001
Proj IDRMC - 627205001
Work TypePAINT
 
0.01023318.75379608.72100.0
CountyVAN ZANDT
HighwaySH0019
FromVARIOUS ROADWAYS IN
ToTHE CANTON MAINTENANCE SECTION
CSJ6272-05-002
Proj IDRMC - 627205002
Work TypePAINT
 
0.01023318.7559964.01100.0
CountyRUSK
HighwayUS0259
FromVARIOUS ROADWAYS IN THE
ToHENDERSON MAINTENANCE SECTIONN
CSJ6272-05-003
Proj IDRMC - 627205003
Work TypePAINT
 
0.01023318.7560837.79100.0
CountyCHEROKEE
HighwayUS0079
FromVARIOUS ROADWAYS IN THE
ToJACKSONVILLE MAINTENANCE SECTION
CSJ6272-05-004
Proj IDRMC - 627205004
Work TypePAINT
 
0.01012009.3866767.05100.0
CountyGREGG
HighwaySH0031
FromVARIOUS ROADWAYS IN THE
ToLONGVIEW MAINTENANCE SECTION
CSJ6272-05-005
Proj IDRMC - 627205005
Work TypePAINT
 
0.01023318.7549248.01100.0
CountyWOOD
HighwayUS0080
FromVARIOUS ROADWAYS IN THE
ToMINEOLA MAINTENACE SECTION
CSJ6272-05-006
Proj IDRMC - 627205006
Work TypePAINT
 
0.01023318.7535210.94100.0
CountyANDERSON
HighwayUS0287
FromVARIOUS ROADWAYS IN THE
ToPALESINE MAINTENANCE SECTION
CSJ6272-05-007
Proj IDRMC - 627205007
Work TypePAINT
 
0.01023318.758365.21100.0
CountySMITH
HighwaySH0110
FromVARIOUS ROADWAYS IN THE
ToTYLER MAINTENANCE SECTION
CSJ6272-05-008
Proj IDRMC - 627205008
Work TypePAINT
 
0.01023318.7548327.90100.0
CountyCHEROKEE
HighwayUS0069
FromVARIOUS ROADWAYS IN THE
ToRUSK MAINTENANCE SECTION
CSJ6272-05-009
Proj IDRMC - 627205009
Work TypePAINT
 
0.01012009.3834335.47100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-14-14
Work Began09-25-14
Work Completed09-15-16
Time Computed09-01-14
Contract Working Days255
Addl Days Granted255
Working Days Charged509
Percent Time Used99
Contractor(s)
STRIPING TECHNOLOGY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6272-05-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06141001
Totals187250.010.00742665.10100.0

CountyHENDERSON
HighwaySH0031
FromVARIOUS LOCATIONS IN_THE
ToATHENS AND PALESTINE SECTIONS
CSJ6285-89-001
Proj IDRMC - 628589001
Work TypeGUARDRAIL REPAIR
 
0.010123362.00272014.0099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-15
Work Completed
Time Computed00-00-00
Contract Working Days255
Addl Days Granted255
Working Days Charged510
Percent Time Used100
Contractor(s)
CATOCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6285-89-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06151001
Totals123362.000.00272014.0099.9

CountyGREGG
HighwayUS0259
FromVARIOUS LOCATIONS IN THE
ToLONGVIEW AND HENDERSON SECTIONS
CSJ6285-91-001
Proj IDRMC - 628591001
Work TypeGUARDRAIL REPAIR
 
0.010107213.00363445.50100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-15
Work Completed08-31-17
Time Computed00-00-00
Contract Working Days255
Addl Days Granted255
Working Days Charged510
Percent Time Used100
Contractor(s)
CATOCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6285-91-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06151003
Totals107213.000.00363445.50100.0

CountySMITH
HighwayUS0069
FromVARIOUS LOCATIONS IN THE
ToTYLER AND JACKSONVILLE SECTIONS
CSJ6285-92-001
Proj IDRMC - 628592001
Work TypeGUARDRAIL REPAIR
 
0.010105963.00453562.00100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-15
Work Completed09-12-17
Time Computed00-00-00
Contract Working Days255
Addl Days Granted255
Working Days Charged509
Percent Time Used99
Contractor(s)
CATOCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6285-92-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06151004
Totals105963.000.00453562.00100.0

CountySMITH
HighwayFM0757
FromFM 757 AND SL 323
ToIN SMITH COUNTY
CSJ6288-59-001
Proj IDRMC - 628859001
Work TypeCULVERT REPAIR
 
0.001174696.0096691.56100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-12-16
Work Completed09-01-17
Time Computed00-00-00
Contract Working Days34
Addl Days Granted0
Working Days Charged157
Percent Time Used461
Contractor(s)
DEANGELO BROTHERS LLC
SUBCONTRACTOR(S) FOR CCSJ: 6288-59-001
NORTH TEXAS MAINTENANCE, INC. (100.00)
Contract #01161002
Totals174696.000.0096691.56100.0

CountyHENDERSON
HighwaySH0031
FromVARIOUS ROADWAYS IN THE
ToATHENS MAINTENANCE SECTION
CSJ6288-60-001
Proj IDRMC - 628860001
Work TypeTREE REMOVAL
 
0.001172950.00320914.0099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-15
Work Completed
Time Computed00-00-00
Contract Working Days255
Addl Days Granted255
Working Days Charged482
Percent Time Used94
Contractor(s)
PATTERSON'S COMPLETE TREE SERVICE LLC
SUBCONTRACTOR(S) FOR CCSJ: 6288-60-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09151005
Totals172950.0023764.00320914.0099.9

CountyRUSK
HighwayUS0079
FromVARIOUS ROADWAYS IN THE
ToHENDERSON MAINTENANCE SECTION
CSJ6288-62-001
Proj IDRMC - 628862001
Work TypeTREE REMOVAL
 
0.001213375.00359420.00100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began10-26-15
Work Completed11-01-17
Time Computed00-00-00
Contract Working Days255
Addl Days Granted255
Working Days Charged509
Percent Time Used99
Contractor(s)
PATTERSON'S COMPLETE TREE SERVICE LLC
SUBCONTRACTOR(S) FOR CCSJ: 6288-62-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09151002
Totals213375.0017620.00359420.00100.0

CountyRUSK
HighwayUS0079
FromVARIOUS ROADWAYS IN
ToRUSK AND CHEROKEE COUNTIES
CSJ6290-48-001
Proj IDEMC - 629048001
Work TypeEMERGENCY DEBRIS & TREE REMOVAL
 
0.010435655.003070764.75100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began06-26-15
Work Completed08-11-15
Time Computed00-00-00
Contract Working Days52
Addl Days Granted0
Working Days Charged33
Percent Time Used63
Contractor(s)
DREWERY CONSTRUCTION COMPANY, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6290-48-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06151044
Totals435655.000.003070764.75100.0

CountyGREGG
HighwaySH0031
FromVARIOUS ROADWAYS IN
ToGREGG COUNTY
CSJ6294-86-001
Proj IDRMC - 629486001
Work TypeTREE REMOVAL
 
0.001159225.00200445.0099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began05-16-16
Work Completed
Time Computed00-00-00
Contract Working Days255
Addl Days Granted255
Working Days Charged375
Percent Time Used73
Contractor(s)
DREWERY CONSTRUCTION COMPANY, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6294-86-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11151001
Totals159225.000.00200445.0099.9

CountyHENDERSON
HighwaySH0031
FromVARIOUS LOCATIONS
ToIN THE TYLER DISTRICT
CSJ6299-58-001
Proj IDRMC - 629958001
Work TypeSHORT LINE THERMO
 
0.001288607.50280201.0597.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-13-16
Work Completed
Time Computed00-00-00
Contract Working Days255
Addl Days Granted110
Working Days Charged352
Percent Time Used96
Contractor(s)
STRIPING TECHNOLOGY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6299-58-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05161002
Totals288607.500.00280201.0597.0

CountyHENDERSON
HighwaySH0019
FromVARIOUS ROADWAYS IN
ToTHE TYLER DISTRICT
CSJ6300-22-001
Proj IDRMC - 630022001
Work TypePAINT
 
0.001239245.00626637.0299.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-22-16
Work Completed
Time Computed00-00-00
Contract Working Days255
Addl Days Granted255
Working Days Charged285
Percent Time Used55
Contractor(s)
STRIPING TECHNOLOGY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6300-22-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04161003
Totals239245.0024245.94626637.0299.9

CountyVAN ZANDT
HighwayIH0020
FromIH-20 VARIOUS LOCATIONS
ToIN VAN ZANDT COUNTY
CSJ6301-83-001
Proj IDBPM - 630183001
Work TypeBRIDGE PREVENTIVE MAINTENANCE
 
0.001171979.00157130.51100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began07-28-17
Work Completed09-08-17
Time Computed00-00-00
Contract Working Days82
Addl Days Granted0
Working Days Charged77
Percent Time Used93
Contractor(s)
RED BARON BUILDING COMPANY, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 6301-83-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12161011
Totals171979.000.00157130.51100.0

CountySMITH
HighwaySL0323
FromSL 323 IN
ToSMITH COUNTY
CSJ6303-40-001
Proj IDRMC - 630340001
Work TypeSLOPE FAILURE
 
0.100182290.00461048.79100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began12-05-16
Work Completed10-02-17
Time Computed00-00-00
Contract Working Days40
Addl Days Granted3
Working Days Charged41
Percent Time Used95
Contractor(s)
FNH CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6303-40-001
NEWSTAR DRILLING, INC (2.22)
Contract #08161001
Totals182290.000.00461048.79100.0

CountyHENDERSON
HighwaySH0031
FromATHENS MTCE. SECTION
ToHENDERSON CO.
CSJ6303-70-001
Proj IDSUP - 630370001
Work TypeLANDSCAPE ROW MTCE.
 
0.01014898.0012033.0080.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-16
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged426
Percent Time Used58
Contractor(s)
TIBH INDUSTRIES, INC.
ANDREWS DIVERSIFIED INDUSTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6303-70-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07161030
Totals14898.001146.0012033.0080.7

CountyHENDERSON
HighwaySH0031
FromATHENS MTCE. OFFICE
ToHENDERSON CO
CSJ6303-71-001
Proj IDSUP - 630371001
Work TypeLAWN MTCE.
 
0.01016782.008495.0050.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-16
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged426
Percent Time Used58
Contractor(s)
TIBH INDUSTRIES, INC.
ANDREWS DIVERSIFIED INDUSTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6303-71-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07161031
Totals16782.00765.508495.0050.6

CountyGREGG
HighwaySL0281
FromLONGVIEW MTCE. OFFICE
ToGREGG CO
CSJ6303-72-001
Proj IDSUP - 630372001
Work TypeLAWN MTCE
 
0.01031110.0019065.0061.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-16
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged426
Percent Time Used58
Contractor(s)
TIBH INDUSTRIES, INC.
ANDREWS DIVERSIFIED INDUSTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6303-72-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07161032
Totals31110.001230.0019065.0061.2

CountySMITH
HighwayIH0020
FromIH 20 EAST & WEST DERRICK PARK
ToSH 31 @ FM 2661
CSJ6303-73-001
Proj IDSUP - 630373001
Work TypePICNIC AREA MTCE.
 
0.010124980.0076579.0061.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-16
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged426
Percent Time Used58
Contractor(s)
TIBH INDUSTRIES, INC.
ANDREWS DIVERSIFIED INDUSTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6303-73-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07161033
Totals124980.004123.0076579.0061.2

CountySMITH
HighwayIH0020
FromIH 20 @ US 69 &
ToIH 20 @ US 271
CSJ6303-74-001
Proj IDSUP - 630374001
Work TypeTRAFFIC ISLAND LANDSCAPE MTCE
 
0.01029450.0020630.5070.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-16
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged426
Percent Time Used58
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6303-74-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07161034
Totals29450.00775.0020630.5070.0

CountyWOOD
HighwayUS0080
FromUS 80(2), US 69, FM 2088
ToSH 37(2)
CSJ6303-75-001
Proj IDSUP - 630375001
Work TypePICNIC AREA MTCE
 
0.010122429.0478720.4064.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-16
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged426
Percent Time Used58
Contractor(s)
TIBH INDUSTRIES, INC.
WOODCREEK OUTREACH REHABILITATION DEVELOPMENT
SUBCONTRACTOR(S) FOR CCSJ: 6303-75-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07161035
Totals122429.044899.6578720.4064.2

CountyWOOD
HighwaySL0564
FromMINEOLA AO & MTCE OFFICE
ToSL 564, WOOD CO
CSJ6303-76-001
Proj IDSUP - 630376001
Work TypeLAWN MTCE
 
0.01026367.0017232.3865.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-16
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged426
Percent Time Used58
Contractor(s)
TIBH INDUSTRIES, INC.
WOODCREEK OUTREACH REHABILITATION DEVELOPMENT
SUBCONTRACTOR(S) FOR CCSJ: 6303-76-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07161036
Totals26367.00861.1017232.3865.3

page 1 | page 2 | page 3 | page 4