North Tarrant Express logo

The North Tarrant Express (NTE) is dedicated to improving mobility along north I-35W, northeast I-820 and SH 121/183 Airport Freeway through a regionally supported TEXpress Lane system.

NTE | I-820 and SH 121/183

The NTE | I-820 and SH 121/183 project began in October 2010 and reached substantial completion in October 2014 – nine months ahead of schedule. In addition to design, right-of-way acquisition, and utility relocation, the project rebuilt and expanded 13 miles along I-820 and SH 121/183 from I-35W to the SH 121 split. This $2.1 billion project rebuilt the existing four to six mainlanes and added four TEXpress Lanes, plus frontage roads and auxiliary lanes to approximately double the existing capacity.

The project provided an additional value of approximately $450 million for operations and maintenance through 2061. Two additional non-tolled mainlanes will also be added no later than 2030 at no additional cost. This public-private partnership used two-thirds private funds with one-third public funds to complete the 13-mile corridor.

NTE | I-35W

The $1.6 billion NTE | I-35W project spans 10 miles in Fort Worth from north of I-30 to US 81/287. It is being built in coordination between NTE Mobility Partners Segments 3, LLC (NTEMP3) and TxDOT. I-35W from north of I-820 to US 81/287 reached substantial completion in December 2016. I-35W from north of I-30 to north of I-820 is estimated for completion in 2018.

TxDOT has received a proposal from NTEMP3 to rebuild I-35W from US 81/287 to Eagle Parkway. This eight-mile project is estimated to begin construction in 2018.