Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyMCLENNAN
Highway SH0006
From VARIOUS
To VARIOUS
CSJ 6245-89-001
Proj ID SUP - 624589001
Work Type LITTER PICK UP & DISPOSAL
 
0.010 91385.70 1753.27 34508.27 37.7
Work Order 08-30-12
Work Began 09-01-12
Work Completed  
Time Computed 09-01-12
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 242
Percent Time Used 66
Contractor(s)
GOODWILL CONTRACT SERVICES, INC.
TIBH INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6245-89-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08120934
Totals 91385.70 1753.27 34508.27 37.7

CountyBELL
Highway SH0095
From PICNIC AREA
To ON SH 95
CSJ 6245-90-001
Proj ID SUP - 624590001
Work Type PICNIC AREA MAINTENANCE
 
0.010 14900.00 1060.00 7460.00 50.0
Work Order 08-30-12
Work Began 09-01-12
Work Completed  
Time Computed 09-01-12
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 242
Percent Time Used 66
Contractor(s)
TIBH INDUSTRIES, INC.
GOODWILL CONTRACT SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6245-90-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08120935
Totals 14900.00 1060.00 7460.00 50.0

CountyBELL
Highway LP0121
From BELL COUNTY AREA
To ENGINEER AND MAINT. OFFICE
CSJ 6245-91-001
Proj ID SUP - 624591001
Work Type LAWN AND GROUND MAINTENANCE
 
0.010 12835.00 1955.00 4795.00 37.3
Work Order 08-29-12
Work Began 09-01-12
Work Completed  
Time Computed 09-01-12
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 242
Percent Time Used 66
Contractor(s)
TIBH INDUSTRIES, INC.
GOODWILL CONTRACT SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6245-91-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08120936
Totals 12835.00 1955.00 4795.00 37.3

CountyCORYELL
Highway US0084
From VARIOUS
To VARIOUS
CSJ 6245-92-001
Proj ID SUP - 624592001
Work Type PICNIC AREA MAINTENANCE
 
0.010 45010.00 2990.00 23690.00 52.6
Work Order 08-30-12
Work Began 09-01-12
Work Completed  
Time Computed 09-01-12
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 242
Percent Time Used 66
Contractor(s)
TIBH INDUSTRIES, INC.
GOODWILL CONTRACT SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6245-92-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08120937
Totals 45010.00 2990.00 23690.00 52.6

CountyHAMILTON
Highway US0281
From VARIOUS
To VARIOUS
CSJ 6245-93-001
Proj ID SUP - 624593001
Work Type PICNIC AREA MAINTENANCE
 
0.010 53850.00 3690.00 25470.00 47.2
Work Order 08-21-12
Work Began 09-01-12
Work Completed  
Time Computed 09-01-12
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 242
Percent Time Used 66
Contractor(s)
TIBH INDUSTRIES, INC.
GOODWILL CONTRACT SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6245-93-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08120948
Totals 53850.00 3690.00 25470.00 47.2

CountyHILL
Highway SH0081
From VARIOUS
To VARIOUS
CSJ 6245-94-001
Proj ID SUP - 624594001
Work Type picnic area maintenance
 
0.010 41800.00 3665.00 20575.00 49.2
Work Order 08-30-12
Work Began 09-01-12
Work Completed  
Time Computed 09-01-12
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 242
Percent Time Used 66
Contractor(s)
TIBH INDUSTRIES, INC.
GOODWILL CONTRACT SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6245-94-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08120947
Totals 41800.00 3665.00 20575.00 49.2

CountyFALLS
Highway SH0006
From VARIOUS
To VARIOUS
CSJ 6245-95-001
Proj ID SUP - 624595001
Work Type LAWN & GROUNDS MAINTENANCE
 
0.010 9750.00 0.00 2285.00 23.4
Work Order 08-30-12
Work Began 09-01-12
Work Completed  
Time Computed 09-01-12
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 242
Percent Time Used 66
Contractor(s)
GOODWILL CONTRACT SERVICES, INC.
TIBH INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6245-95-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08120940
Totals 9750.00 0.00 2285.00 23.4

CountyMCLENNAN
Highway SP0299
From DISTRICT COMPLEX LOCATED AT
To 100 S. LOOP DRIVE
CSJ 6245-96-001
Proj ID SUP - 624596001
Work Type CLEANING / SWEEPING SIDEWALKS / PORCHES
 
0.010 5200.00 350.00 3025.00 58.1
Work Order 08-30-12
Work Began 09-01-12
Work Completed  
Time Computed 09-01-12
Contract Working Days 208
Addl Days Granted 0
Working Days Charged 62
Percent Time Used 29
Contractor(s)
GOODWILL CONTRACT SERVICES, INC.
TIBH INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6245-96-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08120941
Totals 5200.00 350.00 3025.00 58.1

CountyLIMESTONE
Highway US0084
From VARIOUS
To VARIOUS
CSJ 6245-97-001
Proj ID SUP - 624597001
Work Type JANITORIAL SERVICES
 
0.010 6700.00 450.00 3600.00 53.7
Work Order 08-30-12
Work Began 09-01-12
Work Completed  
Time Computed 09-01-12
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 242
Percent Time Used 66
Contractor(s)
CEN-TEX ASSOCIATION FOR RETARDED CHILDREN
TIBH INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6245-97-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08120942
Totals 6700.00 450.00 3600.00 53.7

CountyMCLENNAN
Highway FM3476
From VARIOUS
To VARIOUS
CSJ 6245-99-001
Proj ID SUP - 624599001
Work Type LAWN & GROUNDS MAINTENANCE
 
0.010 20078.00 1720.00 7080.00 35.2
Work Order 08-30-12
Work Began 09-01-12
Work Completed  
Time Computed 09-01-12
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 242
Percent Time Used 66
Contractor(s)
GOODWILL CONTRACT SERVICES, INC.
TIBH INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6245-99-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08120943
Totals 20078.00 1720.00 7080.00 35.2

CountyMCLENNAN
Highway FM0933
From TXDOT COMPLEX LOCATED AT 3119 GHOLSON
To ROAD
CSJ 6246-00-001
Proj ID SUP - 624600001
Work Type LAWN AND GROUNDS MAINTENANCE
 
0.010 6125.00 0.00 390.00 6.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-30-12
Work Began 09-01-12
Work Completed  
Time Computed 09-01-12
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 212
Percent Time Used 58
Contractor(s)
GOODWILL CONTRACT SERVICES, INC.
TIBH INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6246-00-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08120944
Totals 6125.00 0.00 390.00 6.3

CountyHILL
Highway SH0081
From VARIOUS
To VARIOUS
CSJ 6246-01-001
Proj ID SUP - 624601001
Work Type lawn and grounds maintenance
 
0.010 9235.00 740.00 3985.00 43.1
Work Order 08-29-12
Work Began 09-01-12
Work Completed  
Time Computed 09-01-12
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 242
Percent Time Used 66
Contractor(s)
TIBH INDUSTRIES, INC.
GOODWILL CONTRACT SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6246-01-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08120946
Totals 9235.00 740.00 3985.00 43.1

CountyHILL
Highway SH0022
From VARIOUS ROADWAYS IN BOSQUE, HILL AND
To LIMESTONE COUNTIES
CSJ 6246-58-001
Proj ID BPM - 624658001
Work Type BRIDGE PREVENTATIVE MAINTENANCE
 
0.010 243073.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 75
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
BECK-REIT & SONS, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6246-58-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04130904
Totals 243073.00 0.00 0.00 0.0

CountyHILL
Highway SH0171
From VARIOUS ROADWAYS IN FALLS, HILL,
To LIMESTONE AND MCLENNAN COUNTIES
CSJ 6248-14-001
Proj ID RMC - 624814001
Work Type MULTI - COUNTY PAVEMENT MARKINGS
 
0.010 132692.50 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 82
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TEXAS TREE & LANDSCAPE, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6248-14-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09120902
Totals 132692.50 0.00 0.00 0.0

CountyCORYELL
Highway US0084
From TXDOT COMPLEX
To IN CORYELL COUNTY
CSJ 6249-20-001
Proj ID SUP - 624920001
Work Type LAWN AND GROUNDS MAINTENANCE
 
0.010 14250.00 1740.00 4450.00 31.2
Work Order 08-29-12
Work Began 09-01-12
Work Completed  
Time Computed 09-01-12
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 242
Percent Time Used 66
Contractor(s)
TIBH INDUSTRIES, INC.
GOODWILL CONTRACT SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6249-20-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08120945
Totals 14250.00 1740.00 4450.00 31.2

CountyBELL
Highway SH0195
From STATE MAINTAINED RURAL ROADWAYS
To IN BELL COUNTY
CSJ 6250-51-001
Proj ID RMC - 625051001
Work Type RURAL MOWING OF RIGHT OF WAY
 
279.490 129697.26 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 49
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
GREG SCRUGGS
SUBCONTRACTOR(S) FOR CCSJ: 6250-51-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12120901
Totals 129697.26 0.00 0.00 0.0

CountyCORYELL
Highway SH0036
From STATE MAINTAINED ROADWAYS
To IN CORYELL COUNTY
CSJ 6250-52-001
Proj ID RMC - 625052001
Work Type MOWING AND LITTER PICKUP AND DISPOSAL
 
272.300 157756.28 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 113
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TEXAS TREE & LANDSCAPE, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6250-52-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12120902
Totals 157756.28 0.00 0.00 0.0

CountyHAMILTON
Highway US0281
From STATE MAINTAINED ROADWAYS
To IN HAMILTON COUNTY
CSJ 6250-53-001
Proj ID RMC - 625053001
Work Type MOWING AND LITTER PICKUP AND DISPOSAL
 
287.541 129924.73 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 89
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TEXAS TREE & LANDSCAPE, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6250-53-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12120903
Totals 129924.73 0.00 0.00 0.0

CountyHILL
Highway SH0171
From STATE MAINTAINED ROADWAYS
To HILL COUNTY
CSJ 6250-54-001
Proj ID RMC - 625054001
Work Type MOWING ROW & LITTER PICKUP AND DISPOSAL
 
221.740 209531.30 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 124
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
CEN-TEX IRRIGATION SYSTEMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6250-54-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12120904
Totals 209531.30 0.00 0.00 0.0

CountyFALLS
Highway SH0007
From VARIOUS ROADWAYS IN
To FALLS COUNTY
CSJ 6250-55-001
Proj ID RMC - 625055001
Work Type MOWING HIGHWAY RIGHT OF WAY
 
338.743 159083.41 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 63
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
P-VILLE, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6250-55-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12120905
Totals 159083.41 0.00 0.00 0.0