4.10.13 Side Slopes
Side slopes refer to the slopes of areas adjacent to the shoulder and located between the shoulder and the ROW line. For safety reasons, it is desirable to design relatively flat areas adjacent to the travel-way so that out-of-control vehicles are less likely to turn over, vault, or impact the side of a drainage channel.
A section of typical side slopes is illustrated in
.

Figure 4-22: Side Slopes Section
4.10.13.1 Slope Rates
The path that an out-of-control vehicle follows after it leaves the traveled portion of the roadway is related to a number of factors such as driver capabilities, slope rates, and vehicular speed. Crash data indicates that approximately 75 percent of reported encroachments do not exceed a lateral distance of 30-ft from the travel lane edge where roadside slopes are 1V:6H or flatter - slope rates that afford drivers significant opportunity for recovery. Crash test data further indicates that steeper slopes (up to 1V:3H) are negotiable by drivers; however, recovery of vehicular control on these steeper slopes is less likely. Recommended clear zone width associated with these slopes are further discussed in 4.10.7.
4.10.13.2 Design Values
Particularly difficult terrain or restricted ROW width may require deviation from these general guide values. Where conditions are favorable, it is desirable to use flatter slopes to enhance roadside safety.
4.10.13.3 Front Slope
The slope adjacent to the shoulder is called the front slope. Ideally, the front slope should be 1V:6H or flatter, although steeper slopes are acceptable in some locations. Rates of 1V:4H or flatter facilitate efficient operation of construction and maintenance equipment. Slope rates of 1V:3H may be used in constrained conditions. Slope rates of 1V:2H are normally used on bridge header banks or ditch side slopes, both of which would likely require riprap.
Slopes greater than 1V:2.5H require evaluation for slope stability.
See TxDOT’s
for additional guidance with respect to evaluating slope stability for various conditions.When the front slope is steeper than 1V:3H, a longitudinal barrier may be considered to keep vehicles from traversing the slope.
A longitudinal barrier should not be used solely for slope protection for rates of 1V:3H or flatter since the barrier may be more of an obstacle than the slope.
Also, since recovery is less likely on 1V:3H to1V:4H slopes, fixed objects should not be present near the toe of these slopes. Particular care should be taken in the treatment of man-made appurtenances such as culvert ends. See
for additional information on considerations for barrier need.4.10.13.4 Back Slope
The back slope is typically at a slope of 1V:4H or flatter for mowing purposes. Generally, if steep front slopes are provided, the back slopes are relatively flat. Conversely, if flat front slopes are provided, the back slopes may be steeper. The slope ratio of the back slope may vary depending upon the geologic formation encountered. For example, where the roadway alignment traverses through a rock formation area, back slopes are typically much steeper and may be close to vertical.
Steep back slope designs should be examined for slope stability.
4.10.13.5 Design
The intersections of slope planes in the highway cross section should be well rounded for added safety, increased stability, and improved aesthetics. Front slopes, back slopes, and ditches should be sodded and/or seeded where feasible to promote stability and reduce erosion. In arid regions, concrete or rock retards may be necessary to prevent ditch erosion.
Where guardrail is placed on side slopes, the area between the roadway and barrier should be sloped at 1V:10H or flatter.
Roadside drainage ditches should be of sufficient width and depth to handle the design run-off, should be at least 6-in below the subgrade crown, and the design year water elevation should not backflow into the pavement structure. For additional information, see Drainage Facility Placement.
For additional information, see
.