Letting Schedule for Lubbock District (FY 2022)

Last Update: Friday, June 24, 2022

Bid Tabulations Dashboard

Use this interactive Tableau dashboard to display bidding information on projects let through statewide and local district letting for the past 24 months.

The Electronic State Business Daily (ESBD), the Electronic Bidding System, and the project proposal are the official sources of advertisement and bidding information for the State and Local Lettings. Bidders should bid the project using the information found therein, including any addenda. These sources take precedence over information from other sources, including TxDOT webpages, which are unofficial and intended for informational purposes only.

Lubbock District (FY 2022)
Bailey | Gaines | Garza | Hale | Hockley | Lamb | Lubbock | Swisher |

Bailey County

CCSJHighwayLet StatusLetting
Date
Contract
Cost
Fund
Cat
DescriptionDBE Goal
0052-02-036US 70ActualSep 2021$17,626,6861SURFACING/ROADWAY RESTORATION3.5

Gaines County

CCSJHighwayLet StatusLetting
Date
Contract
Cost
Fund
Cat
DescriptionDBE Goal
0228-02-049US 62ActualJan 2022$17,753,1291REHABILITATE EXISTING ROADWAY7.0

Garza County

CCSJHighwayLet StatusLetting
Date
Contract
Cost
Fund
Cat
DescriptionDBE Goal
0905-15-012CRActualDec 2021$955,6186BRIDGE REPLACEMENT0.0

Hale County

CCSJHighwayLet StatusLetting
Date
Contract
Cost
Fund
Cat
DescriptionDBE Goal
0067-04-056IH 27ActualOct 2021$1,502,9328HAZARD ELIMINATION & SAFETY0.0
0905-12-043CSActualFeb 2022$939,2686BRIDGE REPLACEMENT5.0
0439-05-029SH 194ActualDec 2021$101,6158RAILROAD CROSSING IMPROVEMENTS0.0

Hockley County

CCSJHighwayLet StatusLetting
Date
Contract
Cost
Fund
Cat
DescriptionDBE Goal
0130-04-035SH 114ApprovedAug 2022$1,865,7238HAZARD ELIMINATION & SAFETY0.0

Lamb County

CCSJHighwayLet StatusLetting
Date
Contract
Cost
Fund
Cat
DescriptionDBE Goal
0052-05-047US 84ActualMay 2022$2,513,8028HAZARD ELIMINATION & SAFETY0.0

Lubbock County

CCSJHighwayLet StatusLetting
Date
Contract
Cost
Fund
Cat
DescriptionDBE Goal
0905-00-118VAActualFeb 2022$551,9681HIGHWAY IMPROVEMENT0.0
0905-00-112VAApprovedAug 2022$2,376,26411TRAFFIC SIGNAL IMPROVEMENTS0.0
0905-00-102VAActualMar 2022$1,260,11111HAZARD ELIMINATION & SAFETY0.0
0905-00-104VAActualFeb 2022$3,764,7431HAZARD ELIMINATION & SAFETY0.0
2740-02-016FM 2641ActualDec 2021$6,182,6291HIGHWAY IMPROVEMENT5.5
0053-01-130US 84ActualNov 2021$1,531,2671SEAL COAT0.0
0130-05-085US 62ActualFeb 2022$22,738,1473SURFACING/ROADWAY RESTORATION0.0
0905-00-109VAActualJan 2022$2,844,8921SURFACING/ROADWAY RESTORATION0.0

Swisher County

CCSJHighwayLet StatusLetting
Date
Contract
Cost
Fund
Cat
DescriptionDBE Goal
0067-02-074IH 27ActualNov 2021$16,785,9731SEAL COAT0.0
0302-04-022SH 86ActualApr 2022$2,034,7606BRIDGE REPLACEMENT6.5


Let StatusDefinition
TentativeEstimated letting date for this project
ApprovedProject has administrative approval to be let
ActualProject was let to contract