Letting Schedule for Pharr District (FY 2023)
Bid Tabulations Dashboard
This report will no longer be updated, please access links on the Contract Letting page. The Electronic State Business Daily (ESBD), the Electronic Bidding System, and the project proposal are the official sources of advertisement and bidding information for the State and Local Lettings. Bidders should bid the project using the information found therein, including any addenda. These sources take precedence over information from other sources, including TxDOT webpages, which are unofficial and intended for informational purposes only. |
Pharr District (FY 2023) |
Cameron | Hidalgo | Willacy | Zapata | | |||||||
Cameron County |
|||||||
CCSJ | Highway | Let Status | Letting Date | Contract Cost | Fund Cat | Description | DBE Goal |
---|---|---|---|---|---|---|---|
0220-04-059 | US 281 | Tentative | Jul 2023 | $701,027 | 8 | HAZARD ELIMINATION & SAFETY | 0.0 |
0921-06-356 | CS | Tentative | Aug 2023 | $469,640 | 3 | HAZARD ELIMINATION & SAFETY | 0.0 |
1504-01-037 | SH 4 | Tentative | Jul 2023 | $13,648,184 | 3 | REHABILITATE EXISTING ROADWAY | 0.0 |
0921-06-325 | CS | Tentative | May 2023 | $386,012 | 3 | HIKE AND/OR BIKE | 0.0 |
0220-07-068 | SH 48 | Tentative | Aug 2023 | $383,708 | 8 | HAZARD ELIMINATION & SAFETY | 0.0 |
0921-06-302 | CS | Tentative | Dec 2022 | $1,955,738 | 6 | BRIDGE REPLACEMENT | 0.0 |
0921-06-322 | CR | Tentative | Dec 2022 | $1,468,583 | 3 | HIKE AND/OR BIKE | 0.0 |
1137-02-043 | SL 499 | Tentative | Feb 2023 | $350,000 | 8 | INSTALL RAISED MEDIAN | 0.0 |
0342-03-037 | SH 107 | Tentative | Dec 2022 | $4,369,645 | 1 | REHABILITATE EXISTING ROADWAY | 0.0 |
0039-12-259 | BU 77-X | Tentative | Jan 2023 | $6,946,354 | 1 | PREVENTIVE MAINTENANCE | 0.0 |
0921-06-326 | VA | Tentative | May 2023 | $400,859 | 3 | HIKE AND/OR BIKE | 0.0 |
0684-01-068 | SH 550 | Tentative | Mar 2023 | $20,474,606 | 3 | CONSTRUCT NEW TOLL ROAD | 0.0 |
0921-06-306 | CS | Tentative | Jan 2023 | $1,171,726 | 6 | BRIDGE REPLACEMENT | 0.0 |
0039-07-257 | IH 69E | Tentative | Feb 2023 | $2,521,661 | 1 | CONSTRUCT RAMPS | 0.0 |
Hidalgo County |
|||||||
CCSJ | Highway | Let Status | Letting Date | Contract Cost | Fund Cat | Description | DBE Goal |
0862-01-057 | FM 492 | Tentative | Nov 2022 | $1,908,063 | 6 | BRIDGE REPLACEMENT | 0.0 |
0669-03-029 | FM 2221 | Tentative | Aug 2023 | $830,644 | 8 | HAZARD ELIMINATION & SAFETY | 0.0 |
0921-02-500 | Tentative | Aug 2023 | $189,422 | 3 | HAZARD ELIMINATION & SAFETY | 0.0 | |
0528-01-121 | SH 107 | Tentative | Nov 2022 | $3,348,922 | 1 | PREVENTIVE MAINTENANCE | 0.0 |
2831-01-016 | FM 2812 | Tentative | Aug 2023 | $404,945 | 8 | HAZARD ELIMINATION & SAFETY | 0.0 |
0921-02-508 | CS | Tentative | Aug 2023 | $272,914 | 3 | HAZARD ELIMINATION & SAFETY | 0.0 |
0921-02-375 | CS | Tentative | Aug 2023 | $6,949,838 | 3 | ROADWAY REHABILITATION/RECONSTRUCTION WITH NO ADDED CAPACITY | 0.0 |
0921-02-484 | CS | Tentative | Jul 2023 | $451,984 | 3 | HAZARD ELIMINATION & SAFETY | 0.0 |
0921-02-331 | CS | Tentative | Dec 2022 | $482,475 | 6 | BRIDGE REPLACEMENT | 0.0 |
1064-01-032 | FM 676 | Tentative | Feb 2023 | $16,149,113 | 1 | WIDEN ROAD - ADD LANES | 0.0 |
1428-01-027 | FM 1425 | Tentative | Jul 2023 | $14,961,160 | 1 | REHABILITATE EXISTING ROADWAY | 0.0 |
0921-02-194 | CS | Tentative | Dec 2022 | $10,953,888 | 3 | WIDEN ROAD - ADD LANES | 0.0 |
1803-02-049 | FM 1925 | Tentative | Jul 2023 | $434,024 | 8 | HAZARD ELIMINATION & SAFETY | 0.0 |
0921-02-480 | CS | Tentative | Feb 2023 | $378,000 | 3 | BICYCLE AND PEDESTRIAN IMPROVEMENTS | 0.0 |
Willacy County |
|||||||
CCSJ | Highway | Let Status | Letting Date | Contract Cost | Fund Cat | Description | DBE Goal |
0327-10-063 | IH 69E | Tentative | May 2023 | $4,380,000 | 11 | INTERSTATE DESIGNATION | 0.0 |
0921-27-040 | VA | Tentative | Aug 2023 | $2,171,142 | 3 | ROADWAY REHABILITATION/RECONSTRUCTION WITH NO ADDED CAPACITY | 0.0 |
1430-01-031 | FM 490 | Tentative | Jul 2023 | $5,392,365 | 6 | WIDEN ROAD - ADD SHOULDERS | 0.0 |
Zapata County |
|||||||
CCSJ | Highway | Let Status | Letting Date | Contract Cost | Fund Cat | Description | DBE Goal |
0038-05-040 | US 83 | Tentative | May 2023 | $31,117,441 | 1 | WIDEN ROAD - ADD LANES | 0.0 |
|