Monthly State Let Maintenance Report For Wichita Falls District As Of Jan 10, 2018 Page 1 Of 1

Last Update: Wednesday, January 10, 2018
FTP Icon
page 1

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyWICHITA
HighwayUS0082
FromVARIOUSE BRIDGES IN COOKE
ToWICHITA & YOUNG COUNTY
CSJ6304-34-001
Proj IDBPM - 630434001
Work TypeBRIDGE MAINTENANCE
 
0.001589293.70582650.6999.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began04-17-17
Work Completed
Time Computed00-00-00
Contract Working Days75
Addl Days Granted0
Working Days Charged109
Percent Time Used145
Contractor(s)
RESTEK, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6304-34-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01174201
Totals589293.700.00582650.6999.9

CountyCOOKE
HighwayIH0035
FromVARIOUS ROADWAYS IN
ToCOOKE AND MONTAGUE COUNTY
CSJ6308-65-001
Proj IDRMC - 630865001
Work TypeROUTINE STREET SWEEPING
 
0.001288904.00204612.0070.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began02-28-17
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged154
Percent Time Used42
Contractor(s)
WILSON CONTRACTING
SUBCONTRACTOR(S) FOR CCSJ: 6308-65-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10164202
Totals288904.000.00204612.0070.8

CountyMONTAGUE
HighwayUS0287
FromFM 174
ToWISE COUNTY LINE IN MONTAGUE CO
CSJ6315-46-001
Proj IDRMC - 631546001
Work TypeMETAL BEAM GUARD FENCE UPGRADE
 
0.001518214.00615915.9599.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began06-15-17
Work Completed
Time Computed00-00-00
Contract Working Days55
Addl Days Granted0
Working Days Charged77
Percent Time Used140
Contractor(s)
ODUM SERVICES, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6315-46-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04174005
Totals518214.0022216.00615915.9599.9

CountyWICHITA
HighwayIH0044
FromVARIOUS ROADWAYS
ToDISTRICT WIDE
CSJ6318-41-001
Proj IDRMC - 631841001
Work TypeDW ONCALL GRDRAIL/CABLE BARRIER REPAIR
 
0.0011038100.00328661.5031.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-17
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged122
Percent Time Used33
Contractor(s)
MARCOM'S MOWING SERVICE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6318-41-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06174011
Totals1038100.0079448.40328661.5031.6

CountyWICHITA
HighwayUS0287
FromVARIOUS LOCATIONS
ToDISTRICT WIDE
CSJ6318-68-001
Proj IDRMC - 631868001
Work TypeTRUCK MOUNTED ATTENUATORS (TMA)
 
0.001384890.0034535.148.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-17
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged122
Percent Time Used33
Contractor(s)
NIXON ENGINEERING
SUBCONTRACTOR(S) FOR CCSJ: 6318-68-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07174203
Totals384890.007277.9234535.148.9

CountyWICHITA
HighwayUS0082
FromVARIOUS LOCATIONS
ToDISTRICT WIDE
CSJ6318-84-001
Proj IDRMC - 631884001
Work TypeONCALL STRIPING & RPM
 
0.0011010918.00193201.2719.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-17
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged120
Percent Time Used32
Contractor(s)
BARRICADES UNLIMITED
SUBCONTRACTOR(S) FOR CCSJ: 6318-84-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07174002
Totals1010918.0075680.30193201.2719.3

CountyCLAY
HighwaySS0510
FromSP 510 UNDERPASS
ToUNDER RR
CSJ6318-92-001
Proj IDRMC - 631892001
Work TypeDRAINAGE IMPORVEMENT
 
0.001227990.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began01-02-18
Work Completed
Time Computed00-00-00
Contract Working Days52
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
STATELINE CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6318-92-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10174202
Totals227990.000.000.000.0

CountyWICHITA
HighwayFM0368
From.716 MI SOUTH OF FM 1206
To1.329 MI SOUTH OF FM 1206
CSJ6320-20-001
Proj IDRMC - 632020001
Work TypeEROSION/DRAINAGE REPAIR
 
0.001578952.300.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days45
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
STATELINE CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6320-20-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11174215
Totals578952.300.000.000.0

CountyCOOKE
HighwayFM1630
FromVARIOUS LOCATIONS IN COOKE CLAY
ToMONTAGUE WICHITA & WILBARGER COUNTY
CSJ6321-72-001
Proj IDRMC - 632172001
Work TypeCRACK SEAL - HOT POUR RUBBER
 
0.001252205.0029120.0011.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began12-11-17
Work Completed
Time Computed00-00-00
Contract Working Days44
Addl Days Granted0
Working Days Charged1
Percent Time Used2
Contractor(s)
SELECT STRIPING LLC
SUBCONTRACTOR(S) FOR CCSJ: 6321-72-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10174010
Totals252205.0029120.0029120.0011.5

CountyARCHER
HighwaySH0079
FromVARIOUS LOCATION IN ARCHER BAYLOR
ToCLAY THROCKMORTON & YOUNG COUNTY
CSJ6321-73-001
Proj IDRMC - 632173001
Work TypeCRACK SEAL - HOT POUR RUBBER
 
0.001226758.740.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began01-03-18
Work Completed
Time Computed00-00-00
Contract Working Days37
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
BRIGGS BROTHERS ENTERPRISES CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 6321-73-001
SETT CONSTRUCTION (54.00)
Contract #09174001
Totals226758.740.000.000.0

CountyWICHITA
HighwayUS0287
FromVARIOUS LOCATIONS IN WICHITA
ToWILBARGER, YOUNG & COOKE COUNTY
CSJ6322-09-001
Proj IDBPM - 632209001
Work TypeBRIDGE MAINTENANCE
 
0.001786175.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days100
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
L.C. JORDAN & SON
SUBCONTRACTOR(S) FOR CCSJ: 6322-09-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12174203
Totals786175.000.000.000.0

CountyARCHER
HighwayUS0082
FromVARIOUS ROADWAYS
ToDISTRICT WIDE
CSJ6324-00-001
Proj IDRMC - 632400001
Work TypeROUTINE STREET SWEEPING
 
0.001590931.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
WILSON CONTRACTING
SUBCONTRACTOR(S) FOR CCSJ: 6324-00-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11174014
Totals590931.000.000.000.0

CountyWICHITA
HighwayUS0082
FromVARIOUS LOCATIONS IN COOKE CLAY
ToMONTAGUE WICHITA & WILBARGER COUNTY
CSJ6325-72-001
Proj IDRMC - 632572001
Work TypeDEBRIS REMOMVAL
 
0.001517830.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days275
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
WILSON CONTRACTING
SUBCONTRACTOR(S) FOR CCSJ: 6325-72-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01184001
Totals517830.000.000.000.0

page 1