End of Project Process
There are two reasons a project may be closed
out. The first reason is that a project has met the scheduled completion
or secondarily, the project is being terminated early.
When a project has met its scheduled completion, the Closeout
meeting may take place as early as a month before the end of the
project. This meeting includes a discussion of the possibility of
implementation.
If a project is closes earlier than originally stated, a letter
with a termination date is sent to the University Liaison, which
initiates the Closeout.
- If TxDOT concludes that continuation of a Project Agreement into the next fiscal year, in whole or in part, would not produce beneficial results that commensurate with the further expenditure of funds, the Project Agreement may be terminated.
- If both parties conclude that continuation of a Project Agreement for the remainder of a fiscal year, in whole or in part, would not produce beneficial results commensurate with the further expenditure of funds, the Project Agreement may be terminated.
When Project Agreements are terminated prior to scheduled
completion, TxDOT will make every reasonable effort to minimize
adverse impacts to the project team.
After a project ends the University or Federal agency has
90 days to send a final bill
to RTI. If, for any reason,
the University or Federal agency is unable to submit a final bill
within 90 days, they must request a one-time closeout extension
using a request form available from RTI. Closeout extension requests
are subject to RTI and FHWA approval. If a closeout extension request
is not approved by FHWA, TxDOT may choose to pay billings using state
funds only
.