Monthly Local Let Maintenance Report For Lufkin District As Of Apr 10, 2018 Page 4 Of 5

Last Update: Friday, April 20, 2018
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountySAN AUGUSTINE
HighwayUS0096
FromVARIOUS LOCATIONS IN SAN AUGUSTINE
ToCOUNTY MAINTENANCE SECTION
CSJ6319-55-001
Proj IDSUP - 631955001
Work TypeDELINEATOR, OBJ MRK & MAILBOX MAINT
 
0.010180000.00100262.0055.7
Work Order08-30-17
Work Began09-01-17
Work Completed
Time Computed09-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged212
Percent Time Used58
Contractor(s)
TIBH INDUSTRIES, INC.
GATEWAY COMMUNITY PARTNERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6319-55-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08171110
Totals180000.0012990.00100262.0055.7

CountySABINE
HighwayUS0096
FromVARIOUS LOCATION IN SABINE COUNTY
ToMAINTENANCE SECTION
CSJ6319-56-001
Proj IDSUP - 631956001
Work TypeDELINEATOR, OBJ MRK & MAILBOX MAINT
 
0.010182000.0051249.0028.1
Work Order08-28-17
Work Began09-01-17
Work Completed
Time Computed09-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged212
Percent Time Used58
Contractor(s)
TIBH INDUSTRIES, INC.
GATEWAY COMMUNITY PARTNERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6319-56-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08171108
Totals182000.005195.0051249.0028.1

CountyNACOGDOCHES
HighwayUS0059
FromVARIOUS LOCATIONS IN NACOGDOCHES
ToCOUNTY
CSJ6319-57-001
Proj IDSUP - 631957001
Work TypeCURB AND GUTTER MAINTENANCE
 
0.01046744.3215080.9632.2
Work Order08-28-17
Work Began09-01-17
Work Completed
Time Computed09-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged212
Percent Time Used58
Contractor(s)
TIBH INDUSTRIES, INC.
GATEWAY COMMUNITY PARTNERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6319-57-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08171105
Totals46744.320.0015080.9632.2

CountySHELBY
HighwaySH0007
FromVARIOUS LOCATIONS IN SHELBY COUNTY
ToMAINTENANCE SECTION
CSJ6321-56-001
Proj IDRMC - 632156001
Work TypeTREE & BRUSH REMOVAL AND TREE TRIMMING
 
0.010257604.000.000.0
Work Order00-00-00
Work Began10-16-17
Work Completed
Time Computed10-16-17
Contract Working Days200
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
CROSS PLUS CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6321-56-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09171110
Totals257604.000.000.000.0

CountyTRINITY
HighwaySH0019
FromVARIOUS LOCATIONS IN TRINITY COUNTY
ToMAINTENANCE SECTION
CSJ6321-57-001
Proj IDRMC - 632157001
Work TypeGUARD FENCE, ATTENUATOR, & MTL RAIL REP
 
0.010160600.2024705.0015.3
Work Order00-00-00
Work Began10-16-17
Work Completed
Time Computed10-16-17
Contract Working Days200
Addl Days Granted0
Working Days Charged7
Percent Time Used3
Contractor(s)
ACE CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6321-57-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09171111
Totals160600.2010200.0024705.0015.3

CountyTRINITY
HighwaySH0019
FromVARIOUS LOCATIONS IN TRINITY COUNTY
ToMAINTENANCE SECTION
CSJ6322-97-001
Proj IDRMC - 632297001
Work TypeCULVERT CLEANING AND REPLACEMENT
 
0.010134140.000.000.0
Work Order03-05-18
Work Began03-05-18
Work Completed
Time Computed03-05-18
Contract Working Days80
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
L.C. JORDAN & SON
SUBCONTRACTOR(S) FOR CCSJ: 6322-97-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01181108
Totals134140.000.000.000.0

CountyHOUSTON
HighwayUS0287
FromVARIOUS LOCATIONS IN HOUSTON, POLK,
ToSAN JACINTO, & TRINITY COUNTY MAINT SEC
CSJ6322-99-001
Proj IDRMC - 632299001
Work TypeCRACK SEALING
 
0.01093890.3895361.4499.9
Work Order01-08-18
Work Began01-09-18
Work Completed
Time Computed01-09-18
Contract Working Days40
Addl Days Granted0
Working Days Charged25
Percent Time Used62
Contractor(s)
D & M CONTRACTORS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6322-99-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10171111
Totals93890.3895361.4495361.4499.9

CountyANGELINA
HighwayUS0059
FromANGELINA COUNTY MAINTENANCE
ToOFFICE
CSJ6323-23-001
Proj IDSUP - 632323001
Work TypeJANITORIAL MAINTENANCE
 
0.0107402.004095.0055.3
Work Order08-25-17
Work Began09-01-17
Work Completed
Time Computed09-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged212
Percent Time Used58
Contractor(s)
TIBH INDUSTRIES, INC.
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6323-23-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08171102
Totals7402.00585.004095.0055.3

CountySABINE
HighwaySH0087
FromVARIOUS LOCATIONS IN SABINE COUNTY
ToMAINTENANCE SECTION
CSJ6323-36-001
Proj IDRMC - 632336001
Work TypeDITCH AND CULVERT CLEANING
 
0.010152028.8049993.1632.8
Work Order12-01-17
Work Began12-11-17
Work Completed
Time Computed12-04-17
Contract Working Days60
Addl Days Granted0
Working Days Charged11
Percent Time Used18
Contractor(s)
TEXAS DRAINAGE INC.
SUBCONTRACTOR(S) FOR CCSJ: 6323-36-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10171113
Totals152028.800.0049993.1632.8

CountyANGELINA
HighwayUS0059
FromVARIOUS LOCATIONS
ToDISTRICT WIDE
CSJ6323-73-001
Proj IDRMC - 632373001
Work TypeINSTALLATION OF SPOT PAINT STRIPING
 
0.001262850.0074017.6128.1
Work Order01-11-18
Work Began01-23-18
Work Completed
Time Computed01-18-18
Contract Working Days365
Addl Days Granted0
Working Days Charged73
Percent Time Used20
Contractor(s)
STRIPING TECHNOLOGY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6323-73-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11171101
Totals262850.0051012.7374017.6128.1

CountyANGELINA
HighwayUS0059
FromVARIOUS LOCATIONS
ToDISTRICT WIDE
CSJ6323-74-001
Proj IDRMC - 632374001
Work TypeILLUMINATION
 
0.001362700.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-04-18
Work Began00-00-00
Work Completed
Time Computed04-11-18
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
BAY CITY TRAFFIC
SUBCONTRACTOR(S) FOR CCSJ: 6323-74-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12171102
Totals362700.000.000.000.0

CountyHOUSTON
HighwayUS0287
FromVARIOUS LOCATIONS WITHIN
ToHOUSTON COUNTY
CSJ6323-79-001
Proj IDSUP - 632379001
Work TypeREMOVAL AND DISPOSAL OF LITTER ON ROW
 
0.01076786.7527007.7935.1
Work Order10-01-17
Work Began10-01-17
Work Completed
Time Computed10-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged182
Percent Time Used49
Contractor(s)
TIBH INDUSTRIES, INC.
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6323-79-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09171131
Totals76786.755777.8327007.7935.1

CountyANGELINA
HighwayUS0059
FromVARIOUS LOCATIONS IN
ToANGELINA COUNTY
CSJ6323-80-001
Proj IDSUP - 632380001
Work TypeREMOVAL AND DISPOSAL OF LITTER ON ROW
 
0.01046667.8315632.0133.4
Work Order11-30-17
Work Began12-01-17
Work Completed
Time Computed12-01-17
Contract Working Days304
Addl Days Granted0
Working Days Charged121
Percent Time Used39
Contractor(s)
TIBH INDUSTRIES, INC.
GATEWAY COMMUNITY PARTNERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6323-80-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11171130
Totals46667.836334.5215632.0133.4

CountyNACOGDOCHES
HighwayUS0059
FromVARIOUS LOCATIONS IN
ToNACOGDOCHES COUNTY
CSJ6323-81-001
Proj IDSUP - 632381001
Work TypeREMOVAL AND DISPOSAL OF LITTER ON ROW
 
0.010112955.4529958.3626.5
Work Order10-01-17
Work Began10-01-17
Work Completed
Time Computed10-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged151
Percent Time Used41
Contractor(s)
TIBH INDUSTRIES, INC.
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6323-81-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09171130
Totals112955.456332.7329958.3626.5

CountySABINE
HighwayUS0096
FromVARIOUS LOCATIONS WITHIN
ToSABINE COUNTY
CSJ6323-82-001
Proj IDSUP - 632382001
Work TypeREMOVAL AND DISPOSAL OF LITTER ON ROW
 
0.01043881.5115751.5035.8
Work Order10-01-17
Work Began10-01-17
Work Completed
Time Computed10-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged182
Percent Time Used49
Contractor(s)
TIBH INDUSTRIES, INC.
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6323-82-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09171134
Totals43881.511367.8515751.5035.8

CountySHELBY
HighwayUS0059
FromVARIOUS LOCATIONS IN
ToSHELBY COUNTY
CSJ6323-83-001
Proj IDSUP - 632383001
Work TypeREMOVAL AND DISPOSAL OF LITTER ON ROW
 
0.010110489.4748339.9143.7
Work Order10-01-17
Work Began10-01-17
Work Completed
Time Computed10-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged182
Percent Time Used49
Contractor(s)
TIBH INDUSTRIES, INC.
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6323-83-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09171137
Totals110489.479098.6848339.9143.7

CountyTRINITY
HighwaySH0019
FromVARIOUS LOCATIONS IN
ToTRINITY COUNTY
CSJ6323-84-001
Proj IDSUP - 632384001
Work TypeREMOVAL AND DISPOSAL OF LITTER ON ROW
 
0.01048598.6020281.9741.7
Work Order10-01-17
Work Began10-01-17
Work Completed
Time Computed10-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged182
Percent Time Used49
Contractor(s)
TIBH INDUSTRIES, INC.
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6323-84-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09171136
Totals48598.603356.2320281.9741.7

CountyPOLK
HighwayUS0059
FromVARIOUS LOCATIONS IN
ToPOLK COUNTY
CSJ6323-85-001
Proj IDSUP - 632385001
Work TypeREMOVAL AND DISPOSAL OF LITTER ON ROW
 
0.010120233.7265198.5054.2
Work Order10-01-17
Work Began10-01-17
Work Completed
Time Computed10-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged182
Percent Time Used49
Contractor(s)
TIBH INDUSTRIES, INC.
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6323-85-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09171133
Totals120233.7215265.4165198.5054.2

CountySAN AUGUSTINE
HighwayUS0096
FromVARIOUS LOCATIONS IN
ToSAN AUGUSTINE COUNTY
CSJ6323-86-001
Proj IDSUP - 632386001
Work TypeREMOVAL AND DISPOSAL OF LITTER ON ROW
 
0.01088032.7420547.2923.3
Work Order10-01-17
Work Began10-01-17
Work Completed
Time Computed10-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged182
Percent Time Used49
Contractor(s)
TIBH INDUSTRIES, INC.
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6323-86-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09171132
Totals88032.745554.6520547.2923.3

CountySAN JACINTO
HighwayUS0059
FromVARIOUS LOCATIONS IN
ToSAN JACINTO COUNTY
CSJ6323-87-001
Proj IDSUP - 632387001
Work TypeREMOVAL AND DISPOSAL OF LITTER ON ROW
 
0.01082202.5741339.1250.2
Work Order10-01-17
Work Began10-01-17
Work Completed
Time Computed10-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged182
Percent Time Used49
Contractor(s)
TIBH INDUSTRIES, INC.
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6323-87-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09171135
Totals82202.579481.0441339.1250.2

page 1 | page 2 | page 3 | page 4 | page 5