Tabulation of Bids for Project RMC - 638953001
Use this interactive Tableau dashboard to display bidding information on projects let through statewide and local district letting for the past 24 months.
The Electronic State Business Daily (ESBD), the Electronic Bidding System, and the project proposal are the official sources of advertisement and bidding information for the State and Local Lettings. Bidders should bid the project using the information found therein, including any addenda. These sources take precedence over information from other sources, including TxDOT webpages, which are unofficial and intended for informational purposes only.
Text version of this page | |||
County: | DALLAS | Let Date: | 01/06/22 |
Type: | BRIDGE REPAIR | Seq No: | 4007 |
Time: | 120 CALENDAR DAYS | Project ID: | RMC - 638953001 |
Highway: | US0175 | Contract #: | 01224007 |
Length: | 0.010 | CCSJ: | 6389-53-001 |
Limits: | |||
From: | VARIOUS ROADWAYS | Check: | $11,000 |
To: | SOUTHEAST DALLAS MAINTENANCE SECTIO | Misc Cost: |
Estimate | $571,726.00 | % Over/Under | Company |
Bidder 1 | $567,860.00 | -0.68% | HIGHWAY 19 CONSTRUCTION LLC |
Bidder 2 | $634,080.00 | +10.91% | TALBRAN ENTERPRISES LLC |
Bidder 3 | $665,100.00 | +16.33% | IBCTX, LLC |
Bidder 4 | $884,340.00 | +54.68% | FNH CONSTRUCTION, LLC |
Bidder 5 | $1,121,620.00 | +96.18% | BUILT RIGHT CONSTRUCTION OF OKLAHOMA, LLC |
Bidder 6 | $1,150,486.00 | +101.23% | GIBSON & ASSOCIATES, INC. |
Item Code | Description | Unit | Quantity | Unit Est. | Bidder | Unit Bid |
1006002 | PREPARING ROW | STA | 11.000 | 2,000.00 | 1 2 3 4 5 6 | 5,000.000 4,000.000 2,000.000 6,600.000 1,000.000 1,650.000 |
4206158 | CL C CONC(PILE ENCASEMENT) | LF | 1,330.000 | 350.00 | 1 2 3 4 5 6 | 230.000 340.000 400.000 500.000 700.000 775.000 |
5006001 | MOBILIZATION | LS | 1.000 | 52,066.00 | 1 2 3 4 5 6 | 100,000.000 60,000.000 66,000.000 80,000.000 100,000.000 31,000.000 |
5026001008 | BARRICADES, SIGNS AND TRAFFIC HANDLING | MO | 4.000 | 2,500.00 | 1 2 3 4 5 6 | 15,000.000 3,600.000 2,500.000 8,500.000 925.000 6,500.000 |
5066020002 | CONSTRUCTION EXITS (INSTALL) (TY 1) | SY | 672.000 | 20.00 | 1 2 3 4 5 6 | 45.000 50.000 40.000 30.000 75.000 41.000 |
5066024002 | CONSTRUCTION EXITS (REMOVE) | SY | 672.000 | 10.00 | 1 2 3 4 5 6 | 10.000 40.000 10.000 15.000 35.000 22.000 |
61856002002 | TMA (STATIONARY) | DAY | 10.000 | 200.00 | 1 2 3 4 5 6 | 1,000.000 300.000 150.000 250.000 200.000 225.000 |