Monthly State Let Construction Report For San Angelo District As Of Jun 08, 2018 Page 2 Of 2

Last Update: Tuesday, June 12, 2018
FTP Icon
page 1 | page 2

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyCONCHO
HighwayCS
FromVARIOUS LOCATIONS IN EDEN
To.
CSJ0907-15-005
Proj IDSTP 2017(287)TAPS
Work TypePEDESTRIAN IMPROVEMENTS
 
0.303934493.500.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days83
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ENCINO LANDSCAPE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0907-15-005
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06183249
Totals934493.500.000.000.0

CountyKIMBLE
HighwayVA
FromVARIOUS LOCATIONS IN KIMBLE CO.
To.
CSJ0907-20-006
Proj IDNH 2017(956)
Work TypeREPLACE AND REFURBISH LARGE SIGNS
 
0.0043089229.591542151.5049.9
Work Order05-22-17
Work Began07-10-17
Work Completed
Time Computed07-10-17
Contract Working Days410
Addl Days Granted0
Working Days Charged191
Percent Time Used46
Contractor(s)
COLLINS & HERMANN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0907-20-006
SOUTHWEST DIGGER & ANCHOR SERVICES (5.91)
Contract #04173018
Totals3089229.59160583.871542151.5049.9

CountySCHLEICHER
HighwayCS
FromVARIOUS LOCATIONS IN ELDORADO
To.
CSJ0907-26-004
Proj IDSTP 2017(286)TAPS
Work TypePEDESTRIAN IMPROVEMENTS
 
1.095368395.800.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days57
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
A GREATER AUSTIN DEVELOPMENT COMPANY, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0907-26-004
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05183048
Totals368395.800.000.000.0

CountyCRANE
HighwayRL SO
FromUPTON COUNTY LINE RRMP 843.6
ToCROCKETT COUNTY LINE RRMP 846.9
CSJ7106-05-001
Proj IDSTP 2018(117)
Work TypeINFRASTRUCTURE REHABILIATION
 
0.001432143.000.000.0
CountyUPTON
HighwayRL SO
FromREAGAN COUNTY LINE RRMP 810.4
ToCRANE COUNTY LINE RMP 843.6
CSJ7106-06-003
Proj IDSTP 2018(117)
Work TypeINFRASTRUCTURE REHABILITATION
 
0.0015620674.000.000.0
CountyCROCKETT
HighwayRL SO
FromCRANE COUNTY LINE RRMP 846.9
ToPECOS COUNTY LINE RRMP 847.8
CSJ7107-04-001
Proj IDSTP 2018(117)
Work TypeINFRASTRUCTURE REHABILITATION
 
0.001538925.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days195
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
RAILWORKS TRACK SYSTEMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 7106-05-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05183225
Totals6591742.000.000.000.0

page 1 | page 2