CRUSHER OR SCREEN PLANT OPERATOR – code 9351

Maximum
training time: 26 weeks or 1040 hours
Code 9351
Step
Process
Hours
1
Orientation and Observation
  • Safety procedures, 10 hours
  • Observation of machine in operation, 35 hours
  • Starting of crusher operating conveyors, 30 hours
75
2
Care and Maintenance
  • Safety procedures, 10 hours
  • Routine fueling, lubricating and servicing, 35 hours
45
3
Actual Operation of Equipment
  • Safe operating procedures, 10 hours
  • Operation of conveyors and crusher operations, 120 hours
  • Operation of crusher, 790 hours
920
Total
1040