Monthly Local Let Maintenance Report For Amarillo District As Of Jun 08, 2018 Page 2 Of 3

Last Update: Tuesday, June 12, 2018
FTP Icon
page 1 | page 2 | page 3

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyCARSON
HighwayIH0040
FromSEE PLAN SHEETS
ToSEE PLAN SHEETS
CSJ6307-66-001
Proj IDRMC - 630766001
Work TypeCLEANING & SWEEPING HIGHWAYS
 
0.00198949.62158616.9199.9
Work Order00-00-00
Work Began09-26-16
Work Completed
Time Computed09-26-16
Contract Working Days365
Addl Days Granted365
Working Days Charged611
Percent Time Used83
Contractor(s)
PANHANDLE SWEEPING & MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6307-66-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08160401
Totals98949.620.00158616.9199.9

CountyPOTTER
HighwayIH0040
FromVARIOUS
To.
CSJ6308-19-001
Proj IDSUP - 630819001
Work TypeJANITORIAL AND GROUNDS
 
0.001335405.80208594.8462.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-26-16
Work Began09-01-16
Work Completed
Time Computed09-01-16
Contract Working Days730
Addl Days Granted0
Working Days Charged456
Percent Time Used62
Contractor(s)
TIBH INDUSTRIES, INC.
FRESH START OF MONROE INC.
SUBCONTRACTOR(S) FOR CCSJ: 6308-19-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08160402
Totals335405.800.00208594.8462.1

CountyPOTTER
HighwayUS0087
FromSEE PLAN SHEETS
ToSEE PLAN SHEETS
CSJ6308-76-001
Proj IDSUP - 630876001
Work TypeSTATE USE LITTER PICKUP(LIDS)
 
0.00192692.15136685.8099.9
Work Order00-00-00
Work Began09-01-16
Work Completed
Time Computed09-01-16
Contract Working Days365
Addl Days Granted242
Working Days Charged607
Percent Time Used100
Contractor(s)
TIBH INDUSTRIES, INC.
FRESH START OF MONROE INC.
SUBCONTRACTOR(S) FOR CCSJ: 6308-76-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08160420
Totals92692.156834.29136685.8099.9

CountyDEAF SMITH
HighwayUS0385
FromHEREFORD MAINTENANCE
ToJANITORIAL
CSJ6315-51-001
Proj IDSUP - 631551001
Work TypeHEREFORD JANITORIAL
 
0.0015887.924746.6780.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began03-01-17
Work Completed
Time Computed03-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged365
Percent Time Used100
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6315-51-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02170420
Totals5887.920.004746.6780.6

CountyPOTTER
HighwayIH0040
FromSEE PLANS
ToSEE PLANS
CSJ6316-48-001
Proj IDRMC - 631648001
Work TypeON CALL GUARDRAIL/CABLE BARRIER REPAIR
 
0.001164787.5096497.7558.5
Work Order00-00-00
Work Began07-01-17
Work Completed
Time Computed07-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged310
Percent Time Used84
Contractor(s)
AMARILLO RMT ENTERPRISES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6316-48-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06170401
Totals164787.507556.7596497.7558.5

CountyOLDHAM
HighwayIH0040
FromSEE PLANS
ToSEE PLANS
CSJ6317-35-001
Proj IDSUP - 631735001
Work TypePICNIC AREA/LITTER PICKUP
 
0.00163457.6863457.6899.9
Work Order00-00-00
Work Began05-01-17
Work Completed
Time Computed05-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged365
Percent Time Used100
Contractor(s)
TIBH INDUSTRIES, INC.
FRESH START OF MONROE INC.
SUBCONTRACTOR(S) FOR CCSJ: 6317-35-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04170420
Totals63457.684881.3663457.6899.9

CountyOLDHAM
HighwayIH0040
FromSEE PLAN SHEETS
ToSEE PLAN SHEETS
CSJ6317-36-001
Proj IDSUP - 631736001
Work TypeSTATE USE SPOT LITTER PICKUP
 
0.0019909.249083.4791.6
Work Order00-00-00
Work Began05-01-17
Work Completed
Time Computed05-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged365
Percent Time Used100
Contractor(s)
TIBH INDUSTRIES, INC.
FRESH START OF MONROE INC.
SUBCONTRACTOR(S) FOR CCSJ: 6317-36-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04170421
Totals9909.24825.779083.4791.6

CountyRANDALL
HighwaySL0335
FromAMARILLO AE OFFICE
ToE-WAY MAINTENANCE OFFICE
CSJ6319-08-001
Proj IDSUP - 631908001
Work TypeSTATE USE JANITORIAL SERVICE
 
0.00115202.6813771.2890.5
Work Order00-00-00
Work Began06-01-17
Work Completed
Time Computed06-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged365
Percent Time Used100
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6319-08-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05170420
Totals15202.68909.0413771.2890.5

CountyGRAY
HighwayIH0040
FromSEE PLAN SHEETS
ToSEE PLAN SHEETS
CSJ6319-46-001
Proj IDRMC - 631946001
Work TypeON CALL GUARDRAIL REPAIR
 
0.001185352.5091943.4549.6
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed09-18-17
Contract Working Days365
Addl Days Granted0
Working Days Charged254
Percent Time Used69
Contractor(s)
DFB CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6319-46-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08170401
Totals185352.500.0091943.4549.6

CountyRANDALL
HighwayIH0027
FromSEE PLAN SHEETS
ToSEE PLAN SHEETS
CSJ6321-47-001
Proj IDSUP - 632147001
Work TypeDISTRICT OFFICE JANITORIAL
 
0.00175299.8861584.9281.7
Work Order00-00-00
Work Began08-01-17
Work Completed
Time Computed08-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged304
Percent Time Used83
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6321-47-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07170420
Totals75299.885786.6261584.9281.7

CountyHARTLEY
HighwayFM0767
FromSEE PLAN SHEETS
ToSEE PLAN SHEETS
CSJ6323-11-001
Proj IDRMC - 632311001
Work TypeVARIOUS BRIDGE REPAIRS
 
0.001273466.00278818.0099.9
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed11-09-17
Contract Working Days40
Addl Days Granted0
Working Days Charged7
Percent Time Used17
Contractor(s)
GIBSON & ASSOCIATES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6323-11-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10170401
Totals273466.005352.00278818.0099.9

CountyCARSON
HighwayIH0040
FromSEE PLANS
ToSEE PLANS
CSJ6323-95-001
Proj IDSUP - 632395001
Work TypeSTATE USE PICNIC AREA MAINTENANCE
 
0.00195508.6448266.4250.5
Work Order00-00-00
Work Began10-03-17
Work Completed
Time Computed10-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged243
Percent Time Used66
Contractor(s)
TIBH INDUSTRIES, INC.
FRESH START OF MONROE INC.
SUBCONTRACTOR(S) FOR CCSJ: 6323-95-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09170420
Totals95508.647137.4448266.4250.5

CountyPOTTER
HighwayUS0287
FromSEE PLAN SHEETS
ToSEE PLAN SHEETS
CSJ6324-99-001
Proj IDRMC - 632499001
Work TypeINSTALLATION OF RAISED PAVEMENT MARKERS
 
0.00176382.600.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days80
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
BRYDL CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6324-99-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02180401
Totals76382.600.000.000.0

CountyPOTTER
HighwayIH0040
FromVARIOUS
To.
CSJ6326-77-001
Proj IDSUP - 632677001
Work TypeJANITORIAL AND GROUNDS
 
0.001125432.5883621.7266.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days273
Addl Days Granted0
Working Days Charged182
Percent Time Used66
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6326-77-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11170401
Totals125432.5814243.2683621.7266.6

CountyPOTTER
HighwayIH0040
FromSEE PLAN SHEETS
ToSEE PLAN SHEETS
CSJ6327-93-001
Proj IDSUP - 632793001
Work TypeSTATE USE DEBRIS PICKUP AND DISPOSAL
 
0.001315120.00105200.0033.3
Work Order00-00-00
Work Began01-18-18
Work Completed
Time Computed01-02-18
Contract Working Days365
Addl Days Granted0
Working Days Charged151
Percent Time Used41
Contractor(s)
TIBH INDUSTRIES, INC.
FRESH START OF MONROE INC.
SUBCONTRACTOR(S) FOR CCSJ: 6327-93-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12170420
Totals315120.0031560.00105200.0033.3

CountyGRAY
HighwayUS0060
FromSEE PLAN SHEETS
ToSEE PLAN SHEETS
CSJ6329-65-001
Proj IDRMC - 632965001
Work TypeTREE REMOVAL
 
0.001132500.00142075.0099.9
Work Order00-00-00
Work Began04-16-18
Work Completed
Time Computed04-09-18
Contract Working Days90
Addl Days Granted0
Working Days Charged21
Percent Time Used23
Contractor(s)
EASTGATE SERVICES
SUBCONTRACTOR(S) FOR CCSJ: 6329-65-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03180401
Totals132500.0067825.00142075.0099.9

CountyDEAF SMITH
HighwayUS0385
FromSEE PLAN SHEETS
ToSEE PLAN SHEETS
CSJ6330-23-001
Proj IDSUP - 633023001
Work TypeSTATE USE JANITORIAL MAINTENANCE
 
0.00112129.201516.1512.5
Work Order00-00-00
Work Began03-01-18
Work Completed
Time Computed03-01-18
Contract Working Days731
Addl Days Granted0
Working Days Charged92
Percent Time Used12
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6330-23-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02180420
Totals12129.20385.481516.1512.5

CountyPOTTER
HighwayIH0040
FromSEE PLAN SHEETS
ToSEE PLAN SHEETS
CSJ6330-58-001
Proj IDSUP - 633058001
Work TypeSTATE USE LITTER PICKUP LIDS
 
0.001197239.1714099.687.1
Work Order00-00-00
Work Began05-01-18
Work Completed
Time Computed05-01-18
Contract Working Days365
Addl Days Granted0
Working Days Charged31
Percent Time Used8
Contractor(s)
TIBH INDUSTRIES, INC.
FRESH START OF MONROE INC.
SUBCONTRACTOR(S) FOR CCSJ: 6330-58-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04180420
Totals197239.1714099.6814099.687.1

CountyMOORE
HighwayUS0087
FromSEE PLAN SHEETS
ToSEE PLAN SHEETS
CSJ6330-80-001
Proj IDRMC - 633080001
Work TypeON CALL GUARDRAIL REPAIR
 
0.001142125.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
DFB CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6330-80-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04180401
Totals142125.000.000.000.0

CountyPOTTER
HighwayIH0040
FromSEE PLAN SHEETS
ToSEE PLAN SHEETS
CSJ6330-88-001
Proj IDRMC - 633088001
Work TypeCLEANING AND SWEEPING HIGHWAYS
 
0.001287049.600.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
PANHANDLE SWEEPING & MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6330-88-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04180402
Totals287049.600.000.000.0

page 1 | page 2 | page 3