Monthly Local Let Maintenance Report For Lubbock District As Of Jun 08, 2018 Page 2 Of 2

Last Update: Tuesday, June 12, 2018
FTP Icon
page 1 | page 2

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyLUBBOCK
HighwayUS0084
FromLUBBOCK NORTHEAST
ToLUBBOCK NORTHEAST
CSJ6307-22-001
Proj IDSUP - 630722001
Work TypePICNIC AREA MAINTENANCE
 
0.00154224.0045116.0083.2
Work Order09-01-16
Work Began09-01-16
Work Completed
Time Computed09-01-16
Contract Working Days730
Addl Days Granted0
Working Days Charged638
Percent Time Used87
Contractor(s)
TIBH INDUSTRIES, INC.
MARIAN MOSS ENTERPRISES
SUBCONTRACTOR(S) FOR CCSJ: 6307-22-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07160537
Totals54224.003184.0045116.0083.2

CountyHALE
HighwayIH0027
FromPLAINVIEW AREA
ToPLAINVIEW AREA
CSJ6307-26-001
Proj IDSUP - 630726001
Work TypeGROUND MAINTENANCE
 
0.00184002.0052684.7163.0
Work Order08-19-16
Work Began09-01-16
Work Completed
Time Computed09-01-16
Contract Working Days730
Addl Days Granted0
Working Days Charged638
Percent Time Used87
Contractor(s)
TIBH INDUSTRIES, INC.
MARIAN MOSS ENTERPRISES
SUBCONTRACTOR(S) FOR CCSJ: 6307-26-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07160535
Totals84002.004208.0052684.7163.0

CountyHALE
HighwayIH0027
FromPLAINVIEW AREA
ToPLAINVIEW AREA
CSJ6307-27-001
Proj IDSUP - 630727001
Work TypePICNIC AND LITTER MAINTENANCE
 
0.001376820.00292298.0077.5
Work Order09-07-16
Work Began09-01-16
Work Completed
Time Computed09-19-16
Contract Working Days730
Addl Days Granted0
Working Days Charged638
Percent Time Used87
Contractor(s)
TIBH INDUSTRIES, INC.
MARIAN MOSS ENTERPRISES
SUBCONTRACTOR(S) FOR CCSJ: 6307-27-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07160536
Totals376820.0030908.00292298.0077.5

CountyLUBBOCK
HighwayIH0027
FromLUBBOCK COUNTY
ToLUBBOCK COUNTY
CSJ6307-39-001
Proj IDSUP - 630739001
Work TypeROADSIDE MAINTENANCE
 
0.001224350.00216763.0096.6
Work Order09-01-16
Work Began09-01-16
Work Completed
Time Computed09-01-16
Contract Working Days730
Addl Days Granted0
Working Days Charged607
Percent Time Used83
Contractor(s)
TIBH INDUSTRIES, INC.
MARIAN MOSS ENTERPRISES
SUBCONTRACTOR(S) FOR CCSJ: 6307-39-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07160538
Totals224350.004140.00216763.0096.6

CountyLUBBOCK
HighwayIH0027
FromLUBBOCK SOUTHEAST
ToLUBBOCK SOUTHEAST
CSJ6307-46-001
Proj IDSUP - 630746001
Work TypeLITTER PICK UP
 
0.00174685.7460597.1781.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-01-16
Work Began09-01-16
Work Completed
Time Computed09-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged365
Percent Time Used100
Contractor(s)
TIBH INDUSTRIES, INC.
MARIAN MOSS ENTERPRISES
SUBCONTRACTOR(S) FOR CCSJ: 6307-46-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07160539
Totals74685.740.0060597.1781.1

CountyLUBBOCK
HighwayIH0027
FromLUBBOCK COUNTY
ToLUBBOCK COUNTY
CSJ6307-48-001
Proj IDSUP - 630748001
Work TypeLITTER REMOVAL
 
0.001624222.96455725.9473.0
Work Order09-01-16
Work Began09-01-16
Work Completed
Time Computed09-01-16
Contract Working Days730
Addl Days Granted0
Working Days Charged607
Percent Time Used83
Contractor(s)
TIBH INDUSTRIES, INC.
L&D INDUSTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6307-48-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07160540
Totals624222.9623879.81455725.9473.0

CountyLUBBOCK
HighwayIH0027
FromTULIA MAINTENANCE SECTION
ToSEMINOLE MAINTENACE SECTION
CSJ6310-11-001
Proj IDSUP - 631011001
Work TypePREVENTATIVE MAINTENANCE
 
0.001312530.8077783.8724.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began10-01-16
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged243
Percent Time Used33
Contractor(s)
TIBH INDUSTRIES, INC.
E.Q.U.I.P. ENTERPRISES
SUBCONTRACTOR(S) FOR CCSJ: 6310-11-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10160531
Totals312530.800.0077783.8724.8

CountyTERRY
HighwayUS0062
FromBROWNFIELD
ToSEMINOLE
CSJ6316-58-001
Proj IDSUP - 631658001
Work TypeJANITORIAL FOR BROWNFIELD AREA OFFICES
 
0.001109291.5039126.3635.8
Work Order07-25-17
Work Began08-01-17
Work Completed
Time Computed03-08-18
Contract Working Days731
Addl Days Granted0
Working Days Charged273
Percent Time Used37
Contractor(s)
TIBH INDUSTRIES, INC.
FRESH START OF MONROE INC.
SUBCONTRACTOR(S) FOR CCSJ: 6316-58-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06170531
Totals109291.504371.6639126.3635.8

CountyLUBBOCK
HighwayIH0027
FromLUBBOCK NE
ToLUBBOCK SE
CSJ6316-60-001
Proj IDSUP - 631660001
Work TypeJANITORIAL FOR LUBBOCK OFFICES
 
0.00153356.5015526.4729.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began08-01-17
Work Completed
Time Computed00-00-00
Contract Working Days731
Addl Days Granted0
Working Days Charged273
Percent Time Used37
Contractor(s)
TIBH INDUSTRIES, INC.
FRESH START OF MONROE INC.
SUBCONTRACTOR(S) FOR CCSJ: 6316-60-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06170532
Totals53356.50924.6615526.4729.0

CountyYOAKUM
HighwaySH0083
FromINTERSECTION OF SH 83
ToAND SH 214
CSJ6320-72-001
Proj IDRMC - 632072001
Work TypeSIGNAL INSTALLATION
 
0.001218450.050.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days40
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
WILLIS ELECTRIC CO., LP
SUBCONTRACTOR(S) FOR CCSJ: 6320-72-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03180501
Totals218450.050.000.000.0

CountyGARZA
HighwayUS0380
FromPOST RDC
ToPOST RDC
CSJ6321-45-001
Proj IDSUP - 632145001
Work TypeGROUNDS MAINTENANCE
 
0.00116416.004332.0026.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged242
Percent Time Used33
Contractor(s)
TIBH INDUSTRIES, INC.
MARIAN MOSS ENTERPRISES
SUBCONTRACTOR(S) FOR CCSJ: 6321-45-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08170551
Totals16416.001140.004332.0026.3

CountyLUBBOCK
HighwayIH0027
FromLUBBOCK SOUTHEAST
ToLUBBOCK SOUTHEAST
CSJ6321-51-001
Proj IDSUP - 632151001
Work TypeLITTER PICKUP
 
0.00172954.0043970.8560.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-17
Work Completed
Time Computed00-00-00
Contract Working Days366
Addl Days Granted0
Working Days Charged242
Percent Time Used66
Contractor(s)
TIBH INDUSTRIES, INC.
MARIAN MOSS ENTERPRISES
SUBCONTRACTOR(S) FOR CCSJ: 6321-51-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08170552
Totals72954.007673.4043970.8560.2

CountyLUBBOCK
HighwayUS0084
FromLBB SE MAINT OFFICE
ToLBB SPECIAL CREW OFFICE
CSJ6321-76-001
Proj IDSUP - 632176001
Work TypeGROUNDS MAINTENANCE
 
0.00149780.0010930.0021.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days731
Addl Days Granted0
Working Days Charged242
Percent Time Used33
Contractor(s)
TIBH INDUSTRIES, INC.
MARIAN MOSS ENTERPRISES
SUBCONTRACTOR(S) FOR CCSJ: 6321-76-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08170553
Totals49780.002560.0010930.0021.9

CountyLUBBOCK
HighwayUS0084
FromLBB DISTRICT GROUNDS
ToLBB DISTRICT GROUNDS
CSJ6321-78-001
Proj IDSUP - 632178001
Work TypeGROUNDS MAINTENANCE
 
0.001100368.0024584.0024.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-17
Work Completed
Time Computed00-00-00
Contract Working Days731
Addl Days Granted0
Working Days Charged242
Percent Time Used33
Contractor(s)
TIBH INDUSTRIES, INC.
MARIAN MOSS ENTERPRISES
SUBCONTRACTOR(S) FOR CCSJ: 6321-78-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08170554
Totals100368.005242.0024584.0024.4

CountyHALE
HighwayIH0027
FromVARIOUS
ToVARIOUS
CSJ6322-80-001
Proj IDSUP - 632280001
Work TypeJANITORIAL MAINTENANCE SERVICES
 
0.001101541.2837763.3737.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-17
Work Completed
Time Computed00-00-00
Contract Working Days731
Addl Days Granted0
Working Days Charged273
Percent Time Used37
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6322-80-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08170535
Totals101541.283854.5737763.3737.1

CountyLUBBOCK
HighwayUS0084
FromVARIOUS
ToVARIOUS
CSJ6323-18-001
Proj IDSUP - 632318001
Work TypeJANITORIAL MAINTENANCE
 
0.001194167.6463107.6732.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-17
Work Completed
Time Computed00-00-00
Contract Working Days731
Addl Days Granted0
Working Days Charged242
Percent Time Used33
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6323-18-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08170536
Totals194167.647303.5463107.6732.5

CountyLUBBOCK
HighwayUS0084
FromVARIES
ToVARIES
CSJ6328-89-001
Proj IDRMC - 632889001
Work TypeROW FULL WIDTH MOWING
 
0.001209046.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days38
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
GORMAN OUTDOOR, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6328-89-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04180501
Totals209046.000.000.000.0