Monthly State Let Maintenance Report For Houston District As Of Feb 09, 2018 Page 8 Of 9

Last Update: Friday, February 09, 2018
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyHARRIS
HighwaySL0008
FromVARIOUS HWYS IN SOUTH HARRIS
ToVARIOUS HWYS IN SOUTH HARIS
CSJ6312-90-001
Proj IDRMC - 631290001
Work TypeASPHALT PAVEMENT REPAIR
 
0.001639400.000.000.0
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed05-15-17
Contract Working Days730
Addl Days Granted0
Working Days Charged257
Percent Time Used35
Contractor(s)
MAIN LANE INDUSTRIES LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6312-90-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03174206
Totals639400.000.000.000.0

CountyBRAZORIA
HighwaySH0288
FromVARIOUS HWYS IN N BRAZORIA COUNTY
ToVARIOUS HWYS IN N BRAZORIA COUNTY
CSJ6312-92-001
Proj IDRMC - 631292001
Work TypeMOWING HIGHWAY ROW (NORTH)
 
0.001466316.37192500.9741.2
Work Order06-05-17
Work Began06-05-17
Work Completed
Time Computed06-05-17
Contract Working Days176
Addl Days Granted0
Working Days Charged74
Percent Time Used42
Contractor(s)
YELLOWSTONE LANDSCAPE - CENTRAL, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6312-92-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03174207
Totals466316.3727467.99192500.9741.2

CountyBRAZORIA
HighwayFM0521
FromVARIOUS FM ROADS IN BRAZORIA COUNTY
ToVARIOUS FM ROADS IN BRAZORIA COUNTY
CSJ6312-95-001
Proj IDRMC - 631295001
Work TypeMOWING HIGHWAY ROW (S FMS)
 
0.001383733.31188863.0349.2
Work Order05-15-17
Work Began05-15-17
Work Completed
Time Computed05-15-17
Contract Working Days143
Addl Days Granted0
Working Days Charged69
Percent Time Used48
Contractor(s)
RELIANT SAND AND CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6312-95-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03174005
Totals383733.3144979.53188863.0349.2

CountyHARRIS
HighwaySH0249
FromVARIOUS HWYS IN NORTH HARRIS COUNTY
ToVARIOUS HWYS IN NORTH HARRIS COUNTY
CSJ6313-24-001
Proj IDRMC - 631324001
Work TypeROADSIDE MOWING
 
0.001433156.1684398.8019.4
Work Order10-26-17
Work Began00-00-00
Work Completed
Time Computed10-30-17
Contract Working Days127
Addl Days Granted21
Working Days Charged20
Percent Time Used13
Contractor(s)
YELLOWSTONE LANDSCAPE - CENTRAL, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6313-24-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07174217
Totals433156.1627439.9284398.8019.4

CountyMONTGOMERY
HighwayIH0069
FromVARIOUS HWYS IN MONTGOMERY COUNTY
ToVARIOUS HWYS IN MONTGOMERY COUNTY
CSJ6313-51-001
Proj IDRMC - 631351001
Work TypeASPHALT PAVEMENT REPAIR
 
0.001389100.000.000.0
Work Order08-11-17
Work Began08-15-17
Work Completed
Time Computed08-15-17
Contract Working Days365
Addl Days Granted0
Working Days Charged163
Percent Time Used44
Contractor(s)
MAIN LANE INDUSTRIES LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6313-51-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05174005
Totals389100.000.000.000.0

CountyBRAZORIA
HighwaySH0288
FromVARIOUS HWYS IN BRAZORIA COUNTY
ToVARIOUS HWYS IN BRAZORIA COUNTY
CSJ6314-52-001
Proj IDRMC - 631452001
Work TypeCLEANING & SWEEPING HIGHWAYS
 
0.0011298800.00295550.0022.7
Work Order00-00-00
Work Began08-01-17
Work Completed
Time Computed08-01-17
Contract Working Days730
Addl Days Granted0
Working Days Charged176
Percent Time Used24
Contractor(s)
PANNELL INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6314-52-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05174205
Totals1298800.0038130.00295550.0022.7

CountyHARRIS
HighwaySL0008
FromVARIOUS HWYS IN SOUTH HARRIS COUNTY
ToVARIOUS HWYS IN SOUTH HARRIS COUNTY
CSJ6314-83-001
Proj IDRMC - 631483001
Work TypeGUARDRAIL REPAIR
 
0.001708302.0021843.503.0
Work Order00-00-00
Work Began11-01-17
Work Completed
Time Computed11-01-17
Contract Working Days730
Addl Days Granted0
Working Days Charged58
Percent Time Used7
Contractor(s)
ISI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6314-83-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06174005
Totals708302.005371.5021843.503.0

CountyHARRIS
HighwayIH0610
FromVARIOUS HWYS IN HOUSTON DISTRICT
ToVARIOUS HWYS IN HOUSTON DISTRICT
CSJ6315-05-001
Proj IDRMC - 631505001
Work TypeMNT OF ILLUMINATION SYS
 
0.0011982955.00151466.257.6
Work Order11-02-17
Work Began11-07-17
Work Completed
Time Computed11-06-17
Contract Working Days730
Addl Days Granted0
Working Days Charged80
Percent Time Used10
Contractor(s)
VACA UNDERGROUND UTILITIES INC
SUBCONTRACTOR(S) FOR CCSJ: 6315-05-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08174204
Totals1982955.0066085.75151466.257.6

CountyBRAZORIA
HighwaySH0288
FromVARIOUS HWYS IN S BRAZORIA COUNTY
ToVARIOUS HWYS IN S BRAZORIA COUNTY
CSJ6315-36-001
Proj IDRMC - 631536001
Work TypeROADSIDE MOWING - STATE HIGWAYS (SOUTH)
 
0.001660983.5382622.9412.4
Work Order00-00-00
Work Began11-01-17
Work Completed
Time Computed11-01-17
Contract Working Days221
Addl Days Granted0
Working Days Charged17
Percent Time Used7
Contractor(s)
YELLOWSTONE LANDSCAPE - CENTRAL, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6315-36-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06174204
Totals660983.530.0082622.9412.4

CountyHARRIS
HighwayIH0010
FromVARIOUS HIGHWAYS IN CENTRAL HARRIS CO.
To.
CSJ6315-61-001
Proj IDRMC - 631561001
Work TypeGENERAL MAINTENANCE IH 10, ETC.
 
0.0014321861.952024607.3146.8
Work Order00-00-00
Work Began09-05-17
Work Completed
Time Computed09-05-17
Contract Working Days365
Addl Days Granted0
Working Days Charged109
Percent Time Used29
Contractor(s)
ISI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6315-61-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07174017
Totals4321861.95375602.732024607.3146.8

CountyWALLER
HighwayUS0290
FromVARIOUS HWYS IN WALLER COUNTY
ToVARIOUS HWYS IN WALLER COUNTY
CSJ6316-12-001
Proj IDRMC - 631612001
Work TypeASPHALT PAVEMENT REPAIR
 
0.001521960.000.000.0
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed12-11-17
Contract Working Days365
Addl Days Granted0
Working Days Charged50
Percent Time Used13
Contractor(s)
MAIN LANE INDUSTRIES LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6316-12-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08174006
Totals521960.000.000.000.0

CountyHARRIS
HighwayIH0610
FromIH 610
To.
CSJ6316-22-001
Proj IDRMC - 631622001
Work TypeGENERL MAINTENANCE_IH 610
 
0.0014111633.301450825.8235.2
Work Order00-00-00
Work Began09-05-17
Work Completed
Time Computed09-05-17
Contract Working Days365
Addl Days Granted0
Working Days Charged109
Percent Time Used29
Contractor(s)
ISI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6316-22-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07174218
Totals4111633.30202663.021450825.8235.2

CountyHARRIS
HighwayIH0610
FromVARIOUS HWYS IN HOUSTON DISTRICT
ToVARIOUS HWYS IN HOUSTON DISTRICT
CSJ6316-24-001
Proj IDRMC - 631624001
Work TypePREV MNT OF SGNL EQUIP
 
0.0011084085.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
VACA UNDERGROUND UTILITIES INC
SUBCONTRACTOR(S) FOR CCSJ: 6316-24-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01184204
Totals1084085.000.000.000.0

CountyHARRIS
HighwayUS0059
FromVARIOUS COUNTIES IN THE HOUSTON DRISTICT
ToVARIOUS COUNTIES IN THE HOUSTON DRISTICT
CSJ6316-26-001
Proj IDRMC - 631626001
Work TypeDEBRIS REMOVAL AND DISPOSAL
 
0.0011873100.00238149.90100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-23-17
Work Completed01-11-18
Time Computed00-00-00
Contract Working Days85
Addl Days Granted0
Working Days Charged63
Percent Time Used74
Contractor(s)
T.F.R. ENTERPRISES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6316-26-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04174013
Totals1873100.006275.70238149.90100.0

CountyHARRIS
HighwayIH0610
FromVARIOUS HWYS IN HOUSTON DISTRICT
ToVARIOUS HWYS IN HOUSTON DISTRICT
CSJ6316-49-001
Proj IDRMC - 631649001
Work TypeCOMMUNICATION CABLE
 
0.001535958.400.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-24-18
Work Began01-30-18
Work Completed
Time Computed02-01-18
Contract Working Days240
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
THIRD COAST SERVICES LLC
SUBCONTRACTOR(S) FOR CCSJ: 6316-49-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11174203
Totals535958.400.000.000.0

CountyHARRIS
HighwayIH0045
FromSH 87
ToSOUTHERN STREET
CSJ6316-59-001
Proj IDRMC - 631659001
Work TypeGENERAL MAINTENANCE OF IH 45
 
40.1923379711.00732003.0121.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began08-13-17
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged145
Percent Time Used39
Contractor(s)
ROY JORGENSEN ASSOCIATES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6316-59-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06174210
Totals3379711.00290661.52732003.0121.6

CountyMONTGOMERY
HighwayIH0045
FromWALKER COUNTY LINE TO STOKES STREET
ToLOCATED IN HARRIS COUNTY
CSJ6316-65-001
Proj IDRMC - 631665001
Work TypeGENERAL MAINTENANCE OF IH 45
 
0.0013107757.0087286.002.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-01-17
Work Began08-01-17
Work Completed
Time Computed08-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged151
Percent Time Used41
Contractor(s)
CROSBY RD CONSTRUCTION INC
SUBCONTRACTOR(S) FOR CCSJ: 6316-65-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06174012
Totals3107757.000.0087286.002.8

CountyWALLER
HighwayUS0290
FromVARIOUS HIGHWAYS IN WALLER COUNTY
ToVARIOUS HIGHWAYS IN WALLER COUNTY
CSJ6316-70-001
Proj IDRMC - 631670001
Work TypeCLEANING AND SWEEPING HIGHWAYS
 
0.001449173.600.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
SWEEPING SERVICES OF TEXAS - OPERATING, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6316-70-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10174206
Totals449173.600.000.000.0

CountyWALLER
HighwayUS0290
FromVARIOUS HWYS IN WALLER COUNTY
ToVARIOUS HWYS IN WALLER COUNTY
CSJ6317-09-001
Proj IDRMC - 631709001
Work TypeREFLECTIVE PAVEMNT MARKINGS
 
0.001415063.770.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
BATTERSON, LLP
SUBCONTRACTOR(S) FOR CCSJ: 6317-09-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02184007
Totals415063.770.000.000.0

CountyGALVESTON
HighwayFM0517
FromVARIOUS HWYS IN GALVESTON COUNTY
ToVARIOUS HWYS IN GALVESTON COUNTY
CSJ6317-23-001
Proj IDRMC - 631723001
Work TypeDITCH CLEANING AND RESHAPING
 
0.001279200.00174023.7562.3
Work Order00-00-00
Work Began12-05-17
Work Completed
Time Computed12-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged56
Percent Time Used15
Contractor(s)
TEXAS DRAINAGE INC.
SUBCONTRACTOR(S) FOR CCSJ: 6317-23-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10174003
Totals279200.0084234.00174023.7562.3