Tabulation of Bids for Project NH 2021(103)
This report will no longer be updated, please access links on the Contract Letting page.
The Electronic State Business Daily (ESBD), the Electronic Bidding System, and the project proposal are the official sources of advertisement and bidding information for the State and Local Lettings. Bidders should bid the project using the information found therein, including any addenda. These sources take precedence over information from other sources, including TxDOT webpages, which are unofficial and intended for informational purposes only.
Text version of this page | |||
County: | HARDEMAN | Let Date: | 11/04/20 |
Type: | MILL/INLAY | Seq No: | 3018 |
Time: | 31 WORKING DAYS | Project ID: | NH 2021(103) |
Highway: | US 287 | Contract #: | 11203018 |
Length: | 0.000 | CCSJ: | 0043-04-082 |
Limits: | |||
From: | FM 2568 (EAST), SOUTH | Check: | $43,000 |
To: | CHILLICOTHE WCL | Misc Cost: |
Estimate | $2,129,779.61 | % Over/Under | Company |
Bidder 1 | $1,952,687.34 | -8.32% | A. L. HELMCAMP, INC. |
Bidder 2 | $1,954,990.65 | -8.21% | ZACK BURKETT CO. |
Bidder 3 | $1,996,664.72 | -6.25% | RK HALL, LLC |
Bidder 4 | $2,058,510.30 | -3.35% | DUININCK, INC. |
Bidder 5 | $2,587,497.60 | +21.49% | GILVIN-TERRILL, LTD. |
Bidder 6 | $2,764,510.25 | +29.80% | J. LEE MILLIGAN, INC. |
Item Code | Description | Unit | Quantity | Unit Est. | Bidder | Unit Bid |
3546045 | PLANE ASPH CONC PAV (2") | SY | 117,907.000 | 1.80 | 1 2 3 4 5 6 | 1.700 2.500 1.490 2.100 2.000 2.750 |
5006001 | MOBILIZATION | LS | 1.000 | 144,669.00 | 1 2 3 4 5 6 | 150,000.000 160,000.000 60,000.000 200,000.000 250,000.000 270,000.000 |
5026001008 | BARRICADES, SIGNS AND TRAFFIC HANDLING | MO | 2.000 | 20,000.00 | 1 2 3 4 5 6 | 10,600.000 7,500.000 2,775.300 21,500.000 40,000.000 30,000.000 |
6626109 | WK ZN PAV MRK SHT TERM (TAB)TY W | EA | 9,302.000 | 1.00 | 1 2 3 4 5 6 | 0.700 1.000 1.500 1.400 4.000 1.250 |
6666036007 | REFL PAV MRK TY I (W)8"(SLD)(100MIL) | LF | 1,135.000 | 0.80 | 1 2 3 4 5 6 | 0.740 1.050 0.700 0.790 0.840 0.950 |
6666300007 | RE PM W/RET REQ TY I (W)4"(BRK)(100MIL) | LF | 15,503.000 | 0.35 | 1 2 3 4 5 6 | 0.420 0.600 0.400 0.400 0.420 0.470 |
6666303007 | RE PM W/RET REQ TY I (W)4"(SLD)(100MIL) | LF | 62,010.000 | 0.35 | 1 2 3 4 5 6 | 0.370 0.550 0.350 0.370 0.420 0.470 |
6666315007 | RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL) | LF | 26,400.000 | 0.35 | 1 2 3 4 5 6 | 0.380 0.550 0.360 0.400 0.420 0.470 |
6726007 | REFL PAV MRKR TY I-C | EA | 775.000 | 3.50 | 1 2 3 4 5 6 | 3.940 6.000 3.750 4.250 3.500 3.900 |
30766045 | D-GR HMA TY-D SAC-A PG70-28 | TON | 12,972.000 | 125.00 | 1 2 3 4 5 6 | 115.000 105.000 126.000 112.000 144.000 153.250 |
30766066 | TACK COAT | GAL | 11,624.560 | 3.50 | 1 2 3 4 5 6 | 3.000 3.750 4.000 3.400 4.000 3.650 |
61856002002 | TMA (STATIONARY) | DAY | 40.000 | 400.00 | 1 2 3 4 5 6 | 75.000 125.000 350.000 315.000 425.000 370.000 |
61856005002 | TMA (MOBILE OPERATION) | DAY | 6.000 | 900.00 | 1 2 3 4 5 6 | 250.000 250.000 900.000 1,000.000 950.000 85.000 |