Final Plans

Upon project completion, revise the original plans to show the project as-built. Place the words “FINAL PLANS” in a conspicuous place on the title sheet with the following:
  • contractor’s name
  • letting date
  • begin date of work
  • date of DCO acceptance
  • final contract cost, and
  • AE's seal and signature.
Show a summary of all COs on the title sheet. If needed, insert a separate summary sheet immediately following the title sheet.
For projects involving bridge construction, the drilled shaft or pile foundations tip elevation must be indicated on the bridge layouts in the final (as-built) plans. A copy of all As-built Bridge Plan Sheets, Pile Driving Records ( ), and Drill Shaft Records ( ) are to be provided to the district bridge office to be included in the bridge file in the bridge inspection management system (currently AssetWise). Refer to for guidance (internal access only).
Shop drawings are to be placed in the final as-built plans.
The responsible Engineer affixes the final plans statement to the title sheet and signs, seals, and dates the final as-built plans. Send As-Built drawings to . If the file is too large to email you can send it to CST via us through box.com. Be sure to indicate it is a set of “As-Built” plans.