Monthly State Let Construction Report For Waco District As Of Jan 10, 2018 Page 2 Of 3

Last Update: Wednesday, January 10, 2018
FTP Icon
page 1 | page 2 | page 3

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyMCLENNAN
HighwaySH 6
FromBUFFALO COUNTRY RD IN VALLEY MILLS
ToLADY BIRD RD
CSJ0258-08-032
Proj IDSTP 2013(587)
Work TypeREHAB RDWY, ADD PASS LNS
 
9.6694687935.114842688.1799.9
Work Order08-17-16
Work Began09-26-16
Work Completed
Time Computed09-16-16
Contract Working Days234
Addl Days Granted0
Working Days Charged170
Percent Time Used72
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0258-08-032
COWBELL TRAFFIC SERVICES, INC. (0.29)
D.I.J. CONSTRUCTION, INC (1.90)
FORTSON CONTRACTING, INC. (1.96)
N-LINE TRAFFIC MAINTENANCE, L.P. (1.11)
ROADSAFE TRAFFIC SYSTEMS, INC. (0.21)
TEXAS ALTERNATIVE GRASSER, INC. (0.44)
W.S. CONSTRUCTION COMPANY (12.96)
Contract #06163015
Totals4687935.110.004842688.1799.9

CountyMCLENNAN
HighwaySH 6
FromSP 412
To0.5 MI N OF SP 412
CSJ0258-08-034
Proj IDNH 2016(830)
Work TypeMILL/SEAL/INLAY
 
0.549288197.40292206.6099.9
CountyMCLENNAN
HighwaySH 6
FromFM 3476
ToSP 412
CSJ0258-09-139
Proj IDNH 2016(830)
Work TypeMILL/SEAL/INLAY
 
9.2265380793.715234481.7697.2
CountyMCLENNAN
HighwaySH 6
From@ LAKE WACO (NB MAINLANE)
To(STR #067)
CSJ0258-09-140
Proj IDBR 1602(037)
Work TypeREHAB BR & APPRS
 
0.7434331178.403220454.0174.3
CountyMCLENNAN
HighwaySH 6
From@ LAKE WACO (SB MAINLANE)
To(STR #068)
CSJ0258-09-141
Proj IDBR 1602(037)
Work TypeREHAB BR & APPRS
 
0.7434481138.904500617.9599.9
Work Order05-12-16
Work Began10-03-16
Work Completed
Time Computed07-11-16
Contract Working Days255
Addl Days Granted7
Working Days Charged244
Percent Time Used93
Contractor(s)
J.D. ABRAMS, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0258-08-034
N-LINE TRAFFIC MAINTENANCE, L.P. (0.37)
APAC-TEXAS, INC. (22.26)
ROADWAY SPECIALTIES, INC. (0.06)
GK CONSTRUCTION, LLC (1.01)
A. H. BECK FOUNDATION CO., INC. (20.45)
ODUM SERVICES, L.P. (0.08)
FLASHER EQUIPMENT COMPANY (2.19)
A BROTHERS MILLING, LLC (0.97)
WEST TEXAS RUMBLE STRIP (0.10)
CHEROKEE SERVICES (1.91)
C-HOP CONSTRUCTION (0.60)
POTTER TRUCKING (0.89)
ADCOCK 4 INVESTMENTS, LLC, DBA BRADCO (0.17)
PIONEER UTILITIES, INC. (0.13)
Contract #03163002
Totals14481308.41169608.5613247760.3291.4

CountyMCLENNAN
HighwaySH 6
FromIH 35
ToUS 77
CSJ0258-09-111
Proj IDC 258-9-111
Work TypeCONSTR OP/RAMPS; EXTEND FRTG RDS
 
1.94922387388.2617457172.3177.9
Work Order02-10-16
Work Began03-07-16
Work Completed
Time Computed03-07-16
Contract Working Days701
Addl Days Granted0
Working Days Charged433
Percent Time Used61
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0258-09-111
ANALYTICAL TECHNOLOGY CONSULTANTS, INC. (3.62)
FLASHER EQUIPMENT COMPANY (0.55)
BRICK PAVING PLUS, INC. (0.56)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (0.65)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.37)
JUST GROOVING, LTD. (0.04)
ROADWAY SPECIALTIES, INC. (0.49)
FORTSON CONTRACTING, INC. (0.38)
WEST TEXAS RUMBLE STRIP (0.02)
ABC EROSION CONTROL, INC. (0.36)
MESA ROD BUSTERS, INC. (0.08)
Contract #12153203
Totals22387388.26481425.0617457172.3177.9

CountyMCLENNAN
HighwaySH 6
FromBRAZOS RIVER
ToSP 484 / SH 6
CSJ0258-09-124
Proj IDNH 1602(305)
Work TypeWDN TO 4 LN FRWY
 
1.36514733502.659312549.2963.2
Work Order10-11-16
Work Began11-14-16
Work Completed
Time Computed11-10-16
Contract Working Days617
Addl Days Granted0
Working Days Charged270
Percent Time Used43
Contractor(s)
J.D. ABRAMS, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0258-09-124
N-LINE TRAFFIC MAINTENANCE, L.P. (0.14)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.40)
ADCOCK 4 INVESTMENTS, LLC (2.65)
ROADWAY SPECIALTIES, INC. (0.75)
GK CONSTRUCTION, LLC (0.62)
ATS DRILLING, L.P. (4.59)
THE LEVY COMPANY, L.P. (0.67)
D.I.J. CONSTRUCTION, INC (0.30)
TEXOP CONSTRUCTION (0.15)
S & S BRIDGE PAINTING, INC. (0.06)
HOUSTON SAWING & DRILLING (0.04)
C-HOP CONSTRUCTION (9.05)
OLDCASTLE MATERIALS TEXAS, INC. (12.44)
BOWMAN ENGINEERING & CONSULTING, INC (0.09)
Contract #07163205
Totals14733502.65354671.459312549.2963.2

CountyBELL
HighwaySH 95
From0.5 MI S OF FM 436
ToHOLLAND CITY LIMITS
CSJ0320-02-036
Proj IDSTP 2017(900)
Work TypeWDN, GR, SURF, ADD PASS LNS
 
6.9416123477.870.000.0
Work Order11-15-17
Work Began01-08-18
Work Completed
Time Computed12-15-17
Contract Working Days277
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0320-02-036
CHEROKEE SERVICES (0.36)
D. I. J. CONSTRUCTION, INC. (1.72)
FLASHER EQUIPMENT COMPANY (0.32)
MURRAY CONSTRUCTION (0.45)
ROADWAY SPECIALTIES, INC. (1.96)
SAN-ANN-CO., INC. (0.12)
TEXAS ALTERNATIVE GRASSER, INC. (0.22)
LONE STAR HIGHWAY PRODUCTS, INC. (0.54)
Contract #10173014
Totals6123477.870.000.000.0

CountyFALLS
HighwaySH 7
FromUS 77
ToWEST MARLIN C/L
CSJ0382-01-044
Proj IDSTP 2018(410)
Work TypeSEAL/OVLY
 
10.4622882946.870.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days94
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0382-01-044
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01183209
Totals2882946.870.000.000.0

CountyMCLENNAN
HighwaySH 317
FromMOODY CITY LIMITS
ToBELL CO LINE
CSJ0398-03-058
Proj IDSTP 2016(834)
Work TypeWDN, GR, SURF, ADD SHLDRS
 
9.2799139073.586278911.1868.7
Work Order10-19-16
Work Began12-13-16
Work Completed
Time Computed11-18-16
Contract Working Days361
Addl Days Granted0
Working Days Charged264
Percent Time Used73
Contractor(s)
OLDCASTLE MATERIALS TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0398-03-058
SAN-ANN-CO., INC. (1.00)
BMP SPECIALIST, LLC (0.81)
W.S. CONSTRUCTION COMPANY (16.31)
TEXOP CONSTRUCTION (0.08)
CHEROKEE SERVICES (0.19)
D.I.J. CONSTRUCTION, INC (1.00)
TEXAS ALTERNATIVE GRASSER, INC. (0.44)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (0.18)
WEST TEXAS RUMBLE STRIP (0.05)
FORTSON CONTRACTING, INC. (1.02)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.05)
Contract #08163036
Totals9139073.58580110.266278911.1868.7

CountyBELL
HighwaySH 317
From0.2 MI S OF FM 2305
To0.4 MI N OF FM 439
CSJ0398-04-059
Proj IDC 398-4-59
Work TypeWDN, GR, STRS & SURF
 
2.14916887376.6211365943.9367.3
Work Order07-13-16
Work Began08-19-16
Work Completed
Time Computed08-12-16
Contract Working Days532
Addl Days Granted0
Working Days Charged342
Percent Time Used64
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0398-04-059
BRICK PAVING PLUS, INC. (0.70)
CHEROKEE SERVICES (0.31)
ENCINO LANDSCAPE, INC. (0.87)
FLASHER EQUIPMENT COMPANY (0.22)
FORTSON CONTRACTING, INC. (0.18)
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC. (1.43)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.04)
LONE STAR HIGHWAY PRODUCTS, INC. (0.79)
R K STEPHENS CONSTRUCTION, LLC (3.94)
ROADWAY SPECIALTIES, INC. (1.53)
SAN-ANN-CO., INC. (0.24)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.52)
W. W. FOUNDATION DRILLING, LTD. (1.09)
MCL CONTRACTING, LLC (0.06)
GK CONSTRUCTION, LLC (0.02)
NIXON ENGINEERING (0.00)
Contract #05163006
Totals16887376.62365086.4211365943.9367.3

CountyCORYELL
HighwayFM 116
FromUS 84
ToCACTUS LANE
CSJ0724-01-044
Proj IDSTP 1502(343)
Work TypeADD PASS LNS/SHLDRS
 
18.89117587091.4717020321.5096.7
Work Order08-20-15
Work Began11-11-15
Work Completed
Time Computed12-19-15
Contract Working Days510
Addl Days Granted4
Working Days Charged505
Percent Time Used98
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0724-01-044
ABC EROSION CONTROL, INC. (2.03)
SAN-ANN-CO., INC. (0.30)
W. W. FOUNDATION DRILLING, LTD. (0.67)
GK CONSTRUCTION, LLC (0.11)
PRIMATE CONSTRUCTION, INC. (0.13)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (0.26)
COWBELL TRAFFIC SERVICES, INC. (0.13)
DS TEXAS ICON CONSTRUCTION (0.61)
ROADWAY SPECIALTIES, INC. (0.85)
JOY LATTIMER, LLC. (4.01)
D. I. J. CONSTRUCTION, INC. (1.47)
FORTSON CONTRACTING, INC. (1.05)
MCL CONTRACTING, LLC (0.00)
NIXON ENGINEERING (0.00)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.01)
Contract #06153203
Totals17587091.47141.0817020321.5096.7

CountyCORYELL
HighwayFM 116
FromANDERSON AVE
ToAVENUE B
CSJ0724-01-049
Proj IDSTP 2013(586)
Work TypeWDN, GR & STR
 
0.7044531202.354652773.7899.9
CountyCORYELL
HighwayFM 116
FromANDERSON AVE
ToAVENUE B
CSJ0724-01-052
Proj IDROW 724-1-52
Work TypeROW ACQUISITION
 
0.7041012118.22454230.0544.8
Work Order11-13-15
Work Began02-11-16
Work Completed
Time Computed02-11-16
Contract Working Days340
Addl Days Granted0
Working Days Charged311
Percent Time Used91
Contractor(s)
OLDCASTLE MATERIALS TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0724-01-049
SAN-ANN-CO., INC. (0.78)
ROADWAY SPECIALTIES, INC. (1.24)
TEX OP CONSTRUCTION, LP (0.25)
R K STEPHENS CONSTRUCTION, LLC (7.97)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (0.36)
TRP CONSTRUCTION GROUP, LLC (0.97)
MCLEAN CONSTRUCTION, INC. (39.03)
Contract #09153013
Totals5543320.5724249.505107003.8392.1

CountyCORYELL
HighwayFM 116
FromCACTUS LANE
ToHOUSE CREEK BRIDGE
CSJ0724-01-050
Proj IDSTP 2017(011)
Work TypeADD LFT TRN LN
 
3.4924345840.872045953.7347.0
Work Order04-19-17
Work Began06-05-17
Work Completed
Time Computed05-19-17
Contract Working Days234
Addl Days Granted0
Working Days Charged145
Percent Time Used61
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0724-01-050
AWP, INC. (0.23)
COMEN ENTERPRISE LLC (3.11)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (2.54)
D.I.J. CONSTRUCTION, INC (1.01)
WOLFE CONSTRUCTION GROUP, INC. (0.54)
NIXON ENGINEERING (0.00)
Contract #03173029
Totals4345840.87180442.002045953.7347.0

CountyFALLS
HighwayFM 935
FromDURANGO
ToUS 77
CSJ0752-04-024
Proj IDSTP 1702(621)
Work TypeWDN, GR, BS, SURF, ADD SHLDRS
 
5.6563524688.871162878.9432.9
Work Order09-18-17
Work Began10-16-17
Work Completed
Time Computed10-18-17
Contract Working Days277
Addl Days Granted0
Working Days Charged51
Percent Time Used18
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0752-04-024
FLASHER EQUIPMENT COMPANY (0.51)
MURRAY CONSTRUCTION (0.80)
ROADWAY SPECIALTIES, INC. (3.98)
TEXAS ALTERNATIVE GRASSER, INC. (1.30)
TOTAL HIGHWAY MAINTENANCE, LLC (1.22)
AWP, INC. DBA AREA WIDE PROTECTIVE (0.29)
Contract #08173224
Totals3524688.87259766.431162878.9432.9

CountyLIMESTONE
HighwayFM 147
FromSH 14
ToFALLS CO LINE
CSJ0752-06-022
Proj IDSTP 2016(103)
Work TypeWDN, GR, BS, SURF, ADD SHLDRS
 
10.0554469649.324415047.6399.4
Work Order11-16-15
Work Began02-29-16
Work Completed
Time Computed02-15-16
Contract Working Days234
Addl Days Granted44
Working Days Charged310
Percent Time Used111
Contractor(s)
OLDCASTLE MATERIALS TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0752-06-022
BEAR CREEK CONSTRUCTION, LLC (15.29)
D.I.J. CONSTRUCTION, INC (1.51)
FORTSON CONTRACTING, INC. (0.81)
ROADWAY SPECIALTIES, INC. (4.43)
SAN-ANN-CO., INC. (1.81)
TEXAS ALTERNATIVE GRASSER, INC. (1.15)
WEST TEXAS RUMBLE STRIP (0.10)
BRETT CONSTRUCTION COMPANY (0.37)
Contract #09153221
Totals4469649.320.004415047.6399.4

CountyFALLS
HighwayFM 413
From@ BRAZOS RIVER
To(STR #008)
CSJ0808-01-058
Proj IDBR 2017(897)
Work TypeCONC OVLY DECK REHAB
 
0.2393535361.500.000.0
Work Order08-23-17
Work Began00-00-00
Work Completed
Time Computed09-22-17
Contract Working Days107
Addl Days Granted0
Working Days Charged58
Percent Time Used54
Contractor(s)
FNH CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0808-01-058
S&S BRIDGE PAINTING (28.51)
Contract #07173023
Totals3535361.500.000.000.0

CountyMCLENNAN
HighwayFM 1637
FromFM 3051
To0.65 MI W OF FM 2490
CSJ0833-03-035
Proj IDHP 1502(059)
Work TypeWDN GR, STRS & SURF
 
4.33727836847.9919280955.9169.2
Work Order06-30-15
Work Began04-04-16
Work Completed
Time Computed12-28-15
Contract Working Days574
Addl Days Granted0
Working Days Charged404
Percent Time Used70
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0833-03-035
RAMBO CONTRACTING, INC. (2.78)
APEX LANDSCAPE & IRRIGATION, LLC (0.00)
BRICK PAVING PLUS, INC. (2.72)
DUSTROL, INC. (0.52)
ROADWAY SPECIALTIES, INC. (1.35)
FLASHER EQUIPMENT COMPANY (0.56)
SAN-ANN-CO., INC. (0.27)
ANALYTICAL TECHNOLOGY CONSULTANTS, INC. (2.19)
LONE STAR HIGHWAY PRODUCTS, INC. (4.07)
POTTER TRUCKING (0.49)
B-CORP UTILITIES, INC. (0.17)
BEAR CREEK CONSTRUCTION, LLC (2.34)
I & H CONCRETE CUTTING, INC. (0.09)
AARON CONCRETE CONTRACTORS, L.P. (1.07)
BOEN LANDSCAPING & IRRIGATION, LLC (0.59)
JNB CONSTRUCTION, LLC (0.20)
Contract #04153257
Totals27836847.99792703.4919280955.9169.2

CountyBOSQUE
HighwayCR
FromON CR 333 @ N BOSQUE RIVER
To(MAP #13)
CSJ0909-28-022
Proj IDBR 2000(962)
Work TypeREPL BR & APPRS
 
0.1661451177.001083839.0074.6
Work Order05-16-17
Work Began06-28-17
Work Completed
Time Computed06-15-17
Contract Working Days170
Addl Days Granted0
Working Days Charged122
Percent Time Used71
Contractor(s)
HODGES AND SON CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0909-28-022
PENHALL COMPANY (0.22)
ROADWAY SPECIALTIES, INC. (3.91)
SAN-ANN-CO., INC. (0.45)
TEX OP CONSTRUCTION, LP (0.45)
TOTAL HIGHWAY MAINTENANCE, LLC (0.43)
WOLFE CONSTRUCTION GROUP, INC. (0.22)
MCL CONTRACTING, LLC (0.86)
Contract #04173205
Totals1451177.00186646.521083839.0074.6

CountyBELL
HighwayCR
FromON CR 493 @ SALADO
ToCREEK (MAP#60)
CSJ0909-36-137
Proj IDBR 2012(427)
Work TypeREPL BR & APPRS
 
0.1761202660.75247792.5615.4
Work Order01-29-16
Work Began00-00-00
Work Completed
Time Computed04-28-16
Contract Working Days149
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0909-36-137
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10153004
Totals1202660.750.00247792.5615.4

CountyFALLS
HighwayCR
FromCR 299 @ BRAZOS RV TRIB
To(MAP #2043)
CSJ0909-38-076
Proj IDBR 1602(241)
Work TypeREPL BR & APPRS
 
0.081417696.830.000.0
CountyFALLS
HighwayCR
FromCR 287 @ SANDY CREEK
To(MAP #39)
CSJ0909-38-077
Proj IDBR 1602(242)
Work TypeREPL BR & APPRS
 
0.127721889.300.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days255
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0909-38-076
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01183017
Totals1139586.130.000.000.0

CountyCORYELL
HighwayVA
FromAT VARIOUS LOCATIONS
ToIN CORYELL COUNTY
CSJ0909-39-128
Proj IDSTP 2016(368)
Work TypeCONSTRUCT CURB RAMPS
 
0.100663079.06664481.3699.9
Work Order02-22-17
Work Began05-03-17
Work Completed
Time Computed03-24-17
Contract Working Days107
Addl Days Granted0
Working Days Charged104
Percent Time Used97
Contractor(s)
PROJECT ALLIED RESOURCES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0909-39-128
AWP, INC. (1.37)
Contract #01173014
Totals663079.062986.95664481.3699.9

CountyLIMESTONE
HighwayCR
FromCR 212 @ TEHUACANA CRK
To(MAP #35)
CSJ0909-40-059
Proj IDBR 2014(333)
Work TypeREPL BR & APPRS
 
0.099438543.55368019.8697.0
CountyLIMESTONE
HighwayCR
FromCR 330 @ LAKE LIMESTONE
To(MAP #133)
CSJ0909-40-071
Proj IDBR 2015(446)
Work TypeREPL BR & APPRS
 
0.066302747.00269660.8089.0
CountyLIMESTONE
HighwayCR
FromON CR 181 @ PIN OAK CR RELIEF
To(MAP #22)
CSJ0909-40-072
Proj IDBR 2015(447)
Work TypeREPL BR & APPRS
 
0.074399986.0097130.0024.2
CountyLIMESTONE
HighwayCR
FromCR 416 @ SOWDERS CRK TRIB
To(MAP #209) (LCR 707)
CSJ0909-40-073
Proj IDBR 2015(448)
Work TypeREPL BR & APPRS
 
0.068418722.45393122.9593.8
Work Order12-28-16
Work Began02-13-17
Work Completed
Time Computed01-27-17
Contract Working Days277
Addl Days Granted0
Working Days Charged222
Percent Time Used80
Contractor(s)
PIERCE R & B LLC
SUBCONTRACTOR(S) FOR CCSJ: 0909-40-059
FORTSON CONTRACTING, INC. (2.63)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (10.24)
WOLFE CONSTRUCTION GROUP, INC. (1.50)
SAN-ANN-CO., INC. (1.05)
OLDCASTLE MATERIALS TEXAS, INC. (3.74)
KEECHI CREEK OILFIELD SERVICES, LLC (0.16)
Contract #10163009
Totals1559999.00104807.791127933.6175.9