AVERAGE LOW BID UNIT PRICE - MAINTENANCE - ODESSA DISTRICT

Last Update: Thursday, March 20, 2014
ITEMS 712 2005 TO 788 2004
Items Items Bid Code Range
0104 - 0110
0216 - 0275
0310 - 0354
0416 - 0496
0500 - 0545
0610 - 0677
0712 - 0788
3270 - 3270
4100 - 4100
6834 - 6834
8251 - 8251
712 2005 - 788 2004
Item No Description Units February 28, 2014 Twelve Month Moving Usage
Quantity Avg Bid Quantity Avg Bid
712 2005 JT / CRCK SEAL (RUBBER - ASPHALT) LMI     1,890.800 276.90671 2
730 2001 STRIP MOWING AC     6,640.000 25.78340 9
730 2002 FULL - WIDTH MOWING AC     55,990.000 22.41340 9
734 2001 LITTER REMOVAL AC     11,262.360 9.55101 2
738 2002 CLEANING / SWEEPING (CENTER MEDIAN) MI     479.520 129.00000 2
738 2004 CLEANING / SWEEPING (OUTSIDE MAIN LANE) MI     1,622.880 131.37504 2
738 2006 CLEANING / SWEEPING (FRONTAGE ROAD) MI     440.280 129.00000 2
738 2008 CLEANING / SWEEPING (ENTRANCE / EXIT RAMP) MI     63.600 134.00000 2
745 2010 GROUNDS MAINT - PICNIC MOW / TRIM - SITE (1) CYC     36.000 55.00000 1
745 2011 GROUNDS MAINT - PICNIC MOW / TRIM - SITE (2) CYC     36.000 55.00000 1
745 2012 GROUNDS MAINT - PICNIC MOW / TRIM - SITE (3) CYC     36.000 55.00000 1
745 2013 GROUNDS MAINT - PICNIC MOW / TRIM - SITE (4) CYC     36.000 55.00000 1
745 2100 JANITORIAL MAINT - PICNIC AREA - SITE (1) CYC     208.000 78.00000 1
745 2101 JANITORIAL MAINT - PICNIC AREA - SITE (2) CYC     208.000 78.00000 1
745 2102 JANITORIAL MAINT - PICNIC AREA - SITE (3) CYC     208.000 78.00000 1
745 2103 JANITORIAL MAINT - PICNIC AREA - SITE (4) CYC     208.000 78.00000 1
764 2001 DRAIN INLET CLEANING EA 92.000 175.00000 92.000 175.00000 1
764 2002 PUMP STATION WELL CLEANING EA 32.000 1,800.00000 32.000 1,800.00000 1
764 2007 STORM SEWER CLEANING (PIPE) (19" - 24" DIA LF 734.000 9.00000 734.000 9.00000 1
764 2010 STORM SEWER CLEANING (PIPE) (37" - 42" DIA LF 476.000 10.00000 476.000 10.00000 1
764 2011 STORM SEWER CLEANING (PIPE) (43" - 54" DIA LF 334.000 12.00000 334.000 12.00000 1
770 2001 REPAIR RAIL ELEMENT (W - BEAM) LF     5,500.000 20.00000 2
770 2002 REPAIR RAIL ELEMENT (THRIE - BEAM) LF     250.000 1.00000 2
770 2003 REP RAIL ELMNT (THRIE - BM TRANS TO W - BM) LF     250.000 1.00000 2
770 2004 REM / REPL TIMBER / STL POST W / O CONC FND EA     500.000 32.00000 2
770 2005 REM / REPL TIMBER / STL POST W / CONC FND EA     150.000 30.00000 2
770 2006 REALIGN POSTS EA     500.000 3.00000 2
770 2007 REPAIR OF TERMINAL ANCHORS POSTS EA     10.000 1.00000 2
770 2014 REPAIR STEEL POST WITH BASE PLATE EA     40.000 50.50000 2
770 2027 REMOVE & REPLACE BLOCKOUT EA     700.000 4.00000 2
770 2035 REPAIR RAIL ELEMENT (CURVED RAIL) LF     200.000 11.00000 2
772 2005 POST AND CABLE FENCE (REMV / REPL POSTS) EA     140.000 5.00000 1
772 2006 POST AND CABLE FENCE (RMV / REPL CNC ANCH EA     35.000 1.00000 1
772 2007 POST AND CABLE FENCE (REMV / REPL CABLE) LF     3,500.000 1.00000 1
788 2001 CONCRETE BEAM REPAIR EA 9.000 11,270.00000 16.000 9,433.12500 4
788 2002 CONCRETE BEAM REPAIR (CFRP) EA 9.000 15,770.00000 9.000 15,770.00000 1
788 2003 CONCRETE BEAM REP (STRAND SPLICE & CFRP EA 9.000 22,770.00000 9.000 22,770.00000 1
788 2004 CONCRETE BEAM REP (STRAND SPLICE) EA 9.000 14,770.00000 17.000 12,966.47059 3