The Electronic State Business Daily (ESBD), the Electronic Bidding System, and the project proposal are the official sources of advertisement and bidding information for the State and Local Lettings. Bidders should bid the project using the information found therein, including any addenda. These sources take precedence over information from other sources, including TxDOT webpages, which are unofficial and intended for informational purposes only.

Childress District (FY 2023)
Donley | Hall | Hardeman | Knox | Wheeler |

Donley County

CCSJHighwayLet StatusLetting
Date
Contract
Cost
Fund
Cat
DescriptionDBE Goal
0795-05-010FM 291TentativeDec 2022$2,125,0006BRIDGE REPLACEMENT0.0

Hall County

CCSJHighwayLet StatusLetting
Date
Contract
Cost
Fund
Cat
DescriptionDBE Goal
0311-02-033SH 70TentativeJul 2023$8,603,0006BRIDGE REPLACEMENT0.0

Hardeman County

CCSJHighwayLet StatusLetting
Date
Contract
Cost
Fund
Cat
DescriptionDBE Goal
0043-23-008SL 285TentativeJun 2023$1,398,6006BRIDGE REPLACEMENT0.0

Knox County

CCSJHighwayLet StatusLetting
Date
Contract
Cost
Fund
Cat
DescriptionDBE Goal
0496-04-036SH 222TentativeJun 2023$11,351,6326BRIDGE REPLACEMENT0.0
0538-01-027FM 267TentativeApr 2023$5,682,5798WIDEN ROAD - ADD SHOULDERS0.0

Wheeler County

CCSJHighwayLet StatusLetting
Date
Contract
Cost
Fund
Cat
DescriptionDBE Goal
0031-01-022US 83TentativeDec 2022$9,288,7991HIGHWAY IMPROVEMENT0.0
0030-08-038US 83TentativeJul 2023$18,998,1006BRIDGE REPLACEMENT0.0
2051-01-014FM 2473TentativeJan 2023$416,6743CONSTRUCT PEDESTRIAN INFRASTRUCTURE0.0


Let StatusDefinition
TentativeEstimated letting date for this project
ApprovedProject has administrative approval to be let
ActualProject was let to contract