Monthly Local Let Maintenance Report For Austin District As Of Sep 10, 2024 Page 3 Of 3

Last Update: Tuesday, September 10, 2024
FTP Icon
page 1 | page 2 | page 3

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyTRAVIS
HighwayUS0290
FromVARIOUS LOCATIONS IN
ToTRAVIS COUNTY
CSJ6461-80-001
Proj IDSUP - 646180001
Work TypeLITTER REMOVAL
 
0.010280064.00113141.4840.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began12-01-23
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged275
Percent Time Used37
Contractor(s)
WORKQUEST
RELIEF ENTERPRISES
SUBCONTRACTOR(S) FOR CCSJ: 6461-80-001
RELIEF ENTERPRISES (0.00)
Contract #11231430
Totals280064.0016781.96113141.4840.3

CountyWILLIAMSON
HighwayUS0079
FromVARIOUS LOCATIONS IN
ToWILLIAMSON, BASTROP, AND TRAVIS COUNTIES
CSJ6461-89-001
Proj IDSUP - 646189001
Work TypeLITTER REMOVAL
 
0.010220550.4088920.3240.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began12-01-23
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged275
Percent Time Used37
Contractor(s)
WORKQUEST
RELIEF ENTERPRISES
SUBCONTRACTOR(S) FOR CCSJ: 6461-89-001
RELIEF ENTERPRISES (0.00)
Contract #11231431
Totals220550.40196.9288920.3240.3

CountyTRAVIS
HighwayUS0290
FromVARIOUS LOCATIONS IN TRAVIS AND
ToHAYS COUNTY
CSJ6463-50-001
Proj IDSUP - 646350001
Work TypeLITTER REMOVAL
 
0.010186678.80121793.0465.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began02-01-24
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged213
Percent Time Used58
Contractor(s)
WORKQUEST
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6463-50-001
RUCON, INC. (0.00)
Contract #01241431
Totals186678.8028453.64121793.0465.2

CountyGILLESPIE
HighwayUS0290
FromVARIOUS LOCATIONS
ToGILLESPIE COUNTY
CSJ6463-52-001
Proj IDSUP - 646352001
Work TypeLITTER REMOVAL
 
0.010156241.6678153.8950.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began02-01-24
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged213
Percent Time Used58
Contractor(s)
WORKQUEST
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6463-52-001
RUCON, INC. (0.00)
Contract #01241430
Totals156241.660.0078153.8950.0

CountyHAYS
HighwayFM2001
FromVARIOUS LOCATIONS IN
ToHAYS COUNTY
CSJ6463-53-001
Proj IDSUP - 646353001
Work TypeLITTER REMOVAL
 
0.010187979.16113373.7660.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began02-01-24
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged213
Percent Time Used58
Contractor(s)
WORKQUEST
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6463-53-001
RUCON, INC. (0.00)
Contract #01241432
Totals187979.1617918.52113373.7660.3

CountyBASTROP
HighwaySH0021
FromVARIOUS LOCATIONS IN
ToTHE AUSTIN DISTRICT
CSJ6464-53-001
Proj IDMMC - 646453001
Work TypeROCK/RIPRAP
 
0.010153500.00106834.8369.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began03-28-24
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged153
Percent Time Used41
Contractor(s)
TOUCHSTONE RESOURCES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6464-53-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03241402
Totals153500.000.00106834.8369.5

CountyTRAVIS
HighwayIH0035
FromAUSTIN DISTRICT HEADQUARTERS
To.
CSJ6465-12-001
Proj IDSUP - 646512001
Work TypeGROUNDS MAINTENANCE
 
0.01067500.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
WORKQUEST
AUSTIN TASK, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6465-12-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03241430
Totals67500.000.000.000.0

CountyBLANCO
HighwayUS0281
FromJOHNSON CITY MAINTENANCE OFFICE
To.
CSJ6465-13-001
Proj IDSUP - 646513001
Work TypeJANITORIAL MAINTENANCE
 
0.01019113.683872.4520.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began04-01-24
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged153
Percent Time Used20
Contractor(s)
WORKQUEST
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6465-13-001
WORLD TECHNICAL SERVICES, INC. (0.00)
Contract #03241431
Totals19113.68774.493872.4520.2

CountyLLANO
HighwaySH0016
FromLLANO MAINTENANCE OFFICE
To.
CSJ6465-14-001
Proj IDSUP - 646514001
Work TypeJANITORIAL MAINTENANCE
 
0.01029752.526030.8020.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began04-01-24
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged153
Percent Time Used20
Contractor(s)
WORKQUEST
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6465-14-001
WORLD TECHNICAL SERVICES, INC. (0.00)
Contract #03241432
Totals29752.521206.166030.8020.2

CountyGILLESPIE
HighwayUS0087
FromFREDERICKSBURG MAINTENANCE OFFICE
To.
CSJ6465-15-001
Proj IDSUP - 646515001
Work TypeJANITORIAL MAINTENANCE
 
0.01029334.925956.3020.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began04-01-24
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged153
Percent Time Used20
Contractor(s)
WORKQUEST
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6465-15-001
WORLD TECHNICAL SERVICES, INC. (0.00)
Contract #03241433
Totals29334.921191.265956.3020.3

CountyMASON
HighwaySH0029
FromMASON MAINTENANCE OFFICE
To.
CSJ6465-16-001
Proj IDSUP - 646516001
Work TypeJANITORIAL MAINTENANCE
 
0.01020521.324218.8520.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began04-01-24
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged153
Percent Time Used20
Contractor(s)
WORKQUEST
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6465-16-001
WORLD TECHNICAL SERVICES, INC. (0.00)
Contract #03241434
Totals20521.32843.774218.8520.5

CountyTRAVIS
HighwayIH0035
FromAUSTIN DISTRICT HEADQUARTERS
ToAREA OFFICES / MAINTENANCE OFFICES
CSJ6467-27-001
Proj IDSUP - 646727001
Work TypePEST CONTROL MAINTENANCE
 
0.01039462.088280.5220.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began05-01-24
Work Completed
Time Computed00-00-00
Contract Working Days90
Addl Days Granted0
Working Days Charged15
Percent Time Used16
Contractor(s)
WORKQUEST
DANIEL PEST CONTROL AND PROFESSIONAL SERVICES
SUBCONTRACTOR(S) FOR CCSJ: 6467-27-001
DANIEL PEST CONTROL AND PROFESSIONAL SERVICES (0.00)
Contract #04241432
Totals39462.084472.768280.5220.9

CountyBASTROP
HighwayFM3000
FromVARIOUS LOCATIONS IN
ToBASTROP
CSJ6467-28-001
Proj IDSUP - 646728001
Work TypeLITTER REMOVAL
 
0.010221152.8084367.8038.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began05-01-24
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged123
Percent Time Used33
Contractor(s)
WORKQUEST
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6467-28-001
RUCON, INC. (0.00)
Contract #04241430
Totals221152.8049733.8284367.8038.1

CountyLEE
HighwayUS0290
FromVARIOUS LOCATIONS IN
ToLEE COUNTY
CSJ6467-30-001
Proj IDSUP - 646730001
Work TypeLITTER REMOVAL
 
0.010153943.7958462.1737.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began05-01-24
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged123
Percent Time Used33
Contractor(s)
WORKQUEST
RELIEF ENTERPRISES
SUBCONTRACTOR(S) FOR CCSJ: 6467-30-001
RELIEF ENTERPRISES (0.00)
Contract #04241431
Totals153943.7937656.5858462.1737.9

CountyWILLIAMSON
HighwayUS0183
FromVARIOUS LOCATIONS IN
ToWILLIAMSON AND TRAVIS COUNTIES
CSJ6469-39-001
Proj IDSUP - 646939001
Work TypeLITTER REMOVAL
 
0.010205463.4425726.8712.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began06-01-24
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged92
Percent Time Used12
Contractor(s)
WORKQUEST
RELIEF ENTERPRISES
SUBCONTRACTOR(S) FOR CCSJ: 6469-39-001
RELIEF ENTERPRISES (0.00)
Contract #05241430
Totals205463.446766.7625726.8712.5

CountyBASTROP
HighwaySH0021
FromBASTROP MAINTENANCE OFFICE
ToBASTROP AREA OFFICE
CSJ6470-49-001
Proj IDSUP - 647049001
Work TypeJANITORIAL MAINTENANCE
 
0.01032949.605338.2016.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began07-01-24
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged62
Percent Time Used16
Contractor(s)
WORKQUEST
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6470-49-001
WORLD TECHNICAL SERVICES, INC. (0.00)
Contract #06241430
Totals32949.602669.105338.2016.2

CountyTRAVIS
HighwayIH0035
FromAUSTIN DISTRICT HEADQUARTERS
To.
CSJ6470-59-001
Proj IDSUP - 647059001
Work TypeSTATE USE CONTRACT
 
0.010134784.0021651.3016.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began07-01-24
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged62
Percent Time Used16
Contractor(s)
WORKQUEST
AUSTIN TASK, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6470-59-001
AUSTIN TASK, INC. (0.00)
Contract #06241431
Totals134784.0010878.3021651.3016.0

CountyBLANCO
HighwayUS0281
FromVARIOUS LOCATIONS IN BLANCO, GILLESPIE,
ToHAYS, AND BURNET COUNTIES
CSJ6473-24-001
Proj IDSUP - 647324001
Work TypeLITTER REMOVAL
 
0.010188864.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
WORKQUEST
BOOTSTRAPS OCCUPATIONAL SERVICES INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6473-24-001
BOOTSTRAPS OCCUPATIONAL SERVICES INCORPORATED (0.00)
Contract #08241430
Totals188864.000.000.000.0