Monthly Local Let Maintenance Report For El Paso District As Of Aug 15, 2022 Page 4 Of 4
Last Update: Monday, August 15, 2022
|
|
Contract Identification and Information | Length | Contract Amount | Amount This Estimate | Total Estimate To Date | % Comp |
|
County | EL PASO |
Highway | SL0375 |
From | VARIOUS LOCATIONS |
To | VARIOUS LOCATIONS |
CSJ | 6401-28-001 |
Proj ID | MMC - 640128001 |
Work Type | AGGREGATE |
|
| 0.010 | 142500.00 | | 0.00 | 0.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 07-08-22 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 120 |
Addl Days Granted | 0 |
Working Days Charged | 24 |
Percent Time Used | 20 |
Contractor(s) |
TOUCHSTONE RESOURCES, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6401-28-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 05222401 |
| Totals | 142500.00 | 0.00 | 0.00 | 0.0 |
|
County | CULBERSON |
Highway | IH0010 |
From | VARIOUS LOCATIONS |
To | VARIOUS LOCATIONS |
CSJ | 6402-39-001 |
Proj ID | MMC - 640239001 |
Work Type | DE-ICING SALT |
|
| 0.010 | 271259.00 | | 0.00 | 0.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 00-00-00 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 120 |
Addl Days Granted | 0 |
Working Days Charged | 0 |
Percent Time Used | 0 |
Contractor(s) |
NSG LOGISTICS, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6402-39-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 06222402 |
| Totals | 271259.00 | 0.00 | 0.00 | 0.0 |
|
County | EL PASO |
Highway | IH0010 |
From | EL PASO, TEXAS |
To | EL PASO, TEXAS |
CSJ | 6405-06-001 |
Proj ID | MMC - 640506001 |
Work Type | LIME |
|
| 0.010 | 14240.00 | | 0.00 | 0.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 00-00-00 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 120 |
Addl Days Granted | 0 |
Working Days Charged | 0 |
Percent Time Used | 0 |
Contractor(s) |
TOUCHSTONE RESOURCES, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6405-06-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 06222403 |
| Totals | 14240.00 | 0.00 | 0.00 | 0.0 |
|
County | EL PASO |
Highway | IH0010 |
From | VARIOUS LOCATIONS |
To | VARIOUS LOCATIONS |
CSJ | 6405-08-001 |
Proj ID | RMC - 640508001 |
Work Type | CULVERT CLEANING |
|
| 0.010 | 259010.00 | | 0.00 | 0.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 00-00-00 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 365 |
Addl Days Granted | 0 |
Working Days Charged | 0 |
Percent Time Used | 0 |
Contractor(s) |
DEL MAR CONTRACTING, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6405-08-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 06222401 |
| Totals | 259010.00 | 0.00 | 0.00 | 0.0 |
|
County | EL PASO |
Highway | IH0010 |
From | DISTRICT OFFICE |
To | DISTRICT OFFICE |
CSJ | 6405-20-001 |
Proj ID | MMC - 640520001 |
Work Type | HYDRAULIC CEMENT |
|
| 0.010 | 15000.00 | | 0.00 | 0.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 00-00-00 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 120 |
Addl Days Granted | 0 |
Working Days Charged | 0 |
Percent Time Used | 0 |
Contractor(s) |
TOUCHSTONE RESOURCES, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6405-20-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 06222404 |
| Totals | 15000.00 | 0.00 | 0.00 | 0.0 |
|
County | EL PASO |
Highway | IH0010 |
From | DISTRICT OFFICE |
To | DISTRICT OFFICE |
CSJ | 6410-78-001 |
Proj ID | SUP - 641078001 |
Work Type | JANITORIAL MAINTENANCE |
|
| 0.010 | 92050.00 | | 24506.82 | 26.6 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 06-06-22 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 209 |
Addl Days Granted | 0 |
Working Days Charged | 56 |
Percent Time Used | 26 |
Contractor(s) |
WORKQUEST ENDEAVORS UNLIMITED, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6410-78-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 05222430 |
| Totals | 92050.00 | 13150.00 | 24506.82 | 26.6 |
|