Monthly Local Let Maintenance Report For Tyler District As Of Sep 10, 2018 Page 3 Of 4

Last Update: Monday, September 10, 2018
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountySMITH
HighwayUS0069
FromTYLER MTCE SECTION
ToSMITH COUNTY
CSJ6317-87-001
Proj IDSUP - 631787001
Work TypeLITTER REMOVAL
 
0.001437147.58205081.2746.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-17
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged365
Percent Time Used50
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6317-87-001
RUCON, INC. (0.00)
Contract #07171047
Totals437147.5810590.33205081.2746.9

CountyANDERSON
HighwayUS0084
FromPALESTINE MTCE. SECTION
ToANDERSON CO.
CSJ6317-88-001
Proj IDSUP - 631788001
Work TypeLITTER REMOVAL
 
0.001198530.4381378.6840.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-17
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged363
Percent Time Used49
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6317-88-001
RUCON, INC. (0.00)
Contract #07171048
Totals198530.430.0081378.6840.9

CountyWOOD
HighwayUS0069
FromMINEOLA MTCE. SECTION
ToWOOD CO.
CSJ6317-89-001
Proj IDSUP - 631789001
Work TypeLITTER REMOVAL
 
0.001190421.1796104.0250.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-17
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged363
Percent Time Used49
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6317-89-001
RUCON, INC. (100.00)
Contract #07171049
Totals190421.1710290.2396104.0250.4

CountySMITH
HighwaySH0031
FromTYLER DISTRICT OFFICE
To2709 W FRONT STREET
CSJ6317-90-001
Proj IDSUP - 631790001
Work TypeLAWN MAINTENANCE
 
0.00199968.0033086.0033.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began11-07-17
Work Completed
Time Computed00-00-00
Contract Working Days669
Addl Days Granted0
Working Days Charged304
Percent Time Used45
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6317-90-001
RUCON, INC. (100.00)
Contract #10171030
Totals99968.003816.0033086.0033.0

CountyGREGG
HighwaySH0042
FromSH 149, FM 349, SH 42, FM 2204
ToLONGVIEW MTCE., GREGG CO.
CSJ6318-12-001
Proj IDBPM - 631812001
Work TypeBRIDGE PREVENTIVE MAINTENANCE
 
0.001210592.00208494.4099.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began05-08-18
Work Completed
Time Computed00-00-00
Contract Working Days77
Addl Days Granted0
Working Days Charged64
Percent Time Used83
Contractor(s)
CHAMPION INFRASTRUCTURE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6318-12-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02181002
Totals210592.000.00208494.4099.0

CountyGREGG
HighwayUS0259
FromUS 259 NB, SS 502, SH 42, FM 2605
ToLONGVIEW MTCE., GREGG CO
CSJ6318-13-001
Proj IDBPM - 631813001
Work TypeBRIDGE PREVENTIVE MAINTENANCE
 
0.001167859.50158693.5095.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began05-04-18
Work Completed
Time Computed00-00-00
Contract Working Days77
Addl Days Granted0
Working Days Charged81
Percent Time Used105
Contractor(s)
RED BARON BUILDING COMPANY, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 6318-13-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02181004
Totals167859.5034603.50158693.5095.9

CountyHENDERSON
HighwaySH0031
FromVARIOUS ROADWAYS IN
ToHENDERSON COUNTY
CSJ6322-35-001
Proj IDRMC - 632235001
Work TypeROW MOWING
 
0.001321517.13174123.1055.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began06-07-18
Work Completed
Time Computed00-00-00
Contract Working Days57
Addl Days Granted0
Working Days Charged35
Percent Time Used61
Contractor(s)
C & C MOWING CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6322-35-001
MPR SERVICES (11.83)
Contract #12171001
Totals321517.130.00174123.1055.0

CountyVAN ZANDT
HighwaySH0064
FromVARIOUS ROADWAYS IN
ToVAN ZANDT COUNTY
CSJ6322-36-001
Proj IDRMC - 632236001
Work TypeROW MOWING
 
0.001221324.62120554.0854.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began06-04-18
Work Completed
Time Computed00-00-00
Contract Working Days49
Addl Days Granted0
Working Days Charged23
Percent Time Used46
Contractor(s)
SERNA CONTRACTORS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6322-36-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12171002
Totals221324.620.00120554.0854.4

CountyRUSK
HighwayUS0259
FromVARIOUS ROADWAYS IN
ToRUSK COUNTY
CSJ6322-37-001
Proj IDRMC - 632237001
Work TypeROW MOWING
 
0.001250239.70136467.7055.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began06-09-18
Work Completed
Time Computed00-00-00
Contract Working Days55
Addl Days Granted0
Working Days Charged33
Percent Time Used60
Contractor(s)
SERVIN MOWING
SUBCONTRACTOR(S) FOR CCSJ: 6322-37-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12171003
Totals250239.700.00136467.7055.2

CountyCHEROKEE
HighwayUS0069
FromVARIOUS ROADWAYS IN
ToCHEROKEE COUNTY
CSJ6322-38-001
Proj IDRMC - 632238001
Work TypeROW MOWING
 
0.001175012.2987800.5753.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began06-12-18
Work Completed
Time Computed00-00-00
Contract Working Days51
Addl Days Granted0
Working Days Charged36
Percent Time Used70
Contractor(s)
SERVIN MOWING
SUBCONTRACTOR(S) FOR CCSJ: 6322-38-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12171004
Totals175012.290.0087800.5753.2

CountyGREGG
HighwayUS0259
FromVARIOUS ROADWAYS IN
ToGREGG COUNTY
CSJ6322-39-001
Proj IDRMC - 632239001
Work TypeROW MOWING
 
0.001100165.8855613.6255.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began05-29-18
Work Completed
Time Computed00-00-00
Contract Working Days33
Addl Days Granted0
Working Days Charged14
Percent Time Used42
Contractor(s)
SERVIN MOWING
SUBCONTRACTOR(S) FOR CCSJ: 6322-39-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12171005
Totals100165.880.0055613.6255.5

CountyWOOD
HighwayUS0080
FromVARIOUS ROADWAYS IN
ToWOOD COUNTY
CSJ6322-40-001
Proj IDRMC - 632240001
Work TypeROW MOWING
 
0.001283232.84155873.8155.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began06-09-18
Work Completed
Time Computed00-00-00
Contract Working Days53
Addl Days Granted0
Working Days Charged28
Percent Time Used52
Contractor(s)
CROSS PLUS CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6322-40-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12171006
Totals283232.840.00155873.8155.0

CountyANDERSON
HighwayUS0079
FromVARIOUS ROADWAYS IN
ToANDERSON COUNTY
CSJ6322-41-001
Proj IDRMC - 632241001
Work TypeROW MOWING
 
0.001237948.56130664.8654.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began06-05-18
Work Completed
Time Computed00-00-00
Contract Working Days49
Addl Days Granted0
Working Days Charged21
Percent Time Used42
Contractor(s)
LAWRENCE W. SIMS
SUBCONTRACTOR(S) FOR CCSJ: 6322-41-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12171007
Totals237948.560.00130664.8654.9

CountySMITH
HighwaySH0110
FromVARIOUS ROADWAYS IN
ToSMITH COUNTY
CSJ6322-42-001
Proj IDRMC - 632242001
Work TypeROW MOWING
 
0.001293975.78156640.6453.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began05-29-18
Work Completed
Time Computed00-00-00
Contract Working Days51
Addl Days Granted0
Working Days Charged22
Percent Time Used43
Contractor(s)
JASCO
SUBCONTRACTOR(S) FOR CCSJ: 6322-42-001
MPR SERVICES (6.72)
Contract #12171008
Totals293975.780.00156640.6453.2

CountySMITH
HighwayIH0020
FromAT FM 849 JCT IH 20
ToSMITH CO.
CSJ6326-75-001
Proj IDEMC - 632675001
Work TypeEMERGENCY REPLACEMNT FM 849/IH 20 BRIDGE
 
1.2944639021.794740928.2099.9
Work Order12-06-17
Work Began12-07-17
Work Completed
Time Computed12-07-17
Contract Working Days193
Addl Days Granted0
Working Days Charged142
Percent Time Used73
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6326-75-001
BREDA COMPANY, INC. (0.09)
Contract #11171040
Totals4639021.790.004740928.2099.9

CountyANDERSON
HighwayUS0287
FromUS 287, SH 155 NB, FM 3232, FM 3309
ToPALESTINE MTCE. ANDERSON CO.
CSJ6326-87-001
Proj IDRMC - 632687001
Work TypeBRIDGE PREVENTIVE MAINTENANCE
 
0.001232132.65258974.50100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began04-23-18
Work Completed08-23-18
Time Computed00-00-00
Contract Working Days77
Addl Days Granted12
Working Days Charged103
Percent Time Used115
Contractor(s)
RED BARON BUILDING COMPANY, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 6326-87-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02181003
Totals232132.6530750.00258974.50100.0

CountyCHEROKEE
HighwayUS0069
FromRUSK STATE HOSPITAL
ToCHEROKEE CO
CSJ6328-26-001
Proj IDRMC - 632826001
Work TypePAVEMENT AND SIDEWALK REPAIRS
 
0.010297250.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days761
Addl Days Granted0
Working Days Charged29
Percent Time Used3
Contractor(s)
IIPL USA LLC
SUBCONTRACTOR(S) FOR CCSJ: 6328-26-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06181001
Totals297250.000.000.000.0

CountyWOOD
HighwayUS0080
FromVARIOUS ROADWAYS IN
ToWOOD AND VANZANDT COUNTIES
CSJ6330-92-001
Proj IDRMC - 633092001
Work TypeGUARDRAIL REPAIR
 
0.010189884.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
CATOCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6330-92-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06181002
Totals189884.000.000.000.0

CountyHENDERSON
HighwaySH0031
FromATHENS MTCE SECTION
ToHENDERSON CO.
CSJ6331-79-001
Proj IDSUP - 633179001
Work TypeLANDSCAPE ROW MTCE.
 
0.01021774.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TIBH INDUSTRIES, INC.
ANDREWS DIVERSIFIED INDUSTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6331-79-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06181030
Totals21774.000.000.000.0

CountyHENDERSON
HighwaySH0031
FromATHEN MTCE. OFFICE
ToHENDERSON CO.
CSJ6331-80-001
Proj IDSUP - 633180001
Work TypeLAWN MTCE.
 
0.01016782.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TIBH INDUSTRIES, INC.
ANDREWS DIVERSIFIED INDUSTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6331-80-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06181031
Totals16782.000.000.000.0

page 1 | page 2 | page 3 | page 4