The Electronic State Business Daily (ESBD), the Electronic Bidding System, and the project proposal are the official sources of advertisement and bidding information for the State and Local Lettings. Bidders should bid the project using the information found therein, including any addenda. These sources take precedence over information from other sources, including TxDOT webpages, which are unofficial and intended for informational purposes only.

Hale County (FY 2021)

CCSJ: 0067-06-058

District:LUBBOCKLet Date:Aug 2020
Highway:IH 27Let Status:Tentative
Project ID:STP ( )HESCSJ:0067-06-058
Description:SAFETYHandling
Code:
 
Limits From:0.715 MI SOUTH OF SL 369Fund Cat:8
Limits To:0.185 MI NORTH OF SL 369ESTIMATE:$102,299
Length:0.7Actual$0
 
District:LUBBOCKLet Date:Aug 2020
Highway:US 180Let Status:Tentative
Project ID:STP ( )HESCSJ:0294-02-024
Description:SAFETYHandling
Code:
 
Limits From:0.860 MI EAST OF US 385Fund Cat:8
Limits To:1.270 MI EAST OF US 385ESTIMATE:$125,032
Length:0.4Actual$0
 
Proposal Request
Back...
Totals for 0067-06-058
Length:1.1
Estimate:$227,331
Actual:

CCSJ: 0905-12-044

District:LUBBOCKLet Date:Jul 2020
Highway:CRLet Status:Tentative
Project ID:BR 1802(835)CSJ:0905-12-044
Description:BRIDGE REPLACEMENTHandling
Code:
 
Limits From:1.15 MILES SOUTH OF US 70Fund Cat:6
Limits To:1.22 MILES SOUTH OF US 70ESTIMATE:$371,305
Length:0.0Actual$0
 
Proposal Request
Back...
Totals for 0905-12-044
Length:0
Estimate:$371,305
Actual:

Handling CodeDefinition
XXProject not processed through statewide letting
TRTransfer of funds
LCProject let through local entity
LCProject not charged against district apportionment



Let StatusDefinition
TentativeEstimated letting date for this project
ApprovedProject has administrative approval to be let