Monthly State Let Maintenance Report For Waco District As Of Feb 09, 2018 Page 3 Of 3

Last Update: Friday, February 09, 2018
FTP Icon
page 1 | page 2 | page 3

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyBOSQUE
HighwaySH0006
FromVAR RDWYS IN BOSQUE, BELL, CORYELL,HILL,
ToHAMILTON, FALLS, LIMESTONE & MCLENNAN
CSJ6318-15-001
Proj IDRMC - 631815001
Work TypeFLAGGING AND TRAFFIC CONTROL
 
0.0102234850.00298755.0013.3
Work Order09-14-17
Work Began10-02-17
Work Completed
Time Computed10-02-17
Contract Working Days365
Addl Days Granted0
Working Days Charged117
Percent Time Used32
Contractor(s)
NIXON ENGINEERING
SUBCONTRACTOR(S) FOR CCSJ: 6318-15-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07174212
Totals2234850.0057280.00298755.0013.3

CountyHILL
HighwaySH0022
FromVARIOUS LOCATIONS IN BOSQUE,CORYELL,
ToFALLS,HAMILTON,HILL & MCLENNAN COUNTIES
CSJ6319-12-001
Proj IDRMC - 631912001
Work TypeCRACK SEAL - HOT APPLICATION
 
0.010422070.87110663.5026.2
Work Order12-11-17
Work Began12-11-17
Work Completed
Time Computed12-11-17
Contract Working Days100
Addl Days Granted0
Working Days Charged16
Percent Time Used16
Contractor(s)
CHAMPION INFRASTRUCTURE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6319-12-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08174214
Totals422070.870.00110663.5026.2

CountyMCLENNAN
HighwayFM3529
FromVARIOUS ROADWAYS IN CORYELL, FALLS,
ToHAMILTON, LIMESTONE & MCLENNAN COUNTIES
CSJ6320-83-001
Proj IDRMC - 632083001
Work TypeSEAL COAT
 
0.010993657.540.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days25
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
F. N. PLOCH CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6320-83-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10174015
Totals993657.540.000.000.0

CountyBELL
HighwayUS0190
FromVARIOUS LOCATIONS
ToDISTRICT WIDE
CSJ6320-89-001
Proj IDRMC - 632089001
Work TypeLARGE SIGN MAINTENANCE
 
0.010336750.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
IIPL USA LLC
SUBCONTRACTOR(S) FOR CCSJ: 6320-89-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10174012
Totals336750.000.000.000.0

CountyCORYELL
HighwayUS0084
FromBELL, CORYELL, HILL AND
ToLIMESTONE COUNTIES
CSJ6323-05-001
Proj IDBPM - 632305001
Work TypeBRIDGE PREVENTATIVE MAINTENANCE
 
0.010318825.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days82
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
BECK-REIT & SONS, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6323-05-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11174015
Totals318825.000.000.000.0

CountyMCLENNAN
HighwayUS0084
FromVAR ROADWAYS IN BELL, CORYELL, FALLS,
ToHAMILTON, HILL, LIMESTONE & MCLENNAN CO
CSJ6324-94-001
Proj IDRMC - 632494001
Work TypeMISCELLANEOUS CONCRETE REPAIRS
 
0.010648174.380.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days67
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
DBI SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6324-94-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02184005
Totals648174.380.000.000.0

page 1 | page 2 | page 3