Monthly State Let Maintenance Report For Odessa District As Of Sep 15, 2014 Page 1 Of 1

Last Update: Monday, September 15, 2014
FTP Icon
page 1

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyPECOS
Highway IH0010
From MM 253-00725
To MM 282+00345
CSJ 6236-19-001
Proj ID BPM - 623619001
Work Type REMOVE & REPLACE BRIDGE CLASS CULVERTS
 
0.001 753603.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
RELMCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6236-19-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02124004
Totals 753603.00 0.00 0.00 0.0

CountyMIDLAND
Highway IH0020
From VARIOUS
To VARIOUS
CSJ 6252-18-001
Proj ID RMC - 625218001
Work Type MISCELLANEOUS CONCRETE
 
0.001 471333.50 0.00 343904.99 72.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-21-13
Work Began 12-02-13
Work Completed  
Time Computed 12-02-13
Contract Working Days 40
Addl Days Granted 75
Working Days Charged 109
Percent Time Used 94
Contractor(s)
EASTER CONSTRUCTION INC.
SUBCONTRACTOR(S) FOR CCSJ: 6252-18-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08134002
Totals 471333.50 0.00 343904.99 72.9

CountyREEVES
Highway IH0020
From VARIOUS
To VARIOUS
CSJ 6260-32-001
Proj ID BPM - 626032001
Work Type BRIDGE SUBSTRUCURE REPAIR
 
0.001 887135.00 0.00 703549.00 79.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-26-14
Work Began 06-04-14
Work Completed  
Time Computed 06-02-14
Contract Working Days 120
Addl Days Granted 0
Working Days Charged 65
Percent Time Used 54
Contractor(s)
SCR CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 6260-32-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03144003
Totals 887135.00 0.00 703549.00 79.3

CountyWARD
Highway IH0020
From VARIOUS
To VAIOUS
CSJ 6266-66-001
Proj ID RMC - 626666001
Work Type MILL AND INLAY
 
0.001 954065.62 0.00 1609917.34 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-28-14
Work Began 00-00-00
Work Completed  
Time Computed 04-30-14
Contract Working Days 40
Addl Days Granted 20
Working Days Charged 42
Percent Time Used 70
Contractor(s)
REECE ALBERT, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6266-66-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01144009
Totals 954065.62 0.00 1609917.34 99.9

CountyMIDLAND
Highway IH0020
From VARIOUS
To VARIOUS
CSJ 6268-36-001
Proj ID RMC - 626836001
Work Type BRIDGE REPAIR
 
0.001 626520.00 0.00 604996.32 96.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-15-14
Work Began 00-00-00
Work Completed  
Time Computed 05-20-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 104
Percent Time Used 28
Contractor(s)
SCR CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 6268-36-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02144018
Totals 626520.00 0.00 604996.32 96.5

CountyECTOR
Highway IH0020
From VAR
To VAR
CSJ 6271-35-001
Proj ID RMC - 627135001
Work Type LARGE SIGN REPLACEMENT (CALLOUT)
 
0.001 547500.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-29-14
Work Began 00-00-00
Work Completed  
Time Computed 08-29-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
WILLIS ELECTRIC CO., LP
SUBCONTRACTOR(S) FOR CCSJ: 6271-35-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07144004
Totals 547500.00 0.00 0.00 0.0

page 1