Monthly State Let Maintenance Report For Lufkin District As Of Apr 11, 2014 Page 1 Of 1

Last Update: Friday, April 11, 2014
FTP Icon
page 1

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyHOUSTON
Highway US0287
From FM 2423
To EDENS ST
CSJ 6226-40-001
Proj ID RMC - 622640001
Work Type CONSTRUCTION OF STORM SEWER
 
0.575 818986.69 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
A R BROTHERS CONSTRUCTION SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6226-40-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02144019
Totals 818986.69 0.00 0.00 0.0

CountySHELBY
Highway US0059
From US 59 & VARIOUS LOCATIONS WITHIN
To SHELBY,SAN AUG, AND SABINE COUNTIES
CSJ 6249-12-001
Proj ID RMC - 624912001
Work Type INSTALL RAISED PAVEMENT MARKINGS
 
0.010 185500.00 0.00 170863.84 92.1
Work Order 11-28-12
Work Began 12-17-12
Work Completed  
Time Computed 12-06-12
Contract Working Days 365
Addl Days Granted 180
Working Days Charged 398
Percent Time Used 73
Contractor(s)
BRYDL CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6249-12-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10124015
Totals 185500.00 0.00 170863.84 92.1

CountyANGELINA
Highway US0059
From US 59 & VARIOUS LOCATIONS WITHIN
To ANGELINA,HOUSTON & NACOG COUNTIES
CSJ 6249-14-001
Proj ID RMC - 624914001
Work Type INSTALL RAISED PAVEMENT MARKINGS
 
0.010 185050.00 0.00 206268.65 99.9
Work Order 11-28-12
Work Began 12-20-12
Work Completed  
Time Computed 12-06-12
Contract Working Days 365
Addl Days Granted 180
Working Days Charged 398
Percent Time Used 73
Contractor(s)
BRYDL CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6249-14-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10124014
Totals 185050.00 0.00 206268.65 99.9

page 1