Items Items Bid Code Range
0100 - 0193
0216 - 0275
0305 - 0361
0400 - 0496
0500 - 0560
0610 - 0690
0712 - 0788
1013 - 1122
2022 - 2328
3042 - 3289
4013 - 4681
5369 - 5941
6006 - 6834
7622 - 7624
8020 - 8999
400 2001 - 430 2232
430 4128 - 465 2027
465 2029 - 466 2309
466 2326 - 496 2084
Item No Description Units February 28, 2015 Twelve Month Moving Usage
Quantity Avg Bid Quantity Avg Bid
430 4128 CL C CONC FOR EXT STRU (CULV) (5' X 6.5' EA     26.000 465.00000 1
430 4129 CL C CONC FOR EXT STRU (CULV) (6'X 5.5' LF     18.000 440.00000 1
430 4130 CL C CONC FOR EXT STRU (CULV) (5.5'X 5' LF     8.000 500.00000 1
432 2001 RIPRAP (CONC) (4 IN) CY 30.000 430.00000 735.000 326.95918 7
432 2002 RIPRAP (CONC) (5 IN) CY 29.000 440.00000 1,286.840 316.21990 8
432 2015 RIPRAP (STONE COMMON) (DRY) (6 IN) CY     84.000 77.50000 2
432 2019 RIPRAP (STONE PROTECTION) (12 IN) CY     5,554.000 58.61001 2
432 2021 RIPRAP (STONE PROTECTION) (18 IN) CY     6,518.000 61.77570 6
432 2023 RIPRAP (STONE PROTECTION) (24 IN) CY 1,255.000 90.00000 5,433.000 66.66593 3
432 2024 RIPRAP (STONE PROTECTION) (30 IN) CY 1,564.000 85.00000 1,564.000 85.00000 1
432 2033 RIPRAP (STONE COMMON) (DRY) (12 IN) CY     508.000 88.88976 2
432 2035 RIPRAP (CONC) (6 IN) CY     63.400 391.45994 1
432 2039 RIPRAP (MOW STRIP) (4 IN) CY 86.000 468.60465 891.900 406.44467 10
432 2040 RIPRAP (MOW STRIP) (5 IN) CY     61.840 275.00000 1
432 2041 RIPRAP (STONE COMMON) (DRY) (18 IN) CY     1,666.000 95.00000 2
432 2066 RIPRAP (CONC) (CL B) CY     115.800 461.38601 5
432 2071 RIPRAP (STONE COMMON) (DRY) (24 IN) CY 400.000 90.00000 400.000 90.00000 1
432 2072 RIPRAP (CONC) (CL B) (RR8 & RR9) CY     239.300 404.41914 2
432 2084 RIPRAP (CONC) (CL B) (4") CY     38.000 400.00000 1
432 2098 RIPRAP (CONC) (SIGN MOUNTS) (CL B) CY     64.000 485.47500 3
438 2001 CLEAN EXIST JOINTS LF     438.000 14.75342 4
438 2002 CLEAN AND SEAL EXIST JOINTS LF 528.000 26.00000 2,176.000 30.04963 5
439 2012 LATEX - MODIFIED CONC OVERLAY (2 IN) SY     84.000 150.00000 1
442 2047 STRUCTURAL STEEL (MISCELLANEOUS BRIDGE) LB     1,502.000 5.72403 2
442 2048 STRUCTURAL STEEL (MISC NON - BRIDGE) LB     7,298.000 8.00000 2
450 2003 RAIL (TY T203) LF     2,350.000 69.00000 1
450 2013 RAIL (TY SSTR) LF     260.000 70.00000 1
450 2018 RAIL (TY C411) LF     3,104.190 125.81380 2
450 2025 RAIL (TY PR1) LF     159.000 61.78000 1
450 2026 RAIL (TY PR2) LF     91.900 72.00000 1
450 2028 RAIL (TY C411) (MOD) LF     96.000 125.00000 1
450 2044 RAIL (PEDESTRIAN) (SPL) LF     7,373.000 350.00000 1
450 2057 RAIL (EXIST RAIL MODIFICATION) LF     139.000 24.89000 1
450 2064 RAIL (TY C221) LF     583.000 125.00000 1
450 2071 RAIL (TY C402) LF     133.000 57.11000 1
450 2076 RAIL (HANDRAIL) (TY E) LF     275.000 102.32000 1
450 2154 RAIL (TY T1W) LF     2,345.000 180.00000 1
450 2161 RAIL (TY T223) LF 280.000 85.00000 586.000 86.80546 3
450 2187 RAIL (T223) (MOD) LF     532.300 136.02762 2
450 2190 RAIL (SPECIAL TRAFFIC) (BRIDGE) LF     6,611.000 50.00000 1
450 2195 RAIL (TY T223) (SPL) LF     52.000 161.00000 1
450 2200 RAIL (TY C411) (HPC) LF     1,824.800 105.00000 1
450 2206 RAIL (TY T223) (HPC) LF 1,086.000 82.61510 2,244.000 84.47950 6
450 2612 RAIL (TY C221) (HPC) LF     818.000 105.00000 1
450 2641 RAIL (TY T131RC) LF     270.000 130.00000 1
452 2001 REMOV RAIL (CONC ELEMENTS) LF     8.000 10.00000 1
454 2001 SEALED EXPANSION JOINT (4 IN) (SEJ - A) LF 95.000 95.00000 485.700 86.09224 3
454 2005 ARMOR JOINT (WITH SEAL) LF 213.300 85.53868 1,563.300 86.63839 8
454 2006 HEADER TYPE EXPANSION JOINT LF 528.000 60.00000 2,540.000 88.11575 6
454 2007 HEADER TYPE EXPANSION JOINT CF     147.000 450.00000 1
454 2008 JOINT SEALANT LF     2,082.000 14.10183 3
454 2009 SEALED EXPANSION JOINT (5 IN) (SEJ - A) LF     500.000 125.00000 1
459 2001 GABIONS (PVC) CY     280.000 280.00000 1
459 2002 GABIONS (GALV) CY     107.500 210.00000 1
459 2007 GABION MATTRESSES (PVC) (12 IN) SY 1,255.000 80.00000 2,033.000 71.38957 2
459 2009 GABION MATTRESSES (GALV) (6 IN) SY     93.000 70.00000 1
459 2015 GABIONS (PVC) ( 3FT X 3 FT) CY     813.000 145.97786 2
460 2003 CMP (GAL STL 18 IN) LF     3,893.000 34.92987 4
460 2004 CMP (GAL STL 24 IN) LF     624.000 39.86699 3
460 2005 CMP (GAL STL 30 IN) LF     56.000 50.00000 1
460 2007 CMP (GAL STL 36 IN) LF     37.000 100.00000 1
460 2011 CMP (GAL STL 60 IN) LF     73.000 182.73973 2
460 2013 CMP (GAL STL 72 IN) LF     31.000 130.00000 1
460 2014 CMP AR (GAL STL DES 2) LF     66.100 52.50000 1
460 2016 CMP AR (GAL STL DES 4) LF     88.000 44.00000 1
460 2017 CMP AR (GAL STL DES 5) LF     116.000 50.00000 1
462 2001 CONC BOX CULV (3 FT X 2 FT) LF     8.000 420.00000 1
462 2003 CONC BOX CULV (4 FT X 2 FT) LF     737.000 148.63541 4
462 2004 CONC BOX CULV (4 FT X 3 FT) LF     1,605.000 200.07165 3
462 2006 CONC BOX CULV (5 FT X 2 FT) LF     27.500 900.00000 1
462 2008 CONC BOX CULV (5 FT X 4 FT) LF     26.000 280.00000 1
462 2010 CONC BOX CULV (6 FT X 3 FT) LF     248.000 433.96774 2
462 2011 CONC BOX CULV (6 FT X 4 FT) LF     275.000 432.85455 3
462 2012 CONC BOX CULV (6 FT X 5 FT) LF     102.000 400.00000 1
462 2013 CONC BOX CULV (6 FT X 6 FT) LF     497.000 410.37223 3
462 2014 CONC BOX CULV (7 FT X 3 FT) LF     3,910.000 256.15000 1
462 2017 CONC BOX CULV (7 FT X 6 FT) LF     266.000 400.22556 2
462 2019 CONC BOX CULV (8 FT X 4 FT) LF     161.600 522.58663 3
462 2021 CONC BOX CULV (8 FT X 6 FT) LF     354.000 344.57627 2
462 2023 CONC BOX CULV (8 FT X 8 FT) LF     2,238.000 405.75000 1
462 2034 CONC BOX CULV (10 FT X 10 FT) LF     104.000 660.00000 2
462 2092 CONC BOX CULV (10FT X 10FT) (FURNISHED) LF     136.000 400.00000 1
464 2001 RC PIPE (CL III) (12 IN) LF     77.000 90.00000 1
464 2002 RC PIPE (CL III) (15 IN) LF     9.000 75.00000 1
464 2003 RC PIPE (CL III) (18 IN) LF 268.000 55.89552 9,938.000 42.59799 15
464 2004 RC PIPE (CL III) (21 IN) LF     630.000 65.00000 1
464 2005 RC PIPE (CL III) (24 IN) LF     23,032.000 62.22195 16
464 2006 RC PIPE (CL III) (27 IN) LF     358.000 44.00000 1
464 2007 RC PIPE (CL III) (30 IN) LF     2,954.000 80.37156 9
464 2009 RC PIPE (CL III) (36 IN) LF     4,984.500 107.23478 11
464 2010 RC PIPE (CL III) (42 IN) LF     1,856.000 127.20932 7
464 2011 RC PIPE (CL III) (48 IN) LF     888.000 141.99088 6
464 2012 RC PIPE (CL III) (54 IN) LF     55.000 308.72727 2
464 2013 RC PIPE (CL III) (60 IN) LF     323.000 194.76161 3
464 2014 RC PIPE (CL III) (66 IN) LF     16.500 468.18182 2
464 2021 RC PIPE (CL IV) (18 IN) LF     503.000 50.00000 1
464 2022 RC PIPE (CL IV) (24 IN) LF     190.000 65.00000 1
465 2003 INLET (COMPL) (TY H) EA     5.000 2,868.00000 2
465 2005 MANH (COMPL) (TY M) EA     10.000 4,000.00000 1
465 2027 INLET (COMPL) (CURB) (TY II) (10') EA     1.000 6,680.00000 1