Monthly State Let Construction Report For Dallas District As Of Nov 22, 2017 Page 7 Of 8

Last Update: Wednesday, November 22, 2017
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyELLIS
HighwayFM 879
From2.1 MILES WEST OF IKE RD
To0.3 MILE WEST OF FM 1722
CSJ1159-02-032
Proj IDSTP 1502(328)HES
Work TypeGR, BASE, PVMT, PVMT MKGS, SIGNS
 
6.6679549753.049577977.5399.9
Work Order07-31-15
Work Began09-03-15
Work Completed
Time Computed07-31-15
Contract Working Days315
Addl Days Granted61
Working Days Charged448
Percent Time Used119
Contractor(s)
ED BELL CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1159-02-032
CROSS ROADS, L.P. (0.38)
BROCK ENVIRONMENTAL SERVICES, LLC (0.19)
ACU CONSTRUCTION LLC (1.24)
STRIPING TECHNOLOGY, L.P. (0.61)
SYNERGY SIGNS & SERVICES (0.28)
FORTSON CONTRACTING, INC. (1.62)
NORTH EASTERN PAVERS (4.90)
PEACHTREE CONSTRUCTION, LTD. (13.21)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (4.95)
HAYWARD BAKER, INC. (0.67)
BRENDA PRICE TRUCKING (6.89)
DFW MATERIALS LP (2.63)
SUPERIOR SOD SERVICES, LLC (0.03)
Contract #06153225
Totals9549753.04100.999577977.5399.9

CountyELLIS
HighwayFM 984
FromAT DRAW, 1.7 MI SOUTH OF SH 34
To.
CSJ1211-01-018
Proj IDBR 2015(483)
Work TypeREPL BR AND APPR
 
0.117879623.40492083.0555.9
CountyELLIS
HighwayFM 984
FromAT ONION CREEK RELIEF #1 AND #2
To.
CSJ1211-01-019
Proj IDBR 2015(484)
Work TypeREPL BR
 
0.1561453823.50895621.0061.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-02-15
Work Began02-25-16
Work Completed
Time Computed02-25-16
Contract Working Days379
Addl Days Granted0
Working Days Charged317
Percent Time Used83
Contractor(s)
COLONIAL AMERICAN CASUALTY AND SURETY COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1211-01-018
FORTSON CONTRACTING, INC. (2.16)
USA EROSION, INC. (3.94)
TOTAL HIGHWAY MAINTENANCE, LLC (0.48)
STRIPING TECHNOLOGY, L.P. (1.23)
TEX OP CONSTRUCTION, LP (1.11)
W. W. FOUNDATION DRILLING, LTD. (5.36)
DFW REBAR, INC. (0.68)
ADVANCED PAVING COMPANY (4.32)
B.G. WILLIAMS ASPHALT, LTD (0.22)
HOUSTON SAWING & DRILLING (0.26)
KNIFE RIVER CORPORATION - SOUTH (0.19)
CTBX, INC. (1.02)
MASTERPIECE GRINDING & GROOVING, LLC (0.25)
AVANZA CONSTRUCTION & EARTHWORKS, LLC (0.00)
BUYERS BARRICADES, INC. (0.93)
Contract #01153012
Totals2333446.900.001387704.0559.4

CountyKAUFMAN
HighwayFM 1388
FromFM 148
ToUS 175
CSJ1217-03-019
Proj IDSTP 2016(360)
Work TypeGR, BASE, ACP OVERLAY, PVMT MKGS
 
12.03017608683.4415930496.2690.4
CountyKAUFMAN
HighwayFM 1388
FromAT KINGS CREEK RELIEF #2
To.
CSJ1217-03-020
Proj IDBR 2016(361)
Work TypeREPLACE BRIDGE
 
0.4954432389.142784076.4262.8
Work Order01-29-16
Work Began04-11-16
Work Completed
Time Computed04-11-16
Contract Working Days580
Addl Days Granted0
Working Days Charged424
Percent Time Used73
Contractor(s)
AUSTIN BRIDGE & ROAD SERVICES, LP
SUBCONTRACTOR(S) FOR CCSJ: 1217-03-019
ALTUS TRAFFIC MANAGEMENT LLC (0.13)
SOUTHWEST CONSTRUCTION SERVICES (0.39)
K & S UTILITY CONTRACTORS, INC. (9.31)
ANALYTICAL TECHNOLOGY CONSULTANTS, INC. (0.05)
PEACHTREE CONSTRUCTION, LTD. (4.40)
SOUTHERN CROSS CONTRACTORS, LLC (0.08)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (5.40)
SYNERGY SIGNS & SERVICES, LLC (0.39)
FARR FOUNDATION, INC. (0.56)
FORTSON CONTRACTING, INC. (0.74)
TRP CONSTRUCTION GROUP, LLC (0.60)
HERDEZ TRUCKING, INC. (2.17)
RAMBO CONTRACTING, INC. (4.73)
TEXOP CONSTRUCTION (0.07)
EJ SMITH CONSTRUCTION COMPANY, LLC (7.55)
BEAIRD DRILLING (0.35)
W.O.E. CONSTRUCTION (1.62)
N.L. SCHUTTE FOUNDATION DRILLING, INC. (0.36)
JB STEEL (0.04)
MOBLEY-SPEEDY CEMENT CONTRACTORS, LLC (0.02)
GIBSON & ASSOCIATES, INC. (0.03)
WITHERS CONSTRUCTION, LLC (1.02)
A-CORE, INC. (0.02)
INDUS CONSTRUCTION, L.P. (0.07)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (0.72)
PENHALL COMPANY (0.03)
Contract #12153205
Totals22041072.581164215.9518714572.6884.9

CountyNAVARRO
HighwayFM 1126
FromAT CHAMBERS CREEK, SW OF IH 45
To.
CSJ1289-01-029
Proj IDBR 1602(046)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.8906714487.746066705.9490.3
Work Order06-02-16
Work Began08-09-16
Work Completed
Time Computed07-05-16
Contract Working Days386
Addl Days Granted10
Working Days Charged309
Percent Time Used78
Contractor(s)
COPPELL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 1289-01-029
A. L. HELMCAMP, INC. (22.43)
IOWA BRIDGE & CULVERT, LC (1.25)
AARON CONCRETE CONTRACTORS, L.P. (3.51)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (4.82)
FORTSON CONTRACTING, INC. (0.29)
HIGHWAY TRAFFIC CONTROL & SERVICES, LLC (0.29)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.26)
TOTAL HIGHWAY MAINTENANCE, LLC (0.42)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (1.37)
MCL CONTRACTING, LLC (0.26)
Contract #04163237
Totals6714487.74443488.136066705.9490.3

CountyDENTON
HighwayFM 1171
FromON CORPS OF ENGINEERS PROPERTY
ToNEAR WHITE'S BRANCH
CSJ1311-01-053
Proj IDC 1311-1-53
Work TypeTREES AND PLANTS
 
0.001148908.50104537.2870.2
CountyDENTON
HighwayFM 2499
FromFM 2181
ToHICKORY CREEK
CSJ2681-01-022
Proj IDNH 1502(094)
Work TypeLANDSCAPE DEVELOPMENT
 
1.112299148.05301197.3299.9
Work Order07-20-15
Work Began08-04-15
Work Completed
Time Computed08-04-15
Contract Working Days60
Addl Days Granted2
Working Days Charged34
Percent Time Used54
Contractor(s)
APEX LANDSCAPE & IRRIGATION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 1311-01-053
ALTUS TRAFFIC MANAGEMENT LLC (0.85)
AMAYA UTILITY (0.56)
QUICK SET CONCRETE, INC. (5.50)
Contract #05153018
Totals448056.551887.08405734.6090.5

CountyDENTON
HighwayFM 423
FromUS 380
To0.8 MI SOUTH OF FM 2934
CSJ1315-02-009
Proj IDC 1315-2-9
Work TypeWIDEN TO 6 LANE DIVIDED URBAN
 
3.48829826069.7332025899.5399.9
Work Order12-12-13
Work Began10-08-14
Work Completed
Time Computed09-08-14
Contract Working Days603
Addl Days Granted18
Working Days Charged680
Percent Time Used109
Contractor(s)
MCM
SUBCONTRACTOR(S) FOR CCSJ: 1315-02-009
TOTAL HIGHWAY MAINTENANCE, LLC (0.96)
STORM WATER MANAGEMENT, INC. (0.28)
BOWMAN ENGINEERING & CONSULTING, INC. (0.84)
FORTSON CONTRACTING, INC. (0.09)
IEA, INC (9.39)
JAGOE-PUBLIC COMPANY (10.82)
OSCAR ORDUNO, INC. (0.23)
ROADWAY SOLUTIONS, INC. (4.78)
ROBERTS TRUCKING (1.98)
RUSSO CORPORATION (0.55)
DUSTROL, INC. (0.49)
W.O.E. CONSTRUCTION (4.50)
TRANSPORT TRUST (0.96)
RICHMOND HYDROMULCH AND SEEDING, LLC (0.27)
SUPERIOR SOD SERVICES, LLC (0.87)
HYDROTECH OF TEXAS (0.78)
RAINWATER FACILITY SOLUTIONS, LLC (0.06)
GREENER PASTURES LANDSCAPE, INC. (1.13)
Contract #09133204
Totals29826069.73121942.0132025899.5399.9

CountyKAUFMAN
HighwayFM 1836
FromFM 2515
ToFM 90
CSJ1397-01-030
Proj IDSTP 2016(289)
Work TypeSHLDR WDN,STR EXT,REMX,SC,PAV MRKS
 
6.9056141935.935495586.88100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-29-16
Work Began04-19-16
Work Completed10-18-17
Time Computed04-18-16
Contract Working Days218
Addl Days Granted0
Working Days Charged214
Percent Time Used98
Contractor(s)
D. L. LENNON INCORPORATED - CONTRACTOR
SUBCONTRACTOR(S) FOR CCSJ: 1397-01-030
PEACHTREE CONSTRUCTION, LTD. (1.77)
S & S BRIDGE PAINTING, INC. (4.51)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (1.11)
TRP CONSTRUCTION GROUP, LLC (1.23)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (0.55)
DUSTIN ALLEN, INC. (1.46)
FARR FOUNDATION, INC. (1.51)
K & S UTILITY CONTRACTORS, INC. (6.21)
WITHERS CONSTRUCTION, LLC (0.63)
ALTUS TRAFFIC MANAGEMENT LLC (0.20)
CAMBRIDGEMOEN LLC (2.28)
GIBSON & ASSOCIATES, INC. (1.87)
BAHENA CONSTRUCTION CO.,INC. (1.32)
Contract #11153024
Totals6141935.930.005495586.88100.0

CountyKAUFMAN
HighwayFM 1836
FromSH 34
To0.28 MI EAST OF CR 146
CSJ1397-01-031
Proj IDC 1397-1-31
Work TypePROVIDE ADDITIONAL PAVED SURFACE
 
4.2695943147.305119265.32100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-01-16
Work Began07-18-16
Work Completed10-02-17
Time Computed07-18-16
Contract Working Days166
Addl Days Granted22
Working Days Charged260
Percent Time Used138
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1397-01-031
ALTUS TRAFFIC MANAGEMENT LLC (0.17)
ODUM SERVICES, L.P. (1.02)
TOTAL HIGHWAY MAINTENANCE, LLC (0.55)
J & M CONTRACTING, COMPANY (20.60)
NIXON ENGINEERING, L.L.C. (0.03)
Contract #01163240
Totals5943147.300.005119265.32100.0

CountyELLIS
HighwayFM 55
FromAT LITTLE ONION CREEK
To.
CSJ1451-01-020
Proj IDBR 2005(274)
Work TypeREPLACE BRIDGES AND APPROACHES
 
0.3122010620.161047794.1252.1
Work Order07-24-15
Work Began02-18-16
Work Completed
Time Computed11-21-15
Contract Working Days340
Addl Days Granted0
Working Days Charged337
Percent Time Used99
Contractor(s)
COLONIAL AMERICAN CASUALTY AND SURETY COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1451-01-020
TEXOP CONSTRUCTION (1.10)
FORTSON CONTRACTING, INC. (2.27)
SAN-ANN-CO., INC. (0.96)
USA EROSION, INC. (4.31)
STRIPING TECHNOLOGY, L.P. (1.50)
W. W. FOUNDATION DRILLING, LTD. (2.35)
DFW REBAR, INC. (0.68)
VISTA RIDGE CONCRETE PUMPING, INC. (0.07)
ADVANCED PAVING COMPANY (6.67)
B.G. WILLIAMS ASPHALT, LTD (0.36)
HOUSTON SAWING & DRILLING (0.30)
KNIFE RIVER CORPORATION - SOUTH (0.35)
CTBX, INC. (1.96)
AVANZA CONSTRUCTION & EARTHWORKS, LLC (0.89)
BUYERS BARRICADES, INC. (1.01)
SOUTHEAST GRINDING & GROOVING, LLC (0.20)
Contract #05153220
Totals2010620.162500.001047794.1252.1

CountyELLIS
HighwayFM 55
FromSH 34
To0.14 MI S OF NASH HOWARD RD
CSJ1451-01-024
Proj IDSTP 2014(874)
Work TypeGR, BASE, PVMT MKGS, SIGNS
 
5.0525538628.875080806.41100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-02-14
Work Began12-01-14
Work Completed10-12-17
Time Computed10-18-14
Contract Working Days263
Addl Days Granted0
Working Days Charged378
Percent Time Used143
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1451-01-024
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (3.86)
STRIPING TECHNOLOGY, L.P. (0.83)
SAN-ANN-CO., INC. (1.01)
ANALYTICAL TECHNOLOGY CONSULTANTS, INC. (0.25)
FORTSON CONTRACTING, INC. (3.25)
OLDEN, INC. (5.14)
LONE STAR HIGHWAY PRODUCTS, INC. (0.49)
NIXON ENGINEERING (0.00)
PRECISION PAVEMENT MAINTENANCE, LLC (0.27)
Contract #07143018
Totals5538628.870.005080806.41100.0

CountyELLIS
HighwayFM 55
FromAT BIG ONION CREEK
To.
CSJ1451-01-025
Proj IDBR 1502(533)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.1351530409.40487327.5431.8
Work Order10-28-15
Work Began11-21-16
Work Completed
Time Computed11-30-15
Contract Working Days183
Addl Days Granted0
Working Days Charged137
Percent Time Used74
Contractor(s)
COLONIAL AMERICAN CASUALTY AND SURETY COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1451-01-025
STRIPING TECHNOLOGY, L.P. (1.12)
FORTSON CONTRACTING, INC. (3.06)
ADVANCED PAVING COMPANY (2.70)
USA SWPPP INSPECTIONS, INC.DBA USA EROSION (0.31)
CTBX, INC. (2.13)
ACU CONSTRUCTION LLC (0.62)
W. W. FOUNDATION DRILLING, LTD. (2.81)
DFW REBAR, INC. (1.14)
AVANZA CONSTRUCTION & EARTHWORKS, LLC (1.59)
BUYERS BARRICADES, INC. (0.83)
SOUTHEAST GRINDING & GROOVING, LLC (0.27)
Contract #08153020
Totals1530409.402500.00487327.5431.8

CountyKAUFMAN
HighwayFM 3486
FromFM 986
ToSH 34
CSJ1494-03-001
Proj IDC 1494-3-1
Work TypeGR, STRS, BASE & SURF
 
2.4904849821.374292015.8989.0
Work Order05-26-16
Work Began07-19-16
Work Completed
Time Computed07-19-16
Contract Working Days168
Addl Days Granted1
Working Days Charged195
Percent Time Used115
Contractor(s)
ED BELL CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1494-03-001
PEACHTREE CONSTRUCTION, LTD. (15.94)
TOTAL HIGHWAY MAINTENANCE, LLC (0.46)
SYNERGY SIGNS & SERVICES, LLC (0.64)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (5.05)
BRENDA PRICE TRUCKING (0.73)
FANNIN TREE FARM, LTD (0.79)
DFW MATERIALS LP (12.21)
Contract #04163222
Totals4849821.373211.004292015.8989.0

CountyDENTON
HighwayFM 720
FromELDORADO PKWY (FM 720)
ToSOUTH OF MARTOP
CSJ1567-01-025
Proj IDC 1567-1-25
Work TypeGR, STRS & PVT
 
2.56515597320.2514299637.4791.6
Work Order04-11-14
Work Began10-26-15
Work Completed
Time Computed01-06-15
Contract Working Days420
Addl Days Granted102
Working Days Charged489
Percent Time Used93
Contractor(s)
HAYDON BUILDING CORP.
SUBCONTRACTOR(S) FOR CCSJ: 1567-01-025
S & S BRIDGE PAINTING, INC. (0.02)
C.T. AND S. METALWORKS, INC. (0.11)
ACU CONSTRUCTION LLC (0.69)
W.O.E. CONSTRUCTION (1.22)
BREDA COMPANY, INC. (0.99)
USA SWPPP INSPECTIONS, INC. (1.99)
TOTAL HIGHWAY MAINTENANCE, LLC (1.04)
FORTSON CONTRACTING, INC. (0.02)
DURABLE SPECIALTIES, INC. (1.69)
MARCOM"S MOWING SERVICE, LLC (0.10)
REYNOLDS ASPHALT & CONSTRUCTION COMPANY (15.66)
DALLAS LITE AND BARRICADE INC. (0.66)
THELIN RECYCLING COMPANY, L.P. (0.21)
A.E.A. TRANSPORTATION (0.21)
TEX OP CONSTRUCTION, LP (0.55)
URBAN INFRACONSTRUCTION, LLC. (0.18)
Contract #02143001
Totals15597320.251428385.0814299637.4791.6

CountyDENTON
HighwayFM 423
FromSTEWARTS CREEK ROAD
ToSH 121
CSJ1567-02-032
Proj IDC 1567-2-32
Work TypeWIDEN TO 6 LANE DIVIDED URBAN
 
3.76149691109.9251816329.8399.9
CountyDENTON
HighwayFM 423
FromSTEWARTS CREEK ROAD
ToSH 121
CSJ1567-02-033
Proj IDRW 1567-2-33
Work TypeADJUSTMENT OF UTILITIES
 
3.7618252384.389359236.7399.9
Work Order08-27-14
Work Began10-20-14
Work Completed
Time Computed09-12-14
Contract Working Days756
Addl Days Granted54
Working Days Charged792
Percent Time Used97
Contractor(s)
WEBBER, LLC
SUBCONTRACTOR(S) FOR CCSJ: 1567-02-032
ATS DRILLING, INC. (1.12)
C.T. AND S. METALWORKS, INC. (0.32)
DUSTROL, INC. (0.52)
ENVIRONMENTAL SAFETY SERVICES, INC. (0.08)
HOUSTON SAWING & DRILLING (0.00)
LANDSCAPE CONTRACTING AND IRRIGATION, INC. (0.31)
MEL"S ELECTRIC SERVICE, INC. (6.02)
REYNOLDS ASPHALT & CONSTRUCTION COMPANY (8.40)
DALLAS LITE AND BARRICADE INC. (0.14)
SCOTT DERR PAINTING CO, LLC (0.66)
STORM WATER MANAGEMENT, INC. (0.14)
STRIPING TECHNOLOGY, L.P. (0.73)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (1.13)
WEST TEXAS REBAR PLACERS INC. (0.35)
W.O.E. CONSTRUCTION (4.60)
MCL CONTRACTING, LLC (0.06)
BORE COMPANY (2.11)
GUIDO CONSTRUCTION, INC. DBA GUIDO"S TRUCKS (0.19)
TEXAS STAR TRANSPORT, LP (0.69)
INDUS CONSTRUCTION, L.P. (4.75)
FORTSON CONTRACTING, INC. (0.09)
ACTION CONSTRUCTORS (0.54)
SYNERGY SIGNS & SERVICES, LLC (0.11)
RICE TUNNELING & BORING, INC. (0.15)
HIGH QUALITY ELECTRIC (0.04)
ALLIED DRILLING COMPANY (0.08)
TOMAS REYES TRUCKING, INC. (0.68)
ROAD MAKER CONTRACTORS (0.44)
PANIOLO CONSTRUCTION SERVICES, LLC (0.40)
DALE BROWN, INC. (0.15)
URBAN INFRACONSTRUCTION, LLC (0.14)
AQUA RECOVER GROUP, CORP. (0.73)
WEBBER BARRIER SERVICES, LLC. (0.12)
JSS BORI GROUP, LLC (1.09)
LINDAMOOD DEMOLITION, INC. (0.11)
TRANSAMERICAN UNDERGROUND, LTD (0.00)
TEXAS CONCRETE CUTTING & DEMOLITION (0.02)
J. E. GUZMAN CONSTRUCTION, INC. (0.00)
E-LOGIC, INC. (0.00)
URBAN INFRACONSTRUCTION, LLC. (0.73)
TEX OP CONSTRUCTION, LP (0.00)
C & S UTILITY CONTRACTORS, INC. (0.05)
Contract #05143001
Totals57943494.30668124.1461175566.5699.9

CountyDENTON
HighwayFM 1830
FromFM 407
ToUS 377
CSJ1785-01-032
Proj IDSTP 1602(424)
Work TypeSHLDR WDN,BS REP, CULVERT WDN
 
5.8773769368.722039507.0154.1
CountyDENTON
HighwayFM 1830
FromAT FINCHER BRANCH
To.
CSJ1785-01-034
Proj IDBR 1602(425)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.3982131977.02592857.7427.8
Work Order01-25-17
Work Began04-17-17
Work Completed
Time Computed04-17-17
Contract Working Days400
Addl Days Granted0
Working Days Charged102
Percent Time Used25
Contractor(s)
JAGOE-PUBLIC COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1785-01-032
IOWA BRIDGE & CULVERT, LC (1.11)
DUSTROL, INC. (3.32)
OSCAR ORDUNO, INC. (1.02)
COMEN ENTERPRISE LLC (1.67)
TOTAL HIGHWAY MAINTENANCE, LLC (1.06)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (6.11)
TEXAS SHAFTS, INC. (1.77)
THELIN RECYCLING COMPANY, L.P. (0.55)
Contract #10163011
Totals5901345.74772904.582632364.7544.6

CountyCOLLIN
HighwayFM 1461
FromSH 289
ToFM 2478
CSJ1973-01-014
Proj IDSSW 1973-1-14
Work TypeBASE REPAIR,LEVEL UP,OVERLAY
 
2.9902697083.13358692.7813.2
Work Order07-20-17
Work Began08-28-17
Work Completed
Time Computed08-28-17
Contract Working Days148
Addl Days Granted0
Working Days Charged43
Percent Time Used29
Contractor(s)
AUSTIN BRIDGE & ROAD SERVICES, LP
SUBCONTRACTOR(S) FOR CCSJ: 1973-01-014
ALTUS TRAFFIC MANAGEMENT LLC (0.43)
FORTSON CONTRACTING, INC. (1.54)
MARCOM"S MOWING SERVICE, LLC (0.90)
TRP CONSTRUCTION GROUP, LLC (1.51)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (1.78)
W.S. CONSTRUCTION COMPANY (23.67)
Contract #06173026
Totals2697083.13140315.00358692.7813.2

CountyDALLAS
HighwayIH 635
FromWEST OF US 75
ToKCS RR
CSJ2374-01-176
Proj IDCM 2015(593)
Work TypeTOLL GANTRIES; SIGNS
 
8.9013115183.144213744.0999.9
CountyDALLAS
HighwayIH 635
FromCENTERVILLE RD
ToLA PRADA
CSJ2374-02-139
Proj IDSTP 2015(594)
Work TypeNOISE WALL
 
1.1043648098.254203177.1299.9
Work Order04-24-15
Work Began06-01-15
Work Completed
Time Computed05-10-15
Contract Working Days267
Addl Days Granted172
Working Days Charged433
Percent Time Used98
Contractor(s)
AUSTIN BRIDGE & ROAD SERVICES, LP
SUBCONTRACTOR(S) FOR CCSJ: 2374-01-176
BUYERS BARRICADES, INC. (0.42)
WYLIE DRILLING & DRAINAGE, INC. (6.09)
LAYFIELD CONSTRUCTION, INC (0.25)
USA SWPPP INSPECTIONS, INC. (2.74)
RG PAINTING (0.56)
STRIPE-A-ZONE, INC. (0.25)
HERDEZ TRUCKING, INC. (0.12)
UNDER CONSTRUCTION INC. (0.17)
MCL CONTRACTING, LLC (3.04)
HIGHWAY INTELLIGENT TRAFFIC SYSTEMS, INC (20.98)
DALLAS LIGHT & BARRICADES (1.37)
THE RIOS GROUP, INC. (0.21)
PENHALL COMPANY (0.01)
UNION ELECTRICAL CONTRACTOR, INC. (2.04)
G & B COMMUNICATIONS, INC. (1.97)
TX DOWN UNDER CONSTRUCTION LLC (0.39)
CARRASCO TRUCKING (0.02)
PANIOLO CONSTRUCTION SERVICES, LLC (3.74)
HICKS LIGHTNING PROTECTION (0.41)
SHERON STONE DBA DOUBLE-S CONSTRUCTION (0.03)
W.O.E. CONSTRUCTION (0.08)
FIBER ONE, LLC (0.05)
COLLIER SERVICES, INC. (0.16)
Contract #02153202
Totals6763281.3947250.008416921.2199.9

CountyDALLAS
HighwayIH 635
FromEAST OF ABRAMS RD
ToWEST OF PLANO RD
CSJ2374-01-180
Proj IDC 2374-1-180
Work TypeNOISE WALLS
 
2.5577705519.390.000.0
CountyDALLAS
HighwayIH 635
FromEAST OF CENTERVILLE RD
ToIH 30
CSJ2374-02-144
Proj IDC 2374-2-144
Work TypeNOISE WALLS
 
2.3673665042.150.000.0
CountyDALLAS
HighwayIH 635
FromEAST OF CENTERVILLE RD
ToIH 30
CSJ2374-02-151
Proj IDNH 1702(428)
Work TypeUTILITIES ADJUSTMENTS
 
4.444380045.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days250
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
AUSTIN BRIDGE & ROAD SERVICES, LP
SUBCONTRACTOR(S) FOR CCSJ: 2374-01-180
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11173201
Totals11750606.540.000.000.0

CountyDALLAS
HighwayIH 635 ETC
From0.509 MI WEST OF FM 78
ToGREENVILLE AVE.
CSJ2374-01-187
Proj IDSTP 1702(455)HES
Work TypeINSTALL PROTECTION
 
56.4803522310.640.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-03-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days185
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
SJ&J CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 2374-01-187
LYNCO CONSTRUCTION (0.00)
Contract #07173227
Totals3522310.640.000.000.0

CountyDALLAS
HighwayIH 635
FromAT ELAM ROAD
ToAT LAKE JUNE ROAD
CSJ2374-02-149
Proj IDNH 1602(426)
Work TypeLANDSCAPE ENHANCEMENT
 
1.585821756.18970362.5299.9
Work Order09-21-16
Work Began11-28-16
Work Completed
Time Computed11-21-16
Contract Working Days148
Addl Days Granted41
Working Days Charged178
Percent Time Used94
Contractor(s)
AALC, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2374-02-149
BUYERS BARRICADES, INC. (0.87)
MONSTER TREE SERVICE OF NORTH DFW (0.17)
DOWN UNDER CONSTRUCTION (0.24)
Contract #08163018
Totals821756.18236082.06970362.5299.9

page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8