Monthly State Let Construction Report For Dallas District As Of Jan 10, 2018 Page 5 Of 7

Last Update: Wednesday, January 10, 2018
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyDALLAS
HighwayVA
FromAT VARIOUS LOCATIONS
To.
CSJ0918-00-187
Proj IDSTP 1602(109)
Work TypeNON SITE SPECIFIC SIGNAL CONTRACT
 
0.0011276600.001053391.8982.5
Work Order06-27-16
Work Began12-07-16
Work Completed
Time Computed09-28-16
Contract Working Days548
Addl Days Granted0
Working Days Charged293
Percent Time Used53
Contractor(s)
DURABLE SPECIALTIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0918-00-187
ROAD MASTER STRIPING LLC (4.59)
Contract #05163018
Totals1276600.0093034.001053391.8982.5

CountyDALLAS
HighwayVA
FromVARIOUS LOCATIONS IN DISTRICT
ToAT DIAMOND INTERCHANGES
CSJ0918-00-263
Proj IDNH 2017(084)
Work TypePAVEMENT MARKINGS,SIGNS,SIGNALS
 
0.0011785330.87405131.5722.6
Work Order10-25-16
Work Began02-22-17
Work Completed
Time Computed12-24-16
Contract Working Days548
Addl Days Granted0
Working Days Charged242
Percent Time Used44
Contractor(s)
AMERICAN LIGHTING AND SIGNALIZATION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0918-00-263
TOTAL HIGHWAY MAINTENANCE, LLC (8.18)
WG ENGINEERING & CONSTRUCTION, LLC (19.16)
Contract #09163210
Totals1785330.8764164.75405131.5722.6

CountyDALLAS
HighwayVA
FromVARIOUS LOCATIONS
ToIN DALLAS DISTRICT
CSJ0918-00-267
Proj IDSTP 1702(453)
Work TypeTRAFFIC SIGNAL REHABILITATION
 
0.1001367285.030.000.0
CountyDALLAS
HighwayVA
FromVARIOUS LOCATIONS
ToIN DALLAS COUNTY
CSJ0918-47-175
Proj IDSTP 1702(453)
Work TypeDMS INSTALLATION
 
0.100332183.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-22-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days240
Addl Days Granted0
Working Days Charged11
Percent Time Used4
Contractor(s)
AMERICAN LIGHTING AND SIGNALIZATION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0918-00-267
TCB FOUNDATION DRILLERS, INC. (3.40)
Contract #07173236
Totals1699468.030.000.000.0

CountyDALLAS
HighwayVA
FromVARIOUS LOCATIONS
ToIN THE DALLAS DISTRICT
CSJ0918-00-275
Proj IDSTP 2018(303)
Work TypeNON-SITE SPECIFIC TRAFFIC SIGNALS
 
0.0012600000.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order12-21-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days913
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
DURABLE SPECIALTIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0918-00-275
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11173214
Totals2600000.000.000.000.0

CountyDALLAS
HighwayVA
FromVARIOUS LOCATIONS
ToIN THE DALLAS DISTRICT
CSJ0918-00-283
Proj IDSTP 2018(504)
Work TypeNON-SITE SPECIFIC SIGNALS
 
0.0011468000.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days548
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
DURABLE SPECIALTIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0918-00-283
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01183012
Totals1468000.000.000.000.0

CountyKAUFMAN
HighwayCR
FromON CR 340 AT DUCK CREEK TRIBUTARY
To.
CSJ0918-11-088
Proj IDBR 1602(003)
Work TypeREPL BR & APPR
 
0.050238680.25204872.6385.8
CountyKAUFMAN
HighwayCR
FromON CR 324 AT GREASY CREEK TRIBUTARY
To.
CSJ0918-11-091
Proj IDBR 1602(004)
Work TypeREPL BR & APPRS
 
0.071458096.27405311.0288.4
Work Order06-08-17
Work Began07-19-17
Work Completed
Time Computed07-19-17
Contract Working Days180
Addl Days Granted0
Working Days Charged105
Percent Time Used58
Contractor(s)
STATELINE CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0918-11-088
PANOLA SIGN & BARRICADE, INC. (1.58)
EROSION CONTROL MANAGEMENT SERVICES (11.39)
ODUM SERVICES, L.P. (4.19)
HEMPHILL WBE PILE DRIVING CO. (1.52)
HODGES AND SON CONSTRUCTION COMPANY, INC. (5.12)
WOLFE CONSTRUCTION GROUP, INC. (0.65)
Contract #04173031
Totals696776.5272081.80610183.6587.5

CountyNAVARRO
HighwayCR
FromON CR SE 3040 AT CEDAR CREEK
To.
CSJ0918-18-125
Proj IDBR 2013(500)
Work TypeREPL BR & APPRS
 
0.066434362.49359847.6982.8
CountyNAVARRO
HighwayCR
FromNW CR 2310 AT RUSH CREEK
To.
CSJ0918-18-126
Proj IDBR 2013(501)
Work TypeREPL BR & APPRS
 
0.064298231.14236420.3479.2
CountyNAVARRO
HighwayCS
FromON CR SE 0120 AT RUSH CREEK
To.
CSJ0918-18-129
Proj IDBR 1602(217)
Work TypeREPL BR & APPRS
 
0.071389584.14326130.2183.7
Work Order11-15-16
Work Began01-03-17
Work Completed
Time Computed12-16-16
Contract Working Days341
Addl Days Granted0
Working Days Charged251
Percent Time Used73
Contractor(s)
PIERCE R & B LLC
SUBCONTRACTOR(S) FOR CCSJ: 0918-18-125
TOTAL HIGHWAY MAINTENANCE, LLC (1.23)
FORTSON CONTRACTING, INC. (2.25)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (7.41)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (5.43)
PEACHTREE CONSTRUCTION, LTD. (5.57)
PENHALL COMPANY (0.30)
DFW REBAR, INC. (0.38)
Contract #09163020
Totals1122177.7711742.04922398.2482.1

CountyDALLAS
HighwayCS
From2ND AVE SB AT TRIB OF WHITE ROCK CR
To.
CSJ0918-45-757
Proj IDBR 2007(303)
Work TypeREPL BR & APPRS
 
0.0851161950.9554789.354.7
CountyDALLAS
HighwayCS
FromPARKDALE DR AT WHITE ROCK CRK TRIB
To.
CSJ0918-45-759
Proj IDBR 2007(304)
Work TypeREPL BR & APPRS
 
0.066694170.000.000.0
CountyDALLAS
HighwayCS
From2ND AVE NB AT WHITE ROCK CREEK
To.
CSJ0918-47-147
Proj IDBR 2017(293)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.072902462.75215834.7023.9
CountyDALLAS
HighwayCS
FromPARKDALE DR AT WHITE ROCK CRK TRIB
To.
CSJ0918-47-195
Proj IDROW 918-47-195
Work TypeUTILITY ADJUSTMENTS
 
0.066125215.300.000.0
Work Order09-20-17
Work Began12-11-17
Work Completed
Time Computed12-04-17
Contract Working Days381
Addl Days Granted0
Working Days Charged14
Percent Time Used3
Contractor(s)
SEMA CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0918-45-757
LINDAMOOD CONSTRUCTION COMPANY, INC. (2.50)
STRIPING TECHNOLOGY, L.P. (2.57)
PREMIER PAVING, LTD. (4.01)
ATS DRILLING, INC. (5.55)
BUYERS BARRICADES, INC. (0.71)
OSCAR ORDUNO, INC. (1.45)
USA SWPPP INSPECTIONS, INC.DBA USA EROSION (0.77)
ACU CONSTRUCTION LLC (0.48)
BOWMAN ENGINEERING & CONSTRUCTION, INC. (0.25)
BREDA COMPANY, INC. (0.42)
Contract #08173015
Totals2883799.00270624.05270624.059.3

CountyDALLAS
HighwayCS
FromON WHITLOCK RD, FROM IH 35E
ToOLD DENTON RD IN CARROLLTON
CSJ0918-45-864
Proj IDSTP 2009(860)MM
Work TypeGR, STRS & SURF
 
0.5053063573.241992924.3765.0
CountyDALLAS
HighwayCS
FromON WHITLOCK RD, FROM IH 35E
ToOLD DENTON RD IN CARROLLTON
CSJ0918-47-116
Proj IDRW 918-47-116
Work TypeADJUSTMENT OF UTILITIES IN CONSTRUC
 
0.505372163.901426794.2699.9
Work Order09-11-14
Work Began10-11-16
Work Completed
Time Computed12-09-14
Contract Working Days276
Addl Days Granted16
Working Days Charged232
Percent Time Used79
Contractor(s)
TISEO PAVING CO.
SUBCONTRACTOR(S) FOR CCSJ: 0918-45-864
DALLAS LITE AND BARRICADE INC. (0.86)
T-BAR FENCE, INC. (0.49)
LARRETT, INC. (16.98)
AXIS CONTRACTING, INC. (8.17)
RPM XCONSTRUCTION, LLC (18.81)
BROCK ENVIRONMENTAL SERVICES, LLC (0.10)
SUPERSCAPES LANDSCAPING, INC. (4.86)
TEX OP CONSTRUCTION, LP (0.18)
STRIPE-A-ZONE, INC. (0.71)
DURABLE SPECIALTIES, INC. (3.66)
J R STEEL (1.11)
SYNERGY SIGNS & SERVICES (0.45)
METROPLEX PAVEMENT MARKINGS (0.71)
STENSON LANDSCAPE (4.86)
Contract #07143222
Totals3435737.1498299.733419718.6399.5

CountyDENTON
HighwayCS
FromS. BLUE MOUND RD
ToAT ELIZABETH CREEK IN FT WORTH
CSJ0918-46-274
Proj IDBR 1502(368)
Work TypeREPL BR & APPRS
 
0.120877705.46128689.0714.6
CountyDENTON
HighwayCR
FromHILLTOP RD 0.4 MI NORTH OF FM 407
ToAT LOVING BRANCH TRIB
CSJ0918-46-277
Proj IDBR 1602(008)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.061345671.42206271.5059.6
CountyDENTON
HighwayCS
FromMOBBERLY RD @ LITTLE ELM CREEK TRIB
To.
CSJ0918-46-287
Proj IDBR 1602(142)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.059425036.72143298.3833.7
Work Order07-12-17
Work Began09-06-17
Work Completed
Time Computed09-06-17
Contract Working Days286
Addl Days Granted0
Working Days Charged76
Percent Time Used26
Contractor(s)
COPPELL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0918-46-274
TEXAS SHAFTS, INC. (3.95)
USA SWPPP INSPECTIONS, INC.DBA USA EROSION (1.83)
PEACHTREE CONSTRUCTION, LTD. (3.48)
COMEN ENTERPRISE LLC (3.13)
ALTUS TRAFFIC MANAGEMENT LLC (0.68)
STRIPING TECHNOLOGY, L.P. (0.59)
TEX OP CONSTRUCTION, LP (1.16)
MCL CONTRACTING, LLC (0.21)
Contract #06173246
Totals1648413.6028699.99478258.9529.0

CountyDENTON ETC
HighwayCS
FromMARSH LANE AT ROSEMEADE PKWY
To.
CSJ0918-46-280
Proj IDSTP 1702(357)HES
Work TypeIMPROVE TRAFFIC SIGNALS
 
1.0001284000.00257232.4720.0
Work Order07-12-17
Work Began11-02-17
Work Completed
Time Computed11-02-17
Contract Working Days190
Addl Days Granted0
Working Days Charged44
Percent Time Used23
Contractor(s)
DURABLE SPECIALTIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0918-46-280
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06173017
Totals1284000.0073006.00257232.4720.0

CountyDENTON ETC
HighwayCS
FromFRANKFORD RD AT MARSH LN
To.
CSJ0918-46-291
Proj IDSTP 2018(120)HES
Work TypeIMPROVE TRAFFIC SIGNALS
 
1.4001478000.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order12-04-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days246
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
DURABLE SPECIALTIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0918-46-291
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10173008
Totals1478000.000.000.000.0

CountyDALLAS
HighwayCS
FromCEDAR HILL STATE PARK
ToNEW CLARK RD IN CITY OF CEDAR HILL
CSJ0918-47-097
Proj IDSTP 2014(156)TE
Work TypeHIKE AND BIKE TRAIL
 
1.3682766088.00463779.5616.7
CountyDALLAS
HighwayFM 1382
FromAT CEDAR HILL STATE PARK SPINE RD
To.
CSJ1047-03-066
Proj IDC 1047-3-66
Work TypeGR, BS, ASPH PVMT, PVMT MKGS
 
0.2671257559.701410027.9999.9
CountyDALLAS
HighwayFM 1382
FromSOUTHEAST OF WEST SPINE ROAD
ToWEST OF NEW CLARK ROAD
CSJ1047-03-068
Proj IDCM 1602(423)
Work TypeINTERSECTION IMPROVEMENTS
 
0.6001197552.401233149.8199.9
CountyDALLAS
HighwayFM 1382
FromAT CEDAR HILL STATE PARK SPINE RD
To.
CSJ1047-03-070
Proj IDNH 1602(422)
Work TypeTRAF SIG
 
0.196827701.00926689.3599.9
Work Order11-16-16
Work Began03-01-17
Work Completed
Time Computed03-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged208
Percent Time Used56
Contractor(s)
FNH CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0918-47-097
REYNOLDS ASPHALT & CONSTRUCTION COMPANY (6.94)
STRIPING TECHNOLOGY, L.P. (0.87)
STRIPING SYSTEMS, INC. (0.01)
COWBOY TRUCKING (0.11)
GJ SEEDING, LLC (3.14)
UNDER CONSTRUCTION INC. (0.09)
XTREEME SAWING & SEALING, INC. (0.09)
MABAK DIRECTIONAL DRILLING (0.09)
NEWSTAR DRILLING, INC (1.01)
Q. ROBERTS TRUCKING INCORPORATED (0.57)
TEXOP CONSTRUCTION (0.09)
Contract #07163040
Totals6048901.10181859.434033646.7166.6

CountyDALLAS
HighwayVA
FromVARIOUS LOCATIONS ON STATE HIGHWAYS
ToIN DALLAS COUNTY
CSJ0918-47-114
Proj IDNH 1702(722)
Work TypeCONSTRUCT CURB RAMPS
 
0.0012650440.80561985.5521.2
Work Order09-18-17
Work Began10-26-17
Work Completed
Time Computed10-23-17
Contract Working Days375
Addl Days Granted0
Working Days Charged43
Percent Time Used11
Contractor(s)
HIGHWAY 19 CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0918-47-114
STRIPING TECHNOLOGY, L.P. (3.89)
TOTAL HIGHWAY MAINTENANCE, LLC (2.15)
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC. (12.90)
Contract #08173214
Totals2650440.8081348.61561985.5521.2

CountyDALLAS
HighwayPW
From@ CEDAR HILL STATE PARK
ToIN SHADY RIDGE CAMPING AREA
CSJ0918-47-118
Proj IDC 918-47-118
Work TypeGR,STR,PAV,PAV MARKS
 
0.0011037211.25603051.2958.1
Work Order08-23-17
Work Began09-25-17
Work Completed
Time Computed09-25-17
Contract Working Days84
Addl Days Granted0
Working Days Charged62
Percent Time Used73
Contractor(s)
TEXAS-REYES GROUP LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0918-47-118
DIIBS SPECIALISTS (2.45)
FARR FOUNDATION, INC. (4.76)
EROSION CONTROL, INC. (4.62)
OLDCASTLE MATERIALS TEXAS, INC. (19.22)
ACTION COMMERCIAL SERVICES, L.L.C. (1.40)
C.T. AND S. METALWORKS, INC. (2.14)
USA SWPPP INSPECTIONS, INC.DBA USA EROSION (0.60)
CORONADO R. CONSTRUCTION, LLC (3.12)
Contract #07173037
Totals1037211.25109707.98603051.2958.1

CountyDALLAS
HighwayCS
FromBELT LINE ROAD AT DALLAS PKWY
To.
CSJ0918-47-120
Proj IDSTP 1602(110)HES
Work TypeIMPROVE TRAFFIC SIGNALS
 
1.0001300500.001042449.6081.1
Work Order08-08-16
Work Began11-09-16
Work Completed
Time Computed11-06-16
Contract Working Days172
Addl Days Granted0
Working Days Charged191
Percent Time Used111
Contractor(s)
DURABLE SPECIALTIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0918-47-120
ROAD MASTER STRIPING LLC (5.59)
LUZ LERMA CONSTRUCTION, INC. (15.28)
Contract #05163228
Totals1300500.0025709.901042449.6081.1

CountyNAVARRO
HighwayFM 1838
From0.939 MI N OF CR 4270
ToFM 638
CSJ0997-02-039
Proj IDSTP 2016(992)HES
Work TypeCONSTRUCT PAVED SHOULDERS
 
1.5531991914.541892780.7095.0
CountyNAVARRO
HighwayFM 3383
FromFM 1126
ToCR 1110
CSJ3401-01-007
Proj IDSTP 2016(993)HES
Work TypeSAFETY TREAT FIXED OBJECTS
 
1.5001883297.661776192.9894.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began02-24-17
Work Completed
Time Computed02-24-17
Contract Working Days251
Addl Days Granted0
Working Days Charged169
Percent Time Used67
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0997-02-039
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (3.66)
ODUM SERVICES, L.P. (0.35)
SAN-ANN-CO., INC. (0.90)
TOTAL HIGHWAY MAINTENANCE, LLC (0.57)
BEAR CREEK CONSTRUCTION, LLC (21.49)
POTTER TRUCKING (1.29)
Contract #12163029
Totals3875212.200.003668973.6894.6

CountyCOLLIN
HighwayFM 546
FromSH 5
ToEAST OF COUNTRY LN/AIRPORT RD
CSJ1013-01-026
Proj IDC 1013-1-26
Work TypeGR, PVMT, STR, SIGNS, PVMT MKGS
 
1.72417391616.9812508400.6871.9
Work Order08-11-16
Work Began01-04-17
Work Completed
Time Computed11-09-16
Contract Working Days411
Addl Days Granted0
Working Days Charged149
Percent Time Used36
Contractor(s)
MARIO SINACOLA & SONS EXCAVATING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1013-01-026
SCOTT DERR PAINTING CO, LLC (0.13)
LIRA ELECTRIC (0.49)
ROYAL REBAR (0.95)
PANIOLO CONSTRUCTION SERVICES, LLC (3.60)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (1.18)
BROCK ENVIRONMENTAL, LLC (0.13)
LINDAMOOD DEMOLITION, INC. (0.05)
REYNOLDS ASPHALT & CONSTRUCTION COMPANY (8.87)
WYLIE DRILLING & DRAINAGE, INC. (1.41)
W.O.E. CONSTRUCTION (0.16)
ALLIANCE GEOTECHNICAL GROUP (0.28)
STRIPING TECHNOLOGY, L.P. (0.56)
SYNERGY SIGNS & SERVICES, LLC (0.21)
IRON CONCRETE CONSTRUCTION COMPANY, INC. (0.71)
4-B TRUCKING, INC. (0.60)
L AND T TRANSIT (0.23)
LUZ TRUCKING, INC. (0.23)
M & H TRANSPORT (0.23)
MARCO A. TRUCKING (0.23)
ORTIZ TRUCKING (0.23)
ACU CONSTRUCTION LLC (0.15)
MELS ELECTRIC, L.P. (0.55)
Contract #05163037
Totals17391616.98324507.8812508400.6871.9

CountyROCKWALL
HighwayFM 548
FromSH 276
ToSH 66
CSJ1014-02-041
Proj IDSTP 2016(145)
Work TypeWDN,STR,REMX,OL,PV MRKS
 
12.75113784401.3513945899.9699.9
Work Order02-03-16
Work Began03-28-16
Work Completed
Time Computed03-28-16
Contract Working Days363
Addl Days Granted14
Working Days Charged377
Percent Time Used100
Contractor(s)
ZACHRY CONSTRUCTION CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 1014-02-041
TEXOP CONSTRUCTION (1.79)
EROSION CONTROL MANAGEMENT SERVICES (0.48)
PREMIER PAVING, LTD. (22.61)
SCOTT PAVING, INC. (3.33)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (1.66)
TRP CONSTRUCTION GROUP, LLC (0.94)
DALLAS LITE AND BARRICADE INC. (0.54)
COMEN ENTERPRISE (1.34)
COWBOY TRUCKING (4.54)
FARR FOUNDATION, INC. (0.61)
WOOD WATERING SERVICES, LLC (2.14)
HARDIN TREE, INC. (0.18)
W.O.E. CONSTRUCTION (0.01)
SUPERIOR MATERIALS (0.08)
Contract #10153205
Totals13784401.3563646.7913945899.9699.9

CountyROCKWALL
HighwayFM 740
FromFM 549 / FM 550 INTERSECTION
ToFM 1140 NORTH IN HEATH
CSJ1014-03-049
Proj IDC 1014-3-49
Work TypeGRADING,STRUCTURES,DRAINAGE, & PVMT
 
1.85612967453.4211740823.8991.5
Work Order11-14-13
Work Began07-20-15
Work Completed
Time Computed08-11-14
Contract Working Days412
Addl Days Granted6
Working Days Charged515
Percent Time Used123
Contractor(s)
ED BELL CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1014-03-049
W.O.E. CONSTRUCTION (0.30)
TEX OP CONSTRUCTION, LP (2.01)
TEXAS INLETS, INC. (3.67)
SYNERGY SIGNS & SERVICES, LLC (0.37)
HAYWARD BAKER, INC. (0.81)
STRIPING TECHNOLOGY, L.P. (0.99)
USA SWPPP INSPECTIONS, INC.DBA USA EROSION (1.82)
PREMIER PAVING, LTD. (4.86)
DURABLE SPECIALTIES, INC. (3.25)
BREDA COMPANY, INC. (0.67)
BUYERS BARRICADES, INC. (0.31)
BRENDA PRICE TRUCKING (4.98)
FANNIN TREE FARM, LTD (0.33)
Contract #08133209
Totals12967453.42562473.3911740823.8991.5

page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7