Cost Estimates
A cost
estimate and circuit
diagram
are provided from the railroad company for labor and materials provided
by the railroad company. Estimates will clarify any cost
participation by the railroad company and will be reimbursed through
a railroad agreement.
The local government will produce an estimate for any labor
and materials provided by the local government. Estimates will clarify
any cost participation by the local government.
Unless approved
by
TxDOT, materials and labor provided by the local government
are usually not reimbursed via Section 130 funding. Construction
work funded by Section 130 will need to be covered under an Advanced
Funding Agreement
.For crossings on the state highway system, the district
may
pay
for any TxDOT labor or materials out of district funds. This work
is typically similar to work provided by a local government on an off-system
crossing. Work by a TxDOT contractor is also paid out of district
funds. If Section 130 funds are used for these types of
projects, the district must proceed through the typical letting
process.
The
RRD
project manager will review and
approve all estimates prior to development of the Exhibit B, Force
Account Agreement or Crossing Closure Agreement.For further information on reviewing railroad company cost
estimates and
circuit
diagrams, see Chapter
2 of this Manual.