Monthly Local Let Maintenance Report For Waco District As Of Apr 11, 2014 Page 2 Of 3

Last Update: Friday, April 11, 2014
FTP Icon
page 1 | page 2 | page 3

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyCORYELL
Highway US0084
From TXDOT COMPLEX
To IN CORYELL COUNTY
CSJ 6259-82-001
Proj ID SUP - 625982001
Work Type LAWN AND GROUNDS MAINTENANCE
 
0.100 14290.00 0.00 1890.00 13.2
Work Order 08-21-13
Work Began 09-01-13
Work Completed  
Time Computed 09-01-13
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 212
Percent Time Used 58
Contractor(s)
TIBH INDUSTRIES, INC.
GOODWILL CONTRACT SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6259-82-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08130932
Totals 14290.00 0.00 1890.00 13.2

CountyHAMILTON
Highway FM0218
From VARIOUS
To VARIOUS
CSJ 6259-83-001
Proj ID SUP - 625983001
Work Type PICNIC AREA MAINTENANCE
 
0.100 42090.00 1890.00 14310.00 33.9
Work Order 08-21-13
Work Began 09-01-13
Work Completed  
Time Computed 09-01-13
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 212
Percent Time Used 58
Contractor(s)
TIBH INDUSTRIES, INC.
GOODWILL CONTRACT SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6259-83-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08130933
Totals 42090.00 1890.00 14310.00 33.9

CountyHILL
Highway SH0081
From TXDOT COMPLEX IN
To HILL COUNTY
CSJ 6259-84-001
Proj ID SUP - 625984001
Work Type LAWN AND GROUNDS MAINTENANCE
 
1.100 9290.00 0.00 1670.00 17.9
Work Order 08-21-13
Work Began 09-01-13
Work Completed  
Time Computed 09-01-13
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 212
Percent Time Used 58
Contractor(s)
TIBH INDUSTRIES, INC.
GOODWILL CONTRACT SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6259-84-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08130934
Totals 9290.00 0.00 1670.00 17.9

CountyFALLS
Highway SH0006
From VARIOUS
To VARIOUS
CSJ 6259-85-001
Proj ID SUP - 625985001
Work Type LAWN AND GROUNDS MAINTENANCE
 
0.010 9765.00 860.00 1600.00 16.3
Work Order 08-21-13
Work Began 09-01-13
Work Completed  
Time Computed 09-01-13
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 212
Percent Time Used 58
Contractor(s)
GOODWILL CONTRACT SERVICES, INC.
TIBH INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6259-85-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08130935
Totals 9765.00 860.00 1600.00 16.3

CountyBOSQUE
Highway SH0006
From VARIOUS ROADWAYS IN
To BOSQUE COUNTY
CSJ 6259-86-001
Proj ID SUP - 625986001
Work Type PICNIC AREA MAINTENANCE
 
0.010 50400.00 2115.00 17090.00 33.9
Work Order 08-21-13
Work Began 09-01-13
Work Completed  
Time Computed 09-01-13
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 212
Percent Time Used 58
Contractor(s)
GOODWILL CONTRACT SERVICES, INC.
TIBH INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6259-86-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08130936
Totals 50400.00 2115.00 17090.00 33.9

CountyLIMESTONE
Highway US0084
From VARIOUS
To VARIOUS
CSJ 6259-87-001
Proj ID SUP - 625987001
Work Type LAWN AND GROUNDS MAINTENANCE
 
0.010 7750.00 0.00 1400.00 18.0
Work Order 08-21-13
Work Began 09-01-13
Work Completed  
Time Computed 09-01-13
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 212
Percent Time Used 58
Contractor(s)
GOODWILL CONTRACT SERVICES, INC.
TIBH INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6259-87-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08130937
Totals 7750.00 0.00 1400.00 18.0

CountyLIMESTONE
Highway US0084
From VARIOUS ROADWAYS IN
To LIMESTONE CO.
CSJ 6259-88-001
Proj ID SUP - 625988001
Work Type PICNIC AREA MAINTENANCE
 
0.010 38300.00 1755.00 14555.00 38.0
Work Order 08-21-13
Work Began 09-01-13
Work Completed  
Time Computed 09-01-13
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 212
Percent Time Used 58
Contractor(s)
TIBH INDUSTRIES, INC.
GOODWILL CONTRACT SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6259-88-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08130938
Totals 38300.00 1755.00 14555.00 38.0

CountyMCLENNAN
Highway FM3476
From VARIOUS
To VARIOUS
CSJ 6259-89-001
Proj ID SUP - 625989001
Work Type LAWN AND GROUNDS MAINTENANCE
 
0.010 20088.00 0.00 2580.00 12.8
Work Order 08-21-13
Work Began 09-01-13
Work Completed  
Time Computed 09-01-13
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 212
Percent Time Used 58
Contractor(s)
TIBH INDUSTRIES, INC.
GOODWILL CONTRACT SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6259-89-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08130939
Totals 20088.00 0.00 2580.00 12.8

CountyLIMESTONE
Highway US0084
From VARIOUS
To VARIOUS
CSJ 6259-90-001
Proj ID SUP - 625990001
Work Type JANITORIAL SERVICE
 
0.010 6700.00 450.00 3150.00 47.0
Work Order 08-30-13
Work Began 09-01-13
Work Completed  
Time Computed 09-01-13
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 212
Percent Time Used 58
Contractor(s)
CEN-TEX ASSOCIATION FOR RETARDED CHILDREN
TIBH INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6259-90-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08130946
Totals 6700.00 450.00 3150.00 47.0

CountyMCLENNAN
Highway SH0006
From VARIOUS ROADWAYS IN
To MCLENNAN COUNTIES
CSJ 6259-91-001
Proj ID SUP - 625991001
Work Type LITTER PICK UP & DISPOSAL
 
0.010 87830.23 3844.67 30538.88 34.7
Work Order 08-27-13
Work Began 09-01-13
Work Completed  
Time Computed 09-01-13
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 212
Percent Time Used 58
Contractor(s)
GOODWILL CONTRACT SERVICES, INC.
TIBH INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6259-91-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08130947
Totals 87830.23 3844.67 30538.88 34.7

CountyCORYELL
Highway US0084
From VARIOUS
To VARIOUS
CSJ 6259-92-001
Proj ID SUP - 625992001
Work Type PICNIC AREA MAINTENANCE
 
0.100 45620.00 2340.00 21065.00 46.1
Work Order 08-21-13
Work Began 09-01-13
Work Completed  
Time Computed 09-01-13
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 212
Percent Time Used 58
Contractor(s)
TIBH INDUSTRIES, INC.
GOODWILL CONTRACT SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6259-92-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08130940
Totals 45620.00 2340.00 21065.00 46.1

CountyHAMILTON
Highway US0281
From TXDOT COMPLEX
To IN HAMILTON COUNTY
CSJ 6259-93-001
Proj ID SUP - 625993001
Work Type LAWN AND GROUNDS MAINTENANCE
 
0.100 5450.00 0.00 1175.00 21.5
Work Order 08-21-13
Work Began 09-01-13
Work Completed  
Time Computed 09-01-13
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 212
Percent Time Used 58
Contractor(s)
TIBH INDUSTRIES, INC.
GOODWILL CONTRACT SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6259-93-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08130941
Totals 5450.00 0.00 1175.00 21.5

CountyHILL
Highway SH0081
From VARIOUS
To VARIOUS
CSJ 6259-94-001
Proj ID SUP - 625994001
Work Type PICNIC AREA MAINTENANCE
 
0.100 42600.00 2070.00 16910.00 39.6
Work Order 08-21-13
Work Began 09-01-13
Work Completed  
Time Computed 09-01-13
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 212
Percent Time Used 58
Contractor(s)
TIBH INDUSTRIES, INC.
GOODWILL CONTRACT SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6259-94-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08130942
Totals 42600.00 2070.00 16910.00 39.6

CountyFALLS
Highway SH0006
From VARIOUS ROADWAYS IN
To FALLS COUNTY
CSJ 6259-95-001
Proj ID SUP - 625995001
Work Type PICNIC AREA MAINTENANCE
 
0.010 31300.00 1875.00 13095.00 41.8
Work Order 08-21-13
Work Began 09-01-13
Work Completed  
Time Computed 09-01-13
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 212
Percent Time Used 58
Contractor(s)
TIBH INDUSTRIES, INC.
GOODWILL CONTRACT SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6259-95-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08130943
Totals 31300.00 1875.00 13095.00 41.8

CountyMCLENNAN
Highway SP0299
From VARIOUS
To VARIOUS
CSJ 6259-96-001
Proj ID SUP - 625996001
Work Type CLEANING / SWEEPING DISTRICT COMPLEX
 
0.010 5200.00 450.00 2700.00 51.9
Work Order 08-21-13
Work Began 09-01-13
Work Completed  
Time Computed 09-01-13
Contract Working Days 104
Addl Days Granted 0
Working Days Charged 54
Percent Time Used 51
Contractor(s)
TIBH INDUSTRIES, INC.
GOODWILL CONTRACT SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6259-96-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08130944
Totals 5200.00 450.00 2700.00 51.9

CountyMCLENNAN
Highway FM0933
From VARIOUS
To VARIOUS
CSJ 6259-97-001
Proj ID SUP - 625997001
Work Type LAWN AND GROUNDS MAINTENANCE
 
0.010 6125.00 0.00 390.00 6.3
Work Order 08-21-13
Work Began 09-01-13
Work Completed  
Time Computed 09-01-13
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 212
Percent Time Used 58
Contractor(s)
TIBH INDUSTRIES, INC.
GOODWILL CONTRACT SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6259-97-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08130945
Totals 6125.00 0.00 390.00 6.3

CountyBOSQUE
Highway SH0006
From BOSQUE MAINTENANCE COUNTY LAWN
To AND GROUNDS
CSJ 6260-35-001
Proj ID SUP - 626035001
Work Type LAWN AND GROUNDS MAINTENANCE
 
0.010 17300.00 0.00 4050.00 23.4
Work Order 06-24-13
Work Began 07-01-13
Work Completed  
Time Computed 07-01-13
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 274
Percent Time Used 75
Contractor(s)
GOODWILL CONTRACT SERVICES, INC.
TIBH INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6260-35-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06130930
Totals 17300.00 0.00 4050.00 23.4

CountyHILL
Highway SH0081
From VARIOUS ROADWAYS IN HILL, LIMESTONE AND
To FALLS COUNTIES
CSJ 6260-37-001
Proj ID BPM - 626037001
Work Type BRIDGE PREVENTIVE MAINTENANCE
 
0.100 232137.00 11860.00 11860.00 5.1
Work Order 02-10-14
Work Began 03-10-14
Work Completed  
Time Computed 02-27-14
Contract Working Days 100
Addl Days Granted 0
Working Days Charged 19
Percent Time Used 19
Contractor(s)
TEXAS TREE & LANDSCAPE, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6260-37-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12130911
Totals 232137.00 11860.00 11860.00 5.1

CountyMCLENNAN
Highway FM2491
From VARIOUS ROADWAYS IN BOSQUE, CORYELL,
To HAMILTON AND MCLENNAN COUNTIES
CSJ 6260-38-001
Proj ID BPM - 626038001
Work Type BRIDGE PREVENTIVE MAINTENANCE
 
0.010 153213.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 02-27-14
Work Began 03-04-14
Work Completed  
Time Computed 03-10-14
Contract Working Days 75
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
BECK-REIT & SONS, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6260-38-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12130912
Totals 153213.00 0.00 0.00 0.0

CountyMCLENNAN
Highway US0084
From VARIOUS ROADWAYS IN
To MCLENNAN COUNTY
CSJ 6262-76-001
Proj ID RMC - 626276001
Work Type CONCRETE PAVEMENT & SPALL REPAIR
 
0.010 276650.00 130144.66 130144.66 47.0
Work Order 11-22-13
Work Began 03-06-14
Work Completed  
Time Computed 12-07-13
Contract Working Days 120
Addl Days Granted 0
Working Days Charged 15
Percent Time Used 12
Contractor(s)
VANN/ELLI, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6262-76-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10130901
Totals 276650.00 130144.66 130144.66 47.0