Monthly Local Let Maintenance Report For Beaumont District As Of Apr 10, 2018 Page 4 Of 5

Last Update: Friday, April 20, 2018
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyNEWTON
HighwayUS0190
FromUS 190
ToUS 190
CSJ6324-08-001
Proj IDSUP - 632408001
Work TypeNEWTON GROUNDS
 
1.00010422.142227.1221.3
Work Order10-01-17
Work Began10-01-17
Work Completed
Time Computed10-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged182
Percent Time Used49
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6324-08-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09172007
Totals10422.14482.062227.1221.3

CountyJASPER
HighwayUS0190
FromUS 190
ToUS 190
CSJ6324-09-001
Proj IDSUP - 632409001
Work TypeJASPER GROUNDS
 
1.00011487.453874.2033.7
Work Order10-01-17
Work Began10-01-17
Work Completed
Time Computed10-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged182
Percent Time Used49
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6324-09-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09172008
Totals11487.45865.103874.2033.7

CountyJEFFERSON
HighwayUS0069
FromUS 69
ToUS 69
CSJ6324-10-001
Proj IDSUP - 632410001
Work TypeDMV GROUNDS
 
1.0005217.00691.0013.2
Work Order11-01-17
Work Began11-01-17
Work Completed
Time Computed11-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged151
Percent Time Used41
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6324-10-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09172009
Totals5217.00438.00691.0013.2

CountyORANGE
HighwaySH0062
FromSH 62
ToSH 62
CSJ6324-11-001
Proj IDSUP - 632411001
Work TypeORANGE GROUNDS
 
1.0009405.001980.0021.0
Work Order11-01-17
Work Began00-00-00
Work Completed
Time Computed11-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged151
Percent Time Used41
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6324-11-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09172010
Totals9405.00990.001980.0021.0

CountyJEFFERSON
HighwayUS0069
FromUS 69
ToUS 69
CSJ6324-12-001
Proj IDSUP - 632412001
Work TypeDISTRICT GROUNDS
 
1.00040571.005973.0014.7
Work Order11-01-17
Work Began11-01-17
Work Completed
Time Computed11-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged151
Percent Time Used41
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6324-12-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09172011
Totals40571.003899.005973.0014.7

CountyTYLER
HighwayUS0069
FromUS 69
ToUS 69
CSJ6324-13-001
Proj IDSUP - 632413001
Work TypeWOODVILLE PICNIC
 
1.00038898.7013128.9833.7
Work Order11-01-17
Work Began11-01-17
Work Completed
Time Computed11-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged151
Percent Time Used41
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6324-13-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09172012
Totals38898.702437.8613128.9833.7

CountyNEWTON
HighwayUS0190
FromUS 190
ToUS 190
CSJ6324-14-001
Proj IDSUP - 632414001
Work TypeNEWTON PICNIC
 
1.00019211.966409.1433.3
Work Order11-01-17
Work Began11-01-17
Work Completed
Time Computed11-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged151
Percent Time Used41
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6324-14-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09172013
Totals19211.961341.146409.1433.3

CountyJASPER
HighwayUS0190
FromUS 190
ToUS 190
CSJ6324-15-001
Proj IDSUP - 632415001
Work TypeJASPER PICNIC
 
1.00015654.605355.4034.2
Work Order11-01-17
Work Began11-01-17
Work Completed
Time Computed11-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged151
Percent Time Used41
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6324-15-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09172014
Totals15654.601030.405355.4034.2

CountyJEFFERSON
HighwayUS0069
FromUS 69
ToUS 69
CSJ6325-67-001
Proj IDSUP - 632567001
Work TypeBEAUMONT AO/MO JANITORIAL
 
1.00013548.144905.5536.2
Work Order11-01-17
Work Began11-01-17
Work Completed
Time Computed11-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged151
Percent Time Used41
Contractor(s)
TIBH INDUSTRIES, INC.
OPPORTUNITIES FOR DESERVING INDIVIDUALS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6325-67-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10172006
Totals13548.14981.114905.5536.2

CountyJEFFERSON
HighwaySH0347
FromSH 347
ToSH 347
CSJ6325-68-001
Proj IDSUP - 632568001
Work TypePORT ARTHUR JANITORIAL
 
1.0009039.043653.2040.4
Work Order11-01-17
Work Began11-01-17
Work Completed
Time Computed11-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged151
Percent Time Used41
Contractor(s)
TIBH INDUSTRIES, INC.
OPPORTUNITIES FOR DESERVING INDIVIDUALS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6325-68-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10172005
Totals9039.04625.043653.2040.4

CountyORANGE
HighwaySH0062
FromSH 62
ToSH 62
CSJ6325-69-001
Proj IDSUP - 632569001
Work TypeORANGE JANITORIAL
 
1.00010584.005292.0050.0
Work Order11-01-17
Work Began11-01-17
Work Completed
Time Computed11-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged151
Percent Time Used41
Contractor(s)
TIBH INDUSTRIES, INC.
OPPORTUNITIES FOR DESERVING INDIVIDUALS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6325-69-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10172007
Totals10584.00882.005292.0050.0

CountyHARDIN
HighwayUS0069
FromUS 69
ToUS 69
CSJ6326-20-001
Proj IDSUP - 632620001
Work TypeKOUNTZE JANITORIAL
 
1.0005476.001206.0022.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began01-01-18
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged90
Percent Time Used24
Contractor(s)
TIBH INDUSTRIES, INC.
SPINDLETOP MHMR SERVICES
SUBCONTRACTOR(S) FOR CCSJ: 6326-20-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12172002
Totals5476.00402.001206.0022.0

CountyHARDIN
HighwayUS0069
FromUS 69
ToUS 69
CSJ6327-71-001
Proj IDSUP - 632771001
Work TypeKOUNTZE GROUNDS
 
1.0008721.001083.0012.4
Work Order01-01-18
Work Began01-01-18
Work Completed
Time Computed01-01-18
Contract Working Days365
Addl Days Granted0
Working Days Charged90
Percent Time Used24
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6327-71-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12172004
Totals8721.001083.001083.0012.4

CountyHARDIN
HighwayUS0069
FromUS 69
ToUS 69
CSJ6327-72-001
Proj IDSUP - 632772001
Work TypeKOUNTZE BARRELS
 
1.00014400.002375.00100.0
Work Order01-01-18
Work Began00-00-00
Work Completed01-01-18
Time Computed01-01-18
Contract Working Days365
Addl Days Granted0
Working Days Charged90
Percent Time Used24
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6327-72-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12172003
Totals14400.00900.002375.00100.0

CountyTYLER
HighwayUS0069
FromUS 69
ToUS 69
CSJ6329-10-001
Proj IDSUP - 632910001
Work TypeWOODVILLE JANITORIAL
 
1.0007800.001300.0016.6
Work Order02-01-18
Work Began02-01-18
Work Completed
Time Computed02-01-18
Contract Working Days365
Addl Days Granted0
Working Days Charged59
Percent Time Used16
Contractor(s)
TIBH INDUSTRIES, INC.
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6329-10-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01182003
Totals7800.00650.001300.0016.6

CountyNEWTON
HighwayUS0190
FromUS 190
ToUS 190
CSJ6329-11-001
Proj IDSUP - 632911001
Work TypeNEWTON JANITORIAL
 
1.0006948.001158.0016.6
Work Order02-01-18
Work Began02-01-18
Work Completed
Time Computed02-01-18
Contract Working Days365
Addl Days Granted0
Working Days Charged59
Percent Time Used16
Contractor(s)
TIBH INDUSTRIES, INC.
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6329-11-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01182002
Totals6948.00579.001158.0016.6

CountyJASPER
HighwayUS0190
FromUS 190
ToUS 190
CSJ6329-12-001
Proj IDSUP - 632912001
Work TypeJASPER JANITORIAL
 
1.00010176.001696.0016.6
Work Order02-01-18
Work Began02-01-18
Work Completed
Time Computed02-01-18
Contract Working Days365
Addl Days Granted0
Working Days Charged59
Percent Time Used16
Contractor(s)
TIBH INDUSTRIES, INC.
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6329-12-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01182001
Totals10176.00848.001696.0016.6

CountyJEFFERSON
HighwayUS0069
FromUS 69
ToUS 69
CSJ6329-57-001
Proj IDSUP - 632957001
Work TypeBEAUMONT AO/MO JANITORIAL
 
1.0003850.00350.009.0
Work Order03-01-18
Work Began00-00-00
Work Completed
Time Computed03-01-18
Contract Working Days365
Addl Days Granted0
Working Days Charged31
Percent Time Used8
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6329-57-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02182001
Totals3850.00350.00350.009.0

CountyLIBERTY
HighwayUS0090
FromUS 90
ToUS 90
CSJ6330-54-001
Proj IDSUP - 633054001
Work TypeLIBERTY GROUNDS
 
1.0005376.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-01-18
Work Began04-01-18
Work Completed
Time Computed04-01-18
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6330-54-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03182001
Totals5376.000.000.000.0

CountyCHAMBERS
HighwayFM0563
FromFM 563
ToFM 563
CSJ6330-61-001
Proj IDSUP - 633061001
Work TypeANAHUAC GROUNDS
 
1.00012472.660.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-01-18
Work Began04-01-18
Work Completed
Time Computed04-01-18
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6330-61-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03182002
Totals12472.660.000.000.0