The Electronic State Business Daily (ESBD), the Electronic Bidding System, and the project proposal are the official sources of advertisement and bidding information for the State and Local Lettings. Bidders should bid the project using the information found therein, including any addenda. These sources take precedence over information from other sources, including TxDOT webpages, which are unofficial and intended for informational purposes only.

Text version of this page
County:JACKSONLet Date:01/06/22
Type:SURFACING/ROADWAY RESTORATIONSeq No:3014
Time:180 WORKING DAYSProject ID:F 2022(258)
Highway:FM 616Contract #:01223014
Length:3.840CCSJ:0515-01-071
Limits: 
From:CR 325 (INEZ ROAD)Check:$77,000
To:FM 234Misc Cost:
Estimate$3,826,643.99% Over/UnderCompany
Bidder 1$3,684,181.70-3.72%BRANNAN PAVING CO., LTD.
Bidder 2$3,811,239.24-0.40%HUNTER INDUSTRIES, LTD.
Bidder 3$3,991,328.12+4.30%LCR TOTAL TRANSPORT LLC
Bidder 4$4,022,270.04+5.11%CK NEWBERRY, LLC
Bidder 5$4,176,129.24+9.13%GLENN FUQUA, INC.
Bidder 6$4,270,150.02+11.59%CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.
Item CodeDescriptionUnitQuantityUnit Est.BidderUnit Bid
1006002PREPARING ROWSTA0.50010,000.001
2
3
4
5
6
10,000.000
3,702.960
11,400.000
5,000.000
10,000.000
3,000.000
1046001REMOVING CONC (PAV)SY133.00015.001
2
3
4
5
6
19.890
16.650
19.250
50.000
23.000
50.000
1106001EXCAVATION (ROADWAY)CY2,675.00012.001
2
3
4
5
6
12.220
19.980
12.000
30.000
11.500
12.000
1126001SUBGRADE WIDENING (ORD COMP)STA187.490450.001
2
3
4
5
6
434.690
741.000
190.000
400.000
267.000
850.000
1326021EMBANKMENT (VEHICLE)(ORD COMP)(TY C)CY1,776.00025.001
2
3
4
5
6
22.130
19.710
12.000
15.000
16.000
16.000
1506002BLADINGHR75.000100.001
2
3
4
5
6
125.000
102.600
100.000
130.000
94.000
115.000
1646035DRILL SEEDING (PERM) (RURAL) (CLAY)SY62,897.0000.301
2
3
4
5
6
0.200
0.210
0.200
0.150
0.170
0.170
1646041DRILL SEEDING (TEMP) (WARM)SY15,724.0000.151
2
3
4
5
6
0.150
0.160
0.200
0.140
0.160
0.160
1646043DRILL SEEDING (TEMP) (COOL)SY15,724.0000.151
2
3
4
5
6
0.150
0.160
0.200
0.140
0.160
0.160
1686001VEGETATIVE WATERINGMG529.42025.001
2
3
4
5
6
22.000
16.650
45.000
16.000
20.000
10.000
2476057003FL BS (CMP IN PLC)(TYE GR1-2)(FNAL POS)CY14,836.00080.001
2
3
4
5
6
85.060
84.100
105.100
85.000
106.740
120.500
2476332003FL BS (RDWY DEL)(TY E GR 1-2)(FNL POS)CY1,144.00070.001
2
3
4
5
6
82.390
84.090
92.000
80.000
106.740
105.000
2606006LIME TRT (EXST MATL) (6")SY12,324.0002.501
2
3
4
5
6
6.390
3.190
3.000
3.000
3.300
8.000
2606043LIME (HYD, COM OR QK)(SLURRY)TON112.000200.001
2
3
4
5
6
176.000
173.250
250.000
240.000
153.750
200.000
2756001CEMENTTON501.000200.001
2
3
4
5
6
170.000
176.220
181.000
175.000
167.120
220.000
2756004CEMENT TREAT (MX EXST MTL & NW BS) (6")SY54,991.0003.001
2
3
4
5
6
1.470
2.280
1.450
1.250
1.460
1.750
3166029002ASPH (RC-250)GAL11,912.0004.501
2
3
4
5
6
4.000
4.590
3.950
4.500
6.300
4.500
3166202002AGGR(TY-E GR-5 SAC-B)CY426.000105.001
2
3
4
5
6
150.000
86.180
207.000
145.000
115.000
102.000
3166246002AGGR(TY-PE GR-3 SAC-B)CY701.000100.001
2
3
4
5
6
127.000
100.630
133.000
130.000
110.000
110.000
3166249002AGGR(TY-PE GR-4 SAC-B)CY556.000100.001
2
3
4
5
6
119.480
100.630
120.000
105.000
110.000
110.000
3166400002ASPH (AC-15P OR AC-10-2TR OR CRS-2P)GAL48,422.0004.001
2
3
4
5
6
3.410
3.950
3.850
3.500
4.670
3.350
3516004FLEXIBLE PAVEMENT STRUCTURE REPAIR(8")SY15.00065.001
2
3
4
5
6
400.000
192.720
90.000
500.000
100.000
225.000
3546049PLANE ASPH CONC PAV (6")SY13,730.0006.001
2
3
4
5
6
6.000
3.900
3.900
3.750
5.250
2.000
4006005CEM STABIL BKFLCY42.700120.001
2
3
4
5
6
95.000
238.860
114.000
200.000
164.000
150.000
4006006CUT & RESTORING PAVSY104.000150.001
2
3
4
5
6
50.000
300.000
56.000
125.000
200.000
200.000
4016001FLOWABLE BACKFILLCY5.000250.001
2
3
4
5
6
292.000
252.960
108.000
300.000
300.000
300.000
4026001TRENCH EXCAVATION PROTECTIONLF120.0008.001
2
3
4
5
6
20.000
42.290
23.000
10.000
15.000
15.000
4326002RIPRAP (CONC)(5 IN)CY8.000475.001
2
3
4
5
6
495.000
843.710
415.000
600.000
650.000
650.000
4506018001RAIL (TY T631)LF332.680125.001
2
3
4
5
6
77.000
98.350
97.500
150.000
100.000
100.000
4606003CMP (GAL STL 24 IN)LF12.000135.001
2
3
4
5
6
126.670
131.120
95.000
140.000
125.000
125.000
4606023CMP (GAL STL 15 IN)LF20.000100.001
2
3
4
5
6
118.000
97.430
70.000
105.000
85.000
85.000
4626003002CONC BOX CULV (4 FT X 2 FT)LF80.000450.001
2
3
4
5
6
541.890
735.280
332.000
650.000
800.000
800.000
4626007002CONC BOX CULV (5 FT X 3 FT)LF40.000570.001
2
3
4
5
6
709.500
886.010
495.000
775.000
900.000
900.000
4646002001RC PIPE (CL III)(15 IN)LF120.00095.001
2
3
4
5
6
87.410
76.130
63.000
85.000
60.000
60.000
4646003001RC PIPE (CL III)(18 IN)LF68.000110.001
2
3
4
5
6
118.280
81.180
68.000
90.000
70.000
70.000
4646005001RC PIPE (CL III)(24 IN)LF84.000120.001
2
3
4
5
6
129.270
106.170
78.000
115.000
145.000
145.000
4656005001JCTBOX(COMPL)(PJB)(3FTX3FT)EA1.0006,000.001
2
3
4
5
6
3,775.000
4,529.020
4,220.000
5,500.000
5,500.000
5,500.000
4656146001INLET(COMPL)(PSL)(SFG)(3FTX3FT-3FTX3FT)EA1.0006,500.001
2
3
4
5
6
3,338.000
5,911.710
5,175.000
6,500.000
5,000.000
5,000.000
4676139SET (TY I)(S= 4 FT)(HW= 3 FT)(4:1) (C)EA4.0006,500.001
2
3
4
5
6
8,757.500
10,334.150
5,620.000
11,000.000
8,500.000
8,500.000
4676177SET (TY I)(S= 5 FT)(HW= 4 FT)(4:1) (C)EA2.0007,000.001
2
3
4
5
6
10,949.500
13,285.290
7,740.000
15,000.000
10,000.000
10,000.000
4676333SET (TY II) (15 IN) (CMP) (6: 1) (P)EA4.000950.001
2
3
4
5
6
1,325.000
1,531.120
1,140.000
1,700.000
1,000.000
1,000.000
4676341SET (TY II) (15 IN) (RCP) (6: 1) (P)EA10.0001,000.001
2
3
4
5
6
1,325.000
1,519.380
1,105.000
1,700.000
1,200.000
1,200.000
4676363SET (TY II) (18 IN) (RCP) (6: 1) (P)EA8.0001,800.001
2
3
4
5
6
1,412.500
1,913.400
1,305.000
2,100.000
1,600.000
1,600.000
4676380SET (TY II) (24 IN) (CMP) (6: 1) (P)EA2.0002,100.001
2
3
4
5
6
1,500.000
2,039.780
1,415.000
2,300.000
2,000.000
2,000.000
4676395SET (TY II) (24 IN) (RCP) (6: 1) (P)EA8.0002,250.001
2
3
4
5
6
1,500.000
2,220.330
1,460.000
2,500.000
2,500.000
2,500.000
4966002REMOV STR (INLET)EA1.000600.001
2
3
4
5
6
480.000
975.750
1,025.000
1,500.000
750.000
750.000
4966042REMOV STR (SMALL)EA9.0001,500.001
2
3
4
5
6
540.000
1,393.990
815.000
1,500.000
1,000.000
1,000.000
5006001MOBILIZATIONLS1.000343,000.001
2
3
4
5
6
209,400.000
380,765.100
363,000.000
350,000.000
334,000.000
250,000.000
5026001008BARRICADES, SIGNS AND TRAFFIC HANDLINGMO12.0004,500.001
2
3
4
5
6
3,200.000
5,800.000
750.000
10,000.000
2,100.000
3,000.000
5066001005ROCK FILTER DAMS (INSTALL) (TY 1)LF390.00050.001
2
3
4
5
6
33.000
35.470
26.750
33.000
25.000
25.000
5066011005ROCK FILTER DAMS (REMOVE)LF390.00015.001
2
3
4
5
6
12.000
12.900
9.600
12.000
9.000
9.000
5066038005TEMP SEDMT CONT FENCE (INSTALL)LF490.0005.001
2
3
4
5
6
5.000
5.370
4.250
5.000
4.000
4.000
5066039005TEMP SEDMT CONT FENCE (REMOVE)LF490.0002.001
2
3
4
5
6
2.000
2.150
1.100
2.000
1.000
1.000
5306004DRIVEWAYS (CONC)SY133.00095.001
2
3
4
5
6
88.180
97.330
81.000
125.000
150.000
150.000
5306006DRIVEWAYS (SURF TREAT)SY1,436.00035.001
2
3
4
5
6
38.460
30.660
28.500
25.000
35.000
23.250
5406001001MTL W-BEAM GD FEN (TIM POST)LF1,042.32032.001
2
3
4
5
6
25.250
24.860
29.600
30.000
26.000
26.000
5426001REMOVE METAL BEAM GUARD FENCELF1,025.0004.001
2
3
4
5
6
1.250
1.310
2.600
2.000
0.950
0.950
5446001GUARDRAIL END TREATMENT (INSTALL)EA8.0002,900.001
2
3
4
5
6
3,240.000
2,814.680
3,535.000
3,500.000
3,250.000
3,250.000
5446003GUARDRAIL END TREATMENT (REMOVE)EA8.000250.001
2
3
4
5
6
350.000
328.900
335.000
400.000
160.000
160.000
6446004IN SM RD SN SUP&AM TY10BWG(1)SA(T)EA1.000600.001
2
3
4
5
6
735.000
735.000
790.000
850.000
742.000
750.000
6446007IN SM RD SN SUP&AM TY10BWG(1)SA(U)EA1.000750.001
2
3
4
5
6
795.000
795.000
850.000
925.000
850.000
850.000
6446060IN SM RD SN SUP&AM TYTWT(1)WS(P)EA61.000450.001
2
3
4
5
6
400.000
400.000
428.000
500.000
365.000
365.000
6446061IN SM RD SN SUP&AM TYTWT(1)WS(T)EA6.000500.001
2
3
4
5
6
480.000
480.000
515.000
550.000
460.000
460.000
6446076REMOVE SM RD SN SUP&AMEA69.000100.001
2
3
4
5
6
75.000
75.000
80.250
100.000
60.000
60.000
6586047INSTL OM ASSM (OM-2Y)(WC)GNDEA6.00075.001
2
3
4
5
6
65.000
65.000
70.000
115.000
65.000
65.000
6586062INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)EA40.00035.001
2
3
4
5
6
32.000
32.000
34.000
50.000
40.000
40.000
6626032WK ZN PAV MRK NON-REMOV (Y)4"(BRK)LF16,233.0000.251
2
3
4
5
6
0.340
0.150
0.500
0.500
0.300
0.150
6626034WK ZN PAV MRK NON-REMOV (Y)4"(SLD)LF16,041.0000.251
2
3
4
5
6
0.340
0.150
0.500
0.500
0.300
0.150
6626111WK ZN PAV MRK SHT TERM (TAB)TY Y-2EA5,675.0002.001
2
3
4
5
6
1.500
1.610
1.700
0.750
1.500
1.000
6666303007RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)LF7,880.0000.351
2
3
4
5
6
0.380
0.520
0.600
0.650
0.500
0.520
6666312007RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL)LF986.0000.351
2
3
4
5
6
0.380
0.540
0.600
0.650
0.500
0.540
6666315007RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)LF1,425.0000.351
2
3
4
5
6
0.380
0.520
0.600
0.650
0.500
0.520
6666342007REF PROF PAV MRK TY I(W)4"(SLD)(100MIL)LF37,680.0000.801
2
3
4
5
6
0.620
0.720
0.900
0.900
1.150
0.720
6666344007REF PROF PAV MRK TY I(Y)4"(BRK)(100MIL)LF4,425.0000.801
2
3
4
5
6
0.750
0.790
0.900
0.900
1.150
0.790
6666345007REF PROF PAV MRK TY I(Y)4"(SLD)(100MIL)LF3,922.0000.801
2
3
4
5
6
0.750
0.720
0.900
0.900
1.150
0.720
6686076PREFAB PAV MRK TY C (W) (24") (SLD)LF80.00020.001
2
3
4
5
6
13.400
17.000
16.000
20.000
10.000
17.000
6726009REFL PAV MRKR TY II-A-AEA337.0004.501
2
3
4
5
6
3.900
4.400
5.400
5.500
5.000
4.400
30766002D-GR HMA TY-B SAC-B PG64-22TON3,021.000125.001
2
3
4
5
6
120.000
81.420
114.000
135.000
122.000
110.000
30766042D-GR HMA TY-D SAC-B PG70-22TON1,511.000125.001
2
3
4
5
6
135.000
95.070
133.000
145.000
122.000
117.000
60016002PORTABLE CHANGEABLE MESSAGE SIGNEA2.00010,000.001
2
3
4
5
6
12,500.000
7,698.010
7,500.000
7,500.000
8,500.000
5,000.000
61856002002TMA (STATIONARY)DAY20.000250.001
2
3
4
5
6
200.000
513.200
315.000
300.000
750.000
275.000
61856005002TMA (MOBILE OPERATION)DAY20.000250.001
2
3
4
5
6
150.000
769.800
375.000
100.000
750.000
275.000