The Loop 1604 North Expansion project was planned in 6 separate segments with Segments 1 – 4 currently under construction. The project is expected to be under construction through 2028, with activities occurring throughout the entire corridor simultaneously.

Segment 1: Loop 1604 from SH 16 (Bandera Road) to I-10

Segment 2: Loop 1604 and I-10 Interchange

Segment 3: Loop 1604 from I-10 to US 281

Segment 4: Loop 1604 from US 281 to Redland

Segment 5: Loop 1604 from Redland to Judson Rd.

  • Anticipated Letting Date: 2024
  • Estimated Start: Late 2024
  • Estimated Completion: 2027
  • Estimated Cost: $205 million

Segment 6: Loop 1604 from Judson Rd. to I-35

  • Anticipated Letting Date: 2025
  • Estimated Start: Late 2025
  • Estimated Completion: 2028
  • Estimated Cost: $203 million