Detail Letting Schedule for Hall County (FY 2008)
|
Detail Letting Schedule for Hall County (FY 2008) |
|
Last Update: Monday, February 2, 2009 |
CCSJ: 0541-02-028
|
District: |
Childress |
Let Date: |
MAY 2008 |
Highway: |
SH 256 |
Let Status: |
Actual |
Project ID: |
STP 2008(575)HES |
CSJ: |
0541-02-028 |
Description: |
MODERNIZE BRIDGERAIL AND APPROACH & SAFETY TREAT FIXED |
Handling Code: |
|
Limits From: |
US 287 |
Fund Cat: |
8 |
Limits To: |
0.3 MILES EAST OF SH 70 |
Estimate: |
$542,171 |
Length: |
21.3 Miles |
Actual: |
$501,972 |
|
Back...
|
Totals for 0541-02-028 |
Length: |
21.3 Miles |
Estimate: |
$542,171 |
Actual: |
$501,972 |
CCSJ: 0925-09-024
|
District: |
Childress |
Let Date: |
DEC 2007 |
Highway: |
VA |
Let Status: |
Actual |
Project ID: |
CL 925-9-24 |
CSJ: |
0925-09-024 |
Description: |
LANDSCAPE |
Handling Code: |
|
Limits From: |
@ US 287 AND SH 86 |
Fund Cat: |
10 |
Limits To: |
. |
Estimate: |
$82,947 |
Length: |
0.1 Miles |
Actual: |
$94,273 |
|
Back...
|
Totals for 0925-09-024 |
Length: |
0.1 Miles |
Estimate: |
$82,947 |
Actual: |
$94,273 |
Handling Code |
Definition |
XX |
Project not processed through statewide letting |
TR |
Transfer of funds |
LC |
Project let through local entity |
NC |
Project not charged against district apportionment |
Let Status |
Definition |
Tentative |
Estimated letting date for this project |
Approved |
Project has administrative approval to be let |
Actual |
Project was let to contract |
|