Monthly Local Let Maintenance Report For Wichita Falls District As Of Feb 09, 2018 Page 3 Of 3

Last Update: Friday, February 09, 2018
FTP Icon
page 1 | page 2 | page 3

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyCLAY
HighwayUS0082
FromVARIOUS LOCATIONS
ToIN CLAY COUNTY
CSJ6321-83-001
Proj IDRMC - 632183001
Work TypeTREE TRIMMING & TREE/BRUSH REMOVAL
 
0.001236050.00116400.0049.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began01-02-18
Work Completed
Time Computed00-00-00
Contract Working Days40
Addl Days Granted0
Working Days Charged17
Percent Time Used42
Contractor(s)
BRYDL CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6321-83-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10170301
Totals236050.00116400.00116400.0049.3

CountyWICHITA
HighwayIH0044
FromVARIOUS ROADWAYS IN WICHITA, CLAY
ToMONTAGUE & WILBARGER
CSJ6323-88-001
Proj IDRMC - 632388001
Work TypeDELINEATOR INSTALLATION
 
0.001179433.00156803.9087.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began12-18-17
Work Completed
Time Computed00-00-00
Contract Working Days65
Addl Days Granted0
Working Days Charged22
Percent Time Used33
Contractor(s)
JASCO
SUBCONTRACTOR(S) FOR CCSJ: 6323-88-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10170302
Totals179433.0063966.76156803.9087.3

CountyARCHER
HighwayUS0082
FromVARIOUS ROADWAYS IN
ToARCHER & CLAY COUNTY
CSJ6326-21-001
Proj IDRMC - 632621001
Work TypeRIGHT OF WAY MOWING
 
0.001177844.940.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days73
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
BIG STATE MAINTENANCE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6326-21-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01180301
Totals177844.940.000.000.0

CountyMONTAGUE
HighwayUS0287
FromVARIOUS ROADWAYS IN
ToMONTAGUE & CLAY COUNTY
CSJ6326-22-001
Proj IDRMC - 632622001
Work TypeRIGHT OF WAY MOWING
 
0.001139662.820.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days64
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ARNOLDO CHAVEZ WELDING
SUBCONTRACTOR(S) FOR CCSJ: 6326-22-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01180302
Totals139662.820.000.000.0

CountyWICHITA
HighwayUS0287
FromVARIOUS ROADWAYS IN
ToWICHITA & WILBARGER COUNTY
CSJ6326-23-001
Proj IDRMC - 632623001
Work TypeRIGHT OF WAY MOWING
 
0.001153480.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days56
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
BIG STATE MAINTENANCE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6326-23-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01180303
Totals153480.000.000.000.0

CountyYOUNG
HighwaySH0016
FromVARIOUS ROADWAYS IN
ToYOUNG & THROCKMORTON COUNTY
CSJ6326-24-001
Proj IDRMC - 632624001
Work TypeRIGHT OF WAY MOWING
 
0.001319770.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days104
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
FOUR R OILFIELD SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6326-24-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01180304
Totals319770.000.000.000.0

CountyCLAY
HighwaySH0079
FromVARIOUS ROADWAYS IN
ToCLAY COUNTY
CSJ6326-26-001
Proj IDRMC - 632626001
Work TypeRIGHT OF WAY MOWING
 
0.001201166.100.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days67
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
BIG STATE MAINTENANCE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6326-26-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01180306
Totals201166.100.000.000.0

CountyMONTAGUE
HighwayUS0082
FromVARIOUS ROADWAYS IN
ToMONTAGUE & COOKE COUNTY
CSJ6326-27-001
Proj IDRMC - 632627001
Work TypeRIGHT OF WAY MOWING
 
0.001154681.340.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days71
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ARNOLDO CHAVEZ WELDING
SUBCONTRACTOR(S) FOR CCSJ: 6326-27-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01180307
Totals154681.340.000.000.0

CountyWICHITA
HighwayFM0369
FromVARIOUS ROADWAYS IN
ToWICHITA COUNTY
CSJ6326-30-001
Proj IDRMC - 632630001
Work TypeRIGHT OF WAY MOWING
 
0.001186837.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days46
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
BIG STATE MAINTENANCE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6326-30-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01180310
Totals186837.000.000.000.0

page 1 | page 2 | page 3