Monthly State Let Construction Report For Abilene District As Of Apr 10, 2018 Page 1 Of 2

Last Update: Friday, April 20, 2018
FTP Icon
page 1 | page 2

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyHOWARD
HighwayIH 20
FromMARTIN COUNTY LINE
ToNEAR US 87 (WB LANES ONLY)
CSJ0005-05-109
Proj IDNH 2018(341)
Work TypeOVERLAY
 
8.8156798902.47632764.579.3
Work Order02-14-18
Work Began03-07-18
Work Completed
Time Computed03-07-18
Contract Working Days92
Addl Days Granted0
Working Days Charged17
Percent Time Used18
Contractor(s)
PRICE CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0005-05-109
CONTRACTORS SERVICE COMPANY (0.27)
DOUBLE A CONTRACTING, L.P. (0.83)
GIBSON & ASSOCIATES, INC. (10.90)
HJC FARMS, INC. (3.72)
RPV CONSTRUCTION (2.22)
SCR CIVIL CONSTRUCTION, LLC (12.91)
TEXOP CONSTRUCTION (1.83)
WOLFE CONSTRUCTION GROUP, INC. (0.09)
Contract #12173012
Totals6798902.47632764.57632764.579.3

CountyHOWARD
HighwayIH 20
FromIH 20 AND MOORE FIELD ROAD
ToIH 20 AND MORE FIELD ROAD
CSJ0005-05-112
Proj IDBR 1702(476)
Work TypeINSTALL CRASHWALLS
 
1.0047767027.741623676.2520.9
Work Order08-08-17
Work Began10-16-17
Work Completed
Time Computed09-07-17
Contract Working Days309
Addl Days Granted0
Working Days Charged108
Percent Time Used34
Contractor(s)
SCR CIVIL CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0005-05-112
CONTRACTORS SERVICE COMPANY (1.06)
DIIBS SPECIALISTS (0.66)
DOUBLE A CONTRACTING, L.P. (3.12)
GIBSON & ASSOCIATES, INC. (0.47)
MCL CONTRACTING, LLC (1.60)
NELSON INDUSTRIAL SERVICES, INC. (0.08)
PRICE CONSTRUCTION, LTD. (1.34)
S & S BRIDGE PAINTING, INC. (7.03)
TEXAS CURB CUT, LP (0.04)
Contract #07173231
Totals7767027.74508863.821623676.2520.9

CountyHOWARD ETC
HighwayIH 20 ETC
FromAT FM 700
ToFRONTAGE ROADS ONLY
CSJ0005-06-116
Proj IDSTP 2018(314)HES
Work TypeFLASH BEACON,SIGNALS,SIGNS
 
5.1901092202.76169607.6015.5
Work Order12-19-17
Work Began03-19-18
Work Completed
Time Computed02-16-18
Contract Working Days77
Addl Days Granted0
Working Days Charged17
Percent Time Used22
Contractor(s)
AMERICAN LIGHTING AND SIGNALIZATION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0005-06-116
ALTUS TRAFFIC MANAGEMENT LLC (0.72)
D. I. J. CONSTRUCTION, INC. (3.41)
Contract #11173205
Totals1092202.76169607.60169607.6015.5

CountyHOWARD
HighwayIH 20
FromIH 20 WEST BOUND AT UNION PAC RR
ToIH 20 WEST BOUND AT UNION PAC RR
CSJ0005-06-117
Proj IDBR 1702(598)
Work TypeBRIDGE REHAB
 
0.2401316919.240.000.0
Work Order01-10-18
Work Began00-00-00
Work Completed
Time Computed02-08-18
Contract Working Days99
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
STRUCTURAL TECHNOLOGIES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0005-06-117
S & S BRIDGE PAINTING, INC. (24.55)
TOTAL HIGHWAY MAINTENANCE, LLC (5.40)
SCOTT DERR PAINTING CO, LLC (0.87)
RUBIO"S PAVING (0.07)
HJC FARMS, INC. (4.49)
DUSTROL, INC. (2.67)
Contract #08173037
Totals1316919.240.000.000.0

CountyHOWARD
HighwayIH 20
FromN SCURRY ST
ToMOSS LAKE RD
CSJ0005-06-119
Proj IDSTP 1702(599)HES
Work TypeINSTALL MEDIAN BARRIER
 
11.6611664669.16428449.2025.7
Work Order09-28-17
Work Began02-05-18
Work Completed
Time Computed10-30-17
Contract Working Days93
Addl Days Granted0
Working Days Charged39
Percent Time Used41
Contractor(s)
MASSANA CONSTRUCTION INC.
SUBCONTRACTOR(S) FOR CCSJ: 0005-06-119
WOLFE CONSTRUCTION GROUP, INC. (0.71)
Contract #08173040
Totals1664669.16318938.60428449.2025.7

CountyHOWARD ETC
HighwayIH 20 ETC
From.4 MILES EAST OF US 87
ToMITCHELL COUNTY LINE
CSJ0005-06-120
Proj IDNH 2018(548)
Work TypeINSTALL PAVEMENT MARKINGS
 
390.6721637144.67794997.1848.5
Work Order03-07-18
Work Began03-12-18
Work Completed
Time Computed03-12-18
Contract Working Days80
Addl Days Granted0
Working Days Charged13
Percent Time Used16
Contractor(s)
FLAT LINE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0005-06-120
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02183216
Totals1637144.67794997.18794997.1848.5

CountyNOLAN
HighwayIH 20
FromEAST BI 20-M IN SWEETWATER
ToTAYLOR COUNTY LINE
CSJ0006-03-132
Proj IDNH 2017(456)
Work TypeMILL,SPOT REPAIR,UNDERSEAL &OVERLAY
 
12.47714579827.287949360.2054.5
Work Order05-09-17
Work Began07-10-17
Work Completed
Time Computed07-10-17
Contract Working Days331
Addl Days Granted0
Working Days Charged149
Percent Time Used45
Contractor(s)
REECE ALBERT, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0006-03-132
CONTRACTORS SERVICE COMPANY (0.68)
WEST TEXAS RUMBLE STRIP (0.20)
AARON"S CONCRETE SAWING AND SEALING INC. (0.54)
DOUBLE A CONTRACTING, L.P. (1.65)
DUSTROL, INC. (1.53)
RPV CONSTRUCTION (2.93)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.35)
CHEROKEE SERVICES (0.86)
HJC FARMS, INC. (3.21)
SCR CONSTRUCTION CO., INC. (1.35)
TITAN MILLING INC. (0.99)
Contract #03173237
Totals14579827.28255990.127949360.2054.5

CountyNOLAN
HighwayIH 20
FromBS 70-G_(I-20 NFR ONLY)
ToEAST ARIZONA AVENUE (IN SWEETWATER)
CSJ0006-03-134
Proj IDNH 2018(584)
Work TypeREHABILITATE EXISTING ROADWAY
 
0.6231487306.610.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days113
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
NOBLES ROAD CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0006-03-134
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03183236
Totals1487306.610.000.000.0

CountyTAYLOR
HighwayIH 20
FromIH 20 EAST BOUND LANE
ToAT SH 351(AMBLER AVE IN ABILENE)
CSJ0006-06-099
Proj IDBR 1602(557)
Work TypeREPLACE BRIDGE AND APPROACHES
 
3.93212169359.9511971437.3398.3
CountyTAYLOR
HighwaySH 351
FromEAST STAMFORD STREET
ToEAST OVERLAND STREET
CSJ0011-01-035
Proj IDNH 1602(559)
Work TypeEXC,EMB, CONC PAV
 
0.1802469640.052442728.5498.9
Work Order11-29-16
Work Began03-20-17
Work Completed
Time Computed12-29-16
Contract Working Days445
Addl Days Granted0
Working Days Charged271
Percent Time Used60
Contractor(s)
WEBBER, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0006-06-099
TOTAL HIGHWAY MAINTENANCE, LLC (0.42)
DUSTIN ALLEN, INC. (1.19)
A BROTHERS MILLING, LLC (0.69)
STRIPE-A-ZONE, INC. (2.11)
NOBLES ROAD CONSTRUCTION, INC. (23.37)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.85)
WILLIS ELECTRIC CO., LP (2.41)
A-CORE CONCRETE CUTTING OF TEXAS, INC. (0.07)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (1.88)
MCL CONTRACTING, LLC (0.09)
MCL CONTRACTING, LLC (0.83)
BRENDA CONSTRUCTION (4.15)
UNDER CONSTRUCTION INC. (0.31)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.08)
HJC FARMS, INC. (0.26)
NORTH TEXAS BOMANITE, INC. (0.19)
JE CASEY, LLC (0.08)
Contract #10163008
Totals14639000.00112418.5414414165.8798.4

CountyTAYLOR
HighwayIH 20
FromAT FW&D (SOUTHERN SWITCHING) RR
ToHARDY STREET WEST BOUND
CSJ0006-06-103
Proj IDBR 1702(237)
Work TypeREHAB EXISTING BRIDGE
 
0.6372981256.752625348.0088.0
Work Order07-31-17
Work Began09-11-17
Work Completed
Time Computed08-30-17
Contract Working Days166
Addl Days Granted0
Working Days Charged125
Percent Time Used75
Contractor(s)
JAY-REESE CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0006-06-103
AREA WIDE PROTECTIVE, INC. (3.46)
TEXOP CONSTRUCTION (0.29)
S & S BRIDGE PAINTING, INC. (10.71)
WILLIS ELECTRIC CO., LP (0.59)
NOBLES ROAD CONSTRUCTION, INC. (3.53)
AARON CONCRETE CONTRACTORS, L.P. (3.75)
12-1 HIGHWAY AND ENVIRONMENTAL SERVICES, LLC (1.46)
STRIPE-A-ZONE, INC. (1.84)
ALTUS TRAFFIC MANAGEMENT LLC (0.34)
Contract #06173039
Totals2981256.75542487.502625348.0088.0

CountyCALLAHAN ETC
HighwayFM 18 ETC
FromTAYLOR C/L
ToBI 20T
CSJ0006-11-022
Proj IDSTP 2018(554)HESG
Work TypePROFILE EDGELINE MARKINGS
 
350.0891810774.910.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-08-18
Work Began04-09-18
Work Completed
Time Computed00-00-00
Contract Working Days63
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
SURFACE PREPARATION TECHNOLOGIES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0006-11-022
PMI PAVEMENT MARKING, INC. (65.04)
Contract #02183007
Totals1810774.910.000.000.0

CountyNOLAN ETC
HighwayBI 20-L ETC
From0.8 MILE NORTH OF IH 20
To1.2 MILES NORTH OF IH 20
CSJ0006-14-004
Proj IDSTP 2017(834)HES
Work TypeSURFACE TREAT AND INSTALL CHEVRONS
 
23.2231848432.221817682.2298.3
Work Order05-18-17
Work Began09-20-17
Work Completed
Time Computed08-16-17
Contract Working Days90
Addl Days Granted30
Working Days Charged105
Percent Time Used87
Contractor(s)
TOTAL HIGHWAY MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0006-14-004
WILLIS ELECTRIC CO., LP (33.43)
HJC FARMS, INC. (16.58)
THORNTON"S TREE SERVICE, INC. (0.97)
Contract #03173026
Totals1848432.22408231.601817682.2298.3

CountyNOLAN
HighwayBI 20-M
FromAT THE UPRR
ToIN SWEETWATER (PSN 044)
CSJ0006-15-034
Proj IDBR 1702(521)
Work TypeREPLACE BRIDGE
 
0.3604949400.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-23-18
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days139
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
WEBBER, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0006-15-034
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01183026
Totals4949400.000.000.000.0

CountyCALLAHAN
HighwayIH 20
FromNEAR BAIRD WEST CITY LIMIT_(WBL)
ToAPPROX 0.3 MI E OF MEXIA CREEK
CSJ0007-01-054
Proj IDNH 2017(855)
Work TypeOVERLAY
 
17.5828248492.448404736.4499.9
Work Order05-18-17
Work Began07-17-17
Work Completed
Time Computed07-17-17
Contract Working Days303
Addl Days Granted0
Working Days Charged140
Percent Time Used46
Contractor(s)
J. H. STRAIN & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0007-01-054
DOUBLE A CONTRACTING, L.P. (0.28)
CONTRACTORS SERVICE COMPANY (0.28)
SCR CONSTRUCTION CO., INC. (0.84)
TOTAL HIGHWAY MAINTENANCE, LLC (1.05)
A BROTHERS MILLING, LLC (2.59)
HJC FARMS, INC. (12.03)
VELASQUEZ CONCRETE (1.01)
Contract #04173009
Totals8248492.44299562.108404736.4499.9

CountyTAYLOR
HighwaySH 351
FromBU 83-D (TREADAWAY ST)
ToRAINY CREEK
CSJ0011-01-036
Proj IDC 11-1-36
Work TypeMILL,SPOT REPAIR & OVERLAY
 
1.5441708497.380.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days67
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
FOUTSCO PAVING COMPANY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0011-01-036
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03183027
Totals1708497.380.000.000.0

CountySHACKELFORD ETC
HighwayUS 180 ETC
From@ US 283
To.
CSJ0011-06-045
Proj IDSTP 1602(560)HES
Work TypeFLASH BEACON
 
2.390467417.10478564.9699.9
Work Order09-15-16
Work Began01-10-17
Work Completed
Time Computed12-14-16
Contract Working Days87
Addl Days Granted30
Working Days Charged135
Percent Time Used115
Contractor(s)
DBI SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0011-06-045
TOTAL HIGHWAY MAINTENANCE, LLC (2.01)
COLLIER DIRECTIONAL DRILLING (8.62)
Contract #08163239
Totals467417.1044912.86478564.9699.9

CountyJONES
HighwayUS 83
FromSH 92
ToHAMLIN NORTH CITY LIMITS
CSJ0033-03-029
Proj IDSTP 1702(131)
Work TypeCEMENT TRT BASE,1-CST,6" MILL
 
2.7524161245.371873654.7445.0
Work Order06-07-17
Work Began10-12-17
Work Completed
Time Computed07-06-17
Contract Working Days242
Addl Days Granted18
Working Days Charged141
Percent Time Used54
Contractor(s)
NOBLES ROAD CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0033-03-029
BRENDA CONSTRUCTION (6.51)
CONTRACTORS SERVICE COMPANY (1.54)
DOUBLE A CONTRACTING, L.P. (1.99)
DUSTROL, INC. (1.92)
HJC FARMS, INC. (2.66)
TOTAL HIGHWAY MAINTENANCE, LLC (0.58)
Contract #05173221
Totals4161245.37571819.861873654.7445.0

CountyJONES
HighwayUS 83
FromFM 707
To0.57 MI SOUTH OF FM 1082
CSJ0033-05-091
Proj IDNH 2018(499)
Work TypeRESTORATION OF EXISTING ROAD
 
10.4265078876.00322237.706.3
Work Order02-14-18
Work Began03-21-18
Work Completed
Time Computed03-19-18
Contract Working Days110
Addl Days Granted0
Working Days Charged8
Percent Time Used7
Contractor(s)
J. H. STRAIN & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0033-05-091
DOUBLE A CONTRACTING, L.P. (0.36)
HJC FARMS, INC. (1.95)
CONTRACTORS SERVICE COMPANY (0.31)
A BROTHERS MILLING, LLC (1.41)
FLAT LINE, INC. (0.82)
Contract #01183020
Totals5078876.00322237.70322237.706.3

CountyJONES ETC
HighwayUS 83 ETC
FromFM 707
ToTAYLOR COUNTY LINE
CSJ0033-05-092
Proj IDNH 2018(342)
Work TypeSEAL COAT
 
228.7759187304.69202385.692.2
Work Order01-10-18
Work Began00-00-00
Work Completed
Time Computed02-08-18
Contract Working Days88
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
NORTHEASTERN PAVERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0033-05-092
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12173007
Totals9187304.69202385.69202385.692.2

CountyTAYLOR
HighwayUS 83
FromNEAR FM 2404
ToNEAR S 7TH ST IN ABILENE
CSJ0033-06-107
Proj IDNH 1702(240)
Work TypePLANE,UNDERSEAL,SMA,BR RAIL,BR JTS
 
5.8518326091.951912780.9822.9
Work Order07-26-17
Work Began10-16-17
Work Completed
Time Computed08-28-17
Contract Working Days294
Addl Days Granted15
Working Days Charged96
Percent Time Used31
Contractor(s)
J. H. STRAIN & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0033-06-107
A BROTHERS MILLING, LLC (1.58)
TOTAL HIGHWAY MAINTENANCE, LLC (2.44)
MPB, INC. (6.10)
HJC FARMS, INC. (21.15)
CONTRACTORS SERVICE COMPANY (0.90)
Contract #06173229
Totals8326091.95374116.171912780.9822.9

page 1 | page 2