Detail Letting Schedule for Collingsworth County (FY 2008)
|
Detail Letting Schedule for Collingsworth County (FY 2008) |
|
Last Update: Monday, February 2, 2009 |
Collingsworth County (FY 2008) |
CCSJ: 0031-04-043
|
District: |
Childress |
Let Date: |
DEC 2007 |
Highway: |
US 83 |
Let Status: |
Actual |
Project ID: |
STP 2008(204) |
CSJ: |
0031-03-035 |
Description: |
OVERLAY AND UNDERSEAL |
Handling Code: |
|
Limits From: |
S END OF RED RIVER BRIDGE, N |
Fund Cat: |
1 |
Limits To: |
LUTIE (SBL) |
Estimate: |
$1,970,648 |
Length: |
4.6 Miles |
Actual: |
$1,722,877 |
|
District: |
Childress |
Let Date: |
DEC 2007 |
Highway: |
US 83 |
Let Status: |
Actual |
Project ID: |
STP 2008(204) |
CSJ: |
0031-04-043 |
Description: |
OVERLAY AND UNDERSEAL |
Handling Code: |
|
Limits From: |
3.8 MILES S OF RED RIVER BRIDGE, N |
Fund Cat: |
1 |
Limits To: |
RED RIVER BRIDGE (SBL) |
Estimate: |
$1,414,194 |
Length: |
3.8 Miles |
Actual: |
$1,267,196 |
|
Back...
|
Totals for 0031-04-043 |
Length: |
8.4 Miles |
Estimate: |
$3,384,842 |
Actual: |
$2,990,073 |
Handling Code |
Definition |
XX |
Project not processed through statewide letting |
TR |
Transfer of funds |
LC |
Project let through local entity |
NC |
Project not charged against district apportionment |
Let Status |
Definition |
Tentative |
Estimated letting date for this project |
Approved |
Project has administrative approval to be let |
Actual |
Project was let to contract |
|