Monthly State Let Maintenance Report For Houston District As Of Jan 10, 2018 Page 6 Of 9

Last Update: Wednesday, January 10, 2018
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyHARRIS
HighwayIH0610
FromVARIOUS HWYS IN HOUSTON DISTRICT
ToVARIOUS HWYS IN HOUSTON DISTRICT
CSJ6301-89-001
Proj IDRMC - 630189001
Work TypeCOMMUNICATION CABLE
 
0.001802175.00802174.6099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-23-17
Work Began02-01-17
Work Completed
Time Computed02-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged211
Percent Time Used57
Contractor(s)
THIRD COAST SERVICES LLC
SUBCONTRACTOR(S) FOR CCSJ: 6301-89-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11164020
Totals802175.000.00802174.6099.9

CountyGALVESTON
HighwaySH0146
FromVARIOUS HWYS IN GALVESTON COUNTY
ToVARIOUS HWYS IN GALVESTON COUNTY
CSJ6302-19-001
Proj IDRMC - 630219001
Work TypeGUARDRAIL REPAIR
 
0.001326637.00289686.2088.6
Work Order08-22-16
Work Began09-07-16
Work Completed
Time Computed09-01-16
Contract Working Days365
Addl Days Granted120
Working Days Charged481
Percent Time Used99
Contractor(s)
ISI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6302-19-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07164008
Totals326637.004136.80289686.2088.6

CountyHARRIS
HighwayIH0010
FromVARIOUS HWYS IN EAST HARRIS COUNTY
ToVARIOUS HWYS IN EAST HARRIS COUNTY
CSJ6302-23-001
Proj IDRMC - 630223001
Work TypeCLEANING AND SWEEPING HIGHWAYS
 
0.0011438600.00833469.8857.9
Work Order00-00-00
Work Began09-06-16
Work Completed
Time Computed09-06-16
Contract Working Days730
Addl Days Granted0
Working Days Charged482
Percent Time Used66
Contractor(s)
PANNELL INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6302-23-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07164203
Totals1438600.0063300.00833469.8857.9

CountyHARRIS
HighwaySL0008
FromVARIOUS HWYS IN SOUTH HARRIS COUNTY
ToVARIOUS HWYS IN SOUTH HARRIS COUNTY
CSJ6303-61-001
Proj IDRMC - 630361001
Work TypeBRIDGE MAINTENANCE
 
0.001634776.00401590.4663.2
Work Order00-00-00
Work Began12-01-16
Work Completed
Time Computed12-01-16
Contract Working Days730
Addl Days Granted0
Working Days Charged393
Percent Time Used53
Contractor(s)
MAIN LANE INDUSTRIES LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6303-61-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09164223
Totals634776.000.00401590.4663.2

CountyBRAZORIA
HighwaySH0288
FromVARIOUS HWYS WITHIN BRAZORIA COUNTY
ToVARIOUS HWYS WITHIN BRAZORIA COUNTY
CSJ6304-19-001
Proj IDRMC - 630419001
Work TypeREFL PAV MRKS (LONG LINE)
 
0.001698493.96303904.2543.5
Work Order00-00-00
Work Began04-03-17
Work Completed
Time Computed04-13-17
Contract Working Days730
Addl Days Granted0
Working Days Charged264
Percent Time Used36
Contractor(s)
ROADSAFE TRAFFIC SYSTEMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6304-19-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01174208
Totals698493.9673687.94303904.2543.5

CountyHARRIS
HighwayIH0010
FromVARIOUS HWYS IN EAST HARRIS COUNTY
ToVARIOUS HWYS IN EAST HARRIS COUNTY
CSJ6304-23-001
Proj IDRMC - 630423001
Work TypeASPHALT PAVEMENT REPAIR AND CRACK SEAL
 
0.0011240200.00426294.7734.3
Work Order00-00-00
Work Began01-02-17
Work Completed
Time Computed01-02-17
Contract Working Days730
Addl Days Granted0
Working Days Charged360
Percent Time Used49
Contractor(s)
MAIN LANE INDUSTRIES LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6304-23-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10164005
Totals1240200.0016324.97426294.7734.3

CountyWALLER
HighwayUS0290
FromVARIOUS HWYS IN WALLER COUNTY
ToVARIOUS HWYS IN WALLER COUNTY
CSJ6304-43-001
Proj IDRMC - 630443001
Work TypeASPHALT PAVEMENT REPAIR
 
0.001552700.00729297.4199.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-22-16
Work Began12-01-16
Work Completed
Time Computed12-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged363
Percent Time Used99
Contractor(s)
MAIN LANE INDUSTRIES LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6304-43-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09164224
Totals552700.000.00729297.4199.9

CountyGALVESTON
HighwayFM2004
FromVARIOUS HWYS IN GALVESTON COUNTY
ToVARIOUS HWYS IN GALVESTON COUNTY
CSJ6304-55-001
Proj IDRMC - 630455001
Work TypeREFLECTIVE PAVEMENT MARKERS (LONG LINE)
 
0.001493110.20304194.01100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-08-16
Work Began11-17-16
Work Completed11-14-17
Time Computed11-14-16
Contract Working Days365
Addl Days Granted0
Working Days Charged346
Percent Time Used94
Contractor(s)
STRIPE LINES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6304-55-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09164005
Totals493110.200.00304194.01100.0

CountyWALLER
HighwayFM0362
FromUS 290
ToQUAIL HOLLOW STREET
CSJ6304-84-001
Proj IDRMC - 630484001
Work TypeBASE REP,ACP OVERLAY, SIGNING & PAV MRKS
 
0.660413485.140.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days30
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
JAMES CONSTRUCTION GROUP, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 6304-84-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01184203
Totals413485.140.000.000.0

CountyGALVESTON
HighwaySH0087
FromBOLIVAR FERRY LANDING
ToBOLIVAR FERRY LANDING
CSJ6304-96-001
Proj IDRMC - 630496001
Work TypeDREDGING
 
0.0101762500.001822017.50100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began04-25-17
Work Completed06-12-17
Time Computed04-25-17
Contract Working Days60
Addl Days Granted0
Working Days Charged45
Percent Time Used75
Contractor(s)
ORION CONSTRUCTION, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6304-96-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03174204
Totals1762500.000.001822017.50100.0

CountyGALVESTON
HighwayFM1764
FromVARIOUS HWYS IN GALVESTON COUNTY
ToVARIOUS HWYS IN GALVESTON COUNTY
CSJ6304-97-001
Proj IDRMC - 630497001
Work TypeCLEANING AND SWEEPING HIGHWAYS
 
0.001475020.00435997.51100.0
Work Order11-09-16
Work Began12-06-16
Work Completed12-01-17
Time Computed12-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged365
Percent Time Used100
Contractor(s)
SWEEPING SERVICES OF TEXAS - OPERATING, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6304-97-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09164006
Totals475020.0034680.00435997.51100.0

CountyGALVESTON
HighwaySL0197
From.03 MILES NORTH OF 19TH AVE.
To.03 MILES SOUTH OF 14TH AVE.
CSJ6305-14-001
Proj IDRMC - 630514001
Work Type3/4"TOM-R & 1"TOM-C, MILLING,SEAL COAT
 
0.390564892.18466190.71100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-02-17
Work Began04-10-17
Work Completed06-12-17
Time Computed04-10-17
Contract Working Days45
Addl Days Granted0
Working Days Charged24
Percent Time Used53
Contractor(s)
DURWOOD GREENE CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 6305-14-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01174006
Totals564892.180.00466190.71100.0

CountyGALVESTON
HighwaySH0146
FromVARIOUS HWYS IN GALVESTON COUNTY
ToVARIOUS HWYS IN GALVESTON COUNTY
CSJ6305-34-001
Proj IDRMC - 630534001
Work TypeASPHALT PAVEMENT REPAIR
 
0.001460000.00458348.8299.6
Work Order12-02-16
Work Began12-06-16
Work Completed
Time Computed12-05-16
Contract Working Days365
Addl Days Granted0
Working Days Charged365
Percent Time Used100
Contractor(s)
MAIN LANE INDUSTRIES LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6305-34-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09164225
Totals460000.00112044.93458348.8299.6

CountyHARRIS
HighwayIH0010
FromVARIOUS HIGHWAYS IN WEST HARRIS CO.
To.
CSJ6305-43-001
Proj IDRMC - 630543001
Work TypeSWEEPING
 
0.0011912780.001040618.7854.4
Work Order00-00-00
Work Began12-15-16
Work Completed
Time Computed12-19-16
Contract Working Days730
Addl Days Granted0
Working Days Charged369
Percent Time Used50
Contractor(s)
CEN-TEX IRRIGATION SYSTEMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6305-43-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09164022
Totals1912780.0074506.951040618.7854.4

CountyHARRIS
HighwayIH0010
FromVARIOUS HWYS IN EAST HARRIS COUNTY
ToVARIOUS HWYS IN EASR HARRIS COUNTY
CSJ6305-44-001
Proj IDRMC - 630544001
Work TypeGUARDRAIL REPAIR
 
0.0011222860.00177263.4514.4
Work Order00-00-00
Work Began05-26-17
Work Completed
Time Computed05-26-17
Contract Working Days731
Addl Days Granted0
Working Days Charged217
Percent Time Used29
Contractor(s)
ROY JORGENSEN ASSOCIATES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6305-44-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03174205
Totals1222860.0026710.06177263.4514.4

CountyGALVESTON
HighwayFM0517
FromVARIOUS HWYS IN GALVESTON COUNTY
ToVARIOUS HWYS IN GALVESTON COUNTY
CSJ6305-56-001
Proj IDRMC - 630556001
Work TypeDITCH CLEANING AND RESHAPING
 
0.001309200.00305507.98100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order12-07-16
Work Began01-11-17
Work Completed12-01-17
Time Computed01-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged329
Percent Time Used90
Contractor(s)
TEXAS DRAINAGE INC.
SUBCONTRACTOR(S) FOR CCSJ: 6305-56-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09164226
Totals309200.000.00305507.98100.0

CountyHARRIS
HighwayFM1960
FromFM 2100 FROM SOUTH DIAMONDHEAD
ToBS 249 AT MEDICAL COMPLEX DR.
CSJ6305-63-001
Proj IDRMC - 630563001
Work TypeCLEANING AND RESHAPING DITCHES
 
0.001596351.00176401.9529.5
Work Order04-12-17
Work Began07-11-17
Work Completed
Time Computed04-19-17
Contract Working Days365
Addl Days Granted0
Working Days Charged246
Percent Time Used67
Contractor(s)
GREEN SOURCE ENVIRONMENTAL SOLUTIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6305-63-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01174007
Totals596351.0027764.88176401.9529.5

CountyHARRIS
HighwayIH0010
FromVARIOUS HIGHWAYS IN WEST HARRIS CO.
To.
CSJ6305-68-001
Proj IDRMC - 630568001
Work TypeFULL DEP REP & MISC CONC ITEMS
 
0.001793750.00577466.2472.7
Work Order00-00-00
Work Began12-21-16
Work Completed
Time Computed12-21-16
Contract Working Days730
Addl Days Granted0
Working Days Charged366
Percent Time Used50
Contractor(s)
ISI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6305-68-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10164206
Totals793750.004492.00577466.2472.7

CountyFORT BEND
HighwayUS0059
FromVARIOUS HWYS IN FORT BEND COUNTY
ToVARIOUS HWYS IN FORT BEND COUNTY
CSJ6305-78-001
Proj IDRMC - 630578001
Work TypeCLEANING AND SWEEPING HIGHWAYS
 
0.001797078.00741089.9092.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began11-19-16
Work Completed
Time Computed11-19-16
Contract Working Days365
Addl Days Granted0
Working Days Charged364
Percent Time Used99
Contractor(s)
SWEEPING SERVICES OF TEXAS - OPERATING, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6305-78-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09164023
Totals797078.000.00741089.9092.9

CountyHARRIS
HighwayIH0010
FromVARIOUS HIGHWAYS IN WEST HARRIS CO.
To.
CSJ6305-80-001
Proj IDRMC - 630580001
Work TypeDEBRIS REMOVAL & DISPOSAL
 
0.001364458.00175293.0048.0
Work Order00-00-00
Work Began12-01-16
Work Completed
Time Computed12-01-16
Contract Working Days730
Addl Days Granted0
Working Days Charged386
Percent Time Used52
Contractor(s)
SWEEPING SERVICES OF TEXAS - OPERATING, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6305-80-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09164024
Totals364458.0015062.00175293.0048.0