The Electronic State Business Daily (ESBD), the Electronic Bidding System, and the project proposal are the official sources of advertisement and bidding information for the State and Local Lettings. Bidders should bid the project using the information found therein, including any addenda. These sources take precedence over information from other sources, including TxDOT webpages, which are unofficial and intended for informational purposes only.

San Angelo District (FY 2022)
Crockett | Tom Green |

Crockett County

CCSJHighwayLet StatusLetting
Date
Contract
Cost
Fund
Cat
DescriptionDBE Goal
0140-13-025IH 10ApprovedAug 2022$1,421,6008HAZARD ELIMINATION & SAFETY0.0

Tom Green County

CCSJHighwayLet StatusLetting
Date
Contract
Cost
Fund
Cat
DescriptionDBE Goal
0077-09-010BU 67-HActualMay 2022$1,702,2678HAZARD ELIMINATION & SAFETY6.0
0907-24-054VAApprovedAug 2022$945,8818TRAFFIC SIGNAL IMPROVEMENTS0.0
0070-02-091US 87ActualJan 2022$10,297,8691PREVENTIVE MAINTENANCE0.0
0070-02-097US 87ActualDec 2021$14,653,7051PREVENTIVE MAINTENANCE0.0
0264-06-043US 277ActualApr 2022$15,325,5881HIGHWAY IMPROVEMENT5.5
0907-00-198VAActualJan 2022$3,243,0101HIGHWAY IMPROVEMENT0.0
0907-00-178VAActualApr 2022$1,012,05511TRAFFIC SIGNAL IMPROVEMENTS0.0


Let StatusDefinition
TentativeEstimated letting date for this project
ApprovedProject has administrative approval to be let
ActualProject was let to contract