Monthly State Let Construction Report For Tyler District As Of Jan 10, 2018 Page 1 Of 3

Last Update: Wednesday, January 10, 2018
FTP Icon
page 1 | page 2 | page 3

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyVAN ZANDT ETC
HighwayUS 80 ETC
FromGR SALINE WCL, 1.5 MI W OF SH110, E
ToFM 857
CSJ0095-07-059
Proj IDSTP 2018(257)
Work TypeSEAL COAT AND PAVEMENT MARKINGS
 
143.10910067448.290.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days91
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
MISSOURI PETROLEUM PRODUCTS COMPANY LLC
SUBCONTRACTOR(S) FOR CCSJ: 0095-07-059
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12173205
Totals10067448.290.000.000.0

CountyWOOD ETC
HighwayUS 80 ETC
FromAT FM 2659/CR 3780
To.
CSJ0096-02-049
Proj IDSTP 2018(196)HES
Work TypeINSTALL SAFETY LIGHTING
 
1.200160005.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-10-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days49
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TEXAS TRAFFIC CONTROL SYSTEMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0096-02-049
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10173203
Totals160005.000.000.000.0

CountyGREGG
HighwayUS 80
FromSL 485, E 1.15 MI
ToLOCKERPLANT RD IN GLADEWATER
CSJ0096-04-066
Proj IDNH 2017(893)
Work TypeGR,BS,HMAC SURF,STRM SWR,C&G,SIGNS
 
0.8373538933.211038348.7429.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-16-17
Work Began06-20-17
Work Completed
Time Computed00-00-00
Contract Working Days190
Addl Days Granted0
Working Days Charged119
Percent Time Used62
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0096-04-066
ISAACS CONSTRUCTION SERVICES, LLC. (1.24)
MORRIS COUNTY CONTRACTORS, L.L.C. (0.93)
PANOLA SIGN & BARRICADE, INC. (0.39)
MAC TRANSPORTATION, LTD, L.L.P. (1.97)
STRIPING TECHNOLOGY, L.P. (0.76)
TEXOP CONSTRUCTION (1.84)
SOUTHWEST ENVIRONMENT SERIVES, LLC (2.04)
Contract #04173030
Totals3538933.2198892.511038348.7429.3

CountyHENDERSON
HighwaySH 19
FromFM 1615, SOUTH 3.8 MI
To0.3 MI S OF COON CREEK BRIDGE
CSJ0108-04-037
Proj IDSTP 1702(091)
Work TypeGR,STRS,ACP SURF,FLEX BS,CAM,OCST
 
3.8364949012.53843280.0717.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-14-17
Work Began08-08-17
Work Completed
Time Computed00-00-00
Contract Working Days295
Addl Days Granted0
Working Days Charged84
Percent Time Used28
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0108-04-037
COLD CREEK CONSTRUCTION, LTD (1.34)
J & M CONTRACTING, COMPANY (13.03)
TOTAL HIGHWAY MAINTENANCE, LLC (0.74)
SAN-ANN-CO., INC. (0.51)
FORTSON CONTRACTING, INC. (0.15)
AREA WIDE PROTECTIVE, INC. (0.29)
NIXON ENGINEERING, L.L.C. (0.09)
WACO DRILLING CO., INC. (0.02)
Contract #05173028
Totals4949012.53173805.66843280.0717.0

CountyANDERSON
HighwaySH 19
From3.6 MI N OF FM 837(HENDERSON C/L),S
To0.4 MI N OF FM 321 AT MONTALBA
CSJ0108-06-051
Proj IDSTP 2013(637)
Work TypeGR,STRS,HMA BS & SURF,OCST,LVL-UP
 
11.81312487715.8712068754.5296.6
Work Order07-10-14
Work Began09-02-14
Work Completed
Time Computed07-26-14
Contract Working Days453
Addl Days Granted140
Working Days Charged467
Percent Time Used78
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0108-06-051
COLD CREEK CONSTRUCTION, LTD (0.82)
FORTSON CONTRACTING, INC. (0.45)
HIGHWAY 19 CONSTRUCTION, LLC (10.97)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.35)
SOUTHWEST ENVIRONMENT SERVICES LLC (1.15)
STRIPING TECHNOLOGY, L.P. (1.23)
FARR FOUNDATION, INC. (0.64)
SAN-ANN-CO., INC. (0.04)
MURRAY CONSTRUCTION (0.49)
Contract #05143205
Totals12487715.87617244.8412068754.5296.6

CountyANDERSON ETC
HighwayUS 287 ETC
FromFREESTONE C/L SE
To1.7 MI SE OF FM 488 (FREESTONE CL),
CSJ0122-04-038
Proj IDSTP 2017(355)
Work TypeSEAL COAT & PAVEMENT MARKINGS
 
216.06311487064.257953288.1669.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-13-17
Work Began08-08-17
Work Completed
Time Computed00-00-00
Contract Working Days110
Addl Days Granted0
Working Days Charged112
Percent Time Used101
Contractor(s)
MISSOURI PETROLEUM PRODUCTS COMPANY LLC
SUBCONTRACTOR(S) FOR CCSJ: 0122-04-038
STRIPING TECHNOLOGY, L.P. (12.38)
BRYDL CONTRACTING, INC. (1.55)
Contract #01173005
Totals11487064.256917.857953288.1669.2

CountySMITH
HighwayUS 271
From0.4 MI S OF SS 147 (OAKWOOD ST.)
ToSH 31 (FRONT ST) IN TYLER
CSJ0165-01-102
Proj IDSTP 1702(092)
Work TypePLNG,BS RPR,SEAL,HMAC SURF,PVT MKG
 
1.6322038396.382095989.9199.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-08-17
Work Began07-26-17
Work Completed
Time Computed00-00-00
Contract Working Days45
Addl Days Granted0
Working Days Charged78
Percent Time Used173
Contractor(s)
CLARK CONSTRUCTION OF TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0165-01-102
INTERSTATE BARRICADES & MARKINGS, INC. (3.96)
Contract #05173208
Totals2038396.38711493.442095989.9199.9

CountyHENDERSON
HighwayUS 175
From0.1 MI SE OF FM 804, SE
ToCR 4712 (END OF C-S)
CSJ0198-01-023
Proj IDNH 1402(195)
Work TypeRECONSTR GR, STRS, BS, SURF & PAV M
 
6.69539261003.8935761102.0491.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-21-14
Work Began04-06-15
Work Completed
Time Computed00-00-00
Contract Working Days605
Addl Days Granted25
Working Days Charged502
Percent Time Used79
Contractor(s)
A. L. HELMCAMP, INC.
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0198-01-023
DUSTIN ALLEN, INC. (0.36)
MURRAY CONSTRUCTION (0.22)
STRIPING TECHNOLOGY, L.P. (0.31)
SAN-ANN-CO., INC. (0.21)
KLP COMMERCIAL, LLC (4.91)
KENSAR LLC DBA S & S TRUCKING (1.88)
BIG CREEK CONSTRUCTION, LTD. (0.00)
ENVIRODREDGE (0.20)
TEXAS ORGANIC ENTERPRISES, LTD (0.07)
A. L. CONSTRUCTION, LLC (0.03)
NIXON ENGINEERING, L.L.C. (0.00)
Contract #08143055
Totals39261003.89321200.2935761102.0491.0

CountyHENDERSON
HighwayUS 175
From1.1 MI E OF LP 60E @ LARUE, SE
To0.85 MI E OF FM 315, IN POYNOR
CSJ0198-02-027
Proj IDNH 2015(423)
Work TypeRECONSTR GR, STRS, BS, SURF & PAV M
 
4.73137849155.3138202720.5499.9
Work Order06-30-15
Work Began10-06-15
Work Completed
Time Computed07-16-15
Contract Working Days654
Addl Days Granted4
Working Days Charged476
Percent Time Used72
Contractor(s)
SUNDT CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0198-02-027
N-LINE TRAFFIC MAINTENANCE, L.P. (0.20)
WOLFE CONSTRUCTION GROUP, INC. (0.83)
K & S UTILITY CONTRACTORS, INC. (4.02)
OTTO TRUCKING, INC. (3.31)
APAC-TEXAS, INC. (19.01)
BREDA COMPANY, INC. (2.68)
ANTIGO CONSTRUCTION, INC. (0.02)
LAYFIELD CONSTRUCTION, INC (0.40)
A BROTHERS MILLING, LLC (0.18)
MORRIS COUNTY CONTRACTORS, L.L.C. (0.18)
STRIPING TECHNOLOGY, L.P. (0.54)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (1.00)
MCL CONTRACTING, LLC (0.04)
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C. (1.51)
PRIMATE CONSTRUCTION, INC. (0.00)
CARTHAGE DRILLING, INC. (0.01)
Contract #04153201
Totals37849155.31800630.3038202720.5499.9

CountyHENDERSON
HighwayUS 175
From0.85 MI E OF FM 315, IN POYNOR
ToANDERSON C/L
CSJ0198-02-035
Proj IDC 198-2-35
Work TypeGR,SUB BS,BS,HMAC,DRAIN STRS,SIGNS
 
0.9237052578.983665332.6551.9
CountyANDERSON
HighwayUS 175
From1.9 MI S OF FM 315 (HENDERSON C/L)
To0.5 MI NW OF SH 155 AT FRANKSTON
CSJ0198-03-027
Proj IDNH 1502(561)
Work TypeGR,SUB BS,BS,HMAC,DRAIN STRS,SIGNS
 
3.80420312971.6610776288.4453.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-17-16
Work Began05-04-16
Work Completed
Time Computed00-00-00
Contract Working Days571
Addl Days Granted22
Working Days Charged301
Percent Time Used50
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0198-02-035
STRIPING TECHNOLOGY, L.P. (0.36)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.16)
MARCOM"S MOWING SERVICE, LLC (0.21)
FORTSON CONTRACTING, INC. (0.04)
STRIPING SYSTEMS, INC. (0.00)
FARR FOUNDATION, INC. (0.32)
BIG CREEK CONSTRUCTION, LTD. (27.92)
NIXON ENGINEERING (0.03)
Contract #12153202
Totals27365550.64506387.6214441621.0952.7

CountyCHEROKEE
HighwayUS 69
From2.0 MI N OF FM 1247,NEAR WELLS,S
To0.9 MI S OF FM 1247 (ANGELINA C/L)
CSJ0199-03-028
Proj IDHP 2013(803)
Work TypeGRDG,STRS,BASE,OCST,SURF,PVT MRKG
 
2.89617687832.874295502.2524.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-05-16
Work Began01-23-17
Work Completed
Time Computed00-00-00
Contract Working Days350
Addl Days Granted42
Working Days Charged100
Percent Time Used25
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0199-03-028
AMERICAN REMEDIATION OPTIONS, INC. (2.08)
STRIPING TECHNOLOGY, L.P. (0.44)
STRIPING SYSTEMS, INC. (0.00)
TEX OP CONSTRUCTION, LP (1.05)
LUDCO, INC. (1.00)
FLEX SUPPLY, LLC (0.15)
Contract #06163005
Totals17687832.87303421.574295502.2524.2

CountyANDERSON
HighwayUS 79
From1.6 MI SW OF LP 256 IN PALESTINE, S
To0.4 MI SW OF FM 645
CSJ0205-07-043
Proj IDNH 2008(510)
Work TypeGR,BS,ASPH PVT, SIGS, ILLUM,SIGNS
 
8.60141986850.1944945029.4099.9
Work Order10-24-12
Work Began11-12-12
Work Completed
Time Computed11-09-12
Contract Working Days880
Addl Days Granted147
Working Days Charged975
Percent Time Used94
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0205-07-043
HIGHWAY TECHNOLOGIES, INC. (0.10)
STRIPING TECHNOLOGY, L.P. (1.65)
MAC TRANSPORTATION, LTD, L.L.P. (3.12)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (0.39)
AMERICAN REMEDIATION OPTIONS, INC. (0.53)
DANRIDGE CONSTRUCTION, LLC. (0.30)
DUSTROL, INC. (0.20)
WEST TEXAS RUMBLE STRIP (0.05)
SOUTHWEST ENVIRONMENT SERVICES LLC (1.68)
NORTH TEXAS REBAR, LLC (0.02)
TOTAL HIGHWAY MAINTENANCE, LLC (0.23)
P.R. PARKER COMPANY, INC. (0.00)
TEX OP CONSTRUCTION, LP (0.01)
DIRECTIONAL DRILLING (0.01)
DFW REBAR, INC. (0.01)
ROYAL REBAR (0.03)
Contract #09123003
Totals41986850.19163519.6344945029.4099.9

CountyANDERSON
HighwayUS 79
From1.5 MI EAST OF FM 2574
ToSTR#100010020601032 OVER UPRR
CSJ0206-01-049
Proj IDBR 1702(753)
Work TypeCLN/PNT GIRD,RPL RAIL,CONC DCK OVLY
 
0.6721646254.330.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-10-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days136
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
DREWERY CONSTRUCTION COMPANY, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0206-01-049
DIAMOND SURFACE, INC. (0.52)
SOUTHWEST ENVIRONMENT SERIVES, LLC (0.31)
MORRIS COUNTY CONTRACTORS, LLC (4.76)
HOUSTON SAWING & DRILLING (0.00)
AGGREGATE TECHNOLOGIES, INC. (3.23)
GIBSON & ASSOCIATES, INC. (14.88)
PANOLA SIGN & BARRICADE, INC. (0.72)
S & S BRIDGE PAINTING, INC. (9.03)
STRIPING TECHNOLOGY, L.P. (1.94)
Contract #08173017
Totals1646254.330.000.000.0

CountyGREGG
HighwayUS 259
FromAT HAWKINS PKWY IN LONGVIEW
To0.6 MI N OF SL 281
CSJ0392-03-047
Proj IDNH 1702(380)
Work TypeCONSTR RTL ON NBL
 
0.450475527.90431023.8790.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-20-17
Work Began08-21-17
Work Completed
Time Computed00-00-00
Contract Working Days36
Addl Days Granted0
Working Days Charged34
Percent Time Used94
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0392-03-047
ISAACS CONSTRUCTION SERVICES, LLC. (1.59)
SOUTHWEST ENVIRONMENT SERIVES, LLC (5.76)
TEX OP CONSTRUCTION, LP (2.50)
STRIPING TECHNOLOGY, L.P. (3.64)
TOTAL HIGHWAY MAINTENANCE, LLC (1.49)
STRIPING SYSTEMS, INC. (0.21)
Contract #06173210
Totals475527.900.00431023.8790.6

CountyGREGG
HighwaySH 149
FromAT SABINE RIVER #100930039301017
To.
CSJ0393-01-097
Proj IDBR 1502(474)
Work TypeCONC BR RAIL, MBGF, CONC STR RPR
 
0.9413114797.791379987.5144.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-09-17
Work Began07-24-17
Work Completed
Time Computed00-00-00
Contract Working Days145
Addl Days Granted0
Working Days Charged49
Percent Time Used33
Contractor(s)
GIBSON & ASSOCIATES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0393-01-097
S & S BRIDGE PAINTING, INC. (6.57)
ODUM SERVICES, L.P. (3.31)
SCR CIVIL CONSTRUCTION, LLC (11.57)
SOUTHERN CROSS CONTRACTORS, LLC (0.65)
SOUTHWEST ENVIRONMENT SERIVES, LLC (3.73)
APEX HIGHWAY SERVICES LLC (0.12)
DUSTROL, INC. (1.45)
ISAACS CONSTRUCTION SERVICES, LLC. (0.30)
STRIPING TECHNOLOGY, L.P. (1.00)
AXIS CONTRACTING, INC. (4.61)
STRIPING SYSTEMS, INC. (0.03)
Contract #04173008
Totals3114797.7973352.361379987.5144.3

CountySMITH
HighwaySH 31
FromFM 757, E
To2.5 MI W OF FM 2767(NR MULEY BRC),E
CSJ0424-01-048
Proj IDSTP 2013(640)
Work TypeGR,STRS,ACP BS & SURF,PVT MRK
 
10.7347802782.957904400.8799.9
Work Order10-29-14
Work Began11-18-14
Work Completed
Time Computed11-14-14
Contract Working Days328
Addl Days Granted0
Working Days Charged322
Percent Time Used98
Contractor(s)
REYNOLDS & KAY, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0424-01-048
SOUTHWEST ENVIRONMENT SERVICES LLC (4.79)
ALTUS TRAFFIC MANAGEMENT LLC (0.48)
STRIPING TECHNOLOGY, L.P. (2.44)
C.S. TREE SERVICE (0.48)
FORTSON CONTRACTING, INC. (0.09)
MURRAY CONSTRUCTION (0.22)
TEX OP CONSTRUCTION, LP (0.79)
J & I TRUCKING CO (1.05)
HOPE SERVICES, INC. (0.70)
HARRIS TRUCKING SERVICES (1.40)
ISAACS CONSTRUCTION SERVICES, LLC. (0.93)
TJT CONSTRUCTION (0.25)
Contract #08143053
Totals7802782.9510812.007904400.8799.9

CountyWOOD ETC
HighwaySH 182 ETC
From0.89 MI E OF US 69, E
ToSH 154
CSJ0429-01-023
Proj IDSTP 2017(358)HES
Work TypeSAFETY TREAT FIXED OBJECTS
 
27.8643239526.941114173.7034.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-01-17
Work Began04-07-17
Work Completed
Time Computed00-00-00
Contract Working Days387
Addl Days Granted0
Working Days Charged159
Percent Time Used41
Contractor(s)
HIGHWAY 19 CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0429-01-023
TOTAL HIGHWAY MAINTENANCE, LLC (0.87)
SOUTHWEST ENVIRONMENT SERVICES LLC (2.93)
MORRIS COUNTY CONTRACTORS, L.L.C. (1.27)
ISAACS CONSTRUCTION SERVICES, LLC. (2.61)
Contract #01173007
Totals3239526.9430067.721114173.7034.3

CountyVAN ZANDT
HighwayIH 20
FromAT FM 314 WB EXIT RAMP
To.
CSJ0495-03-061
Proj IDNH 1602(360)
Work TypeGR,CMT TR SBGR,CONC PVT,STRS,ILLUM
 
1.1304570487.364619912.8699.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-19-16
Work Began10-13-16
Work Completed
Time Computed00-00-00
Contract Working Days215
Addl Days Granted120
Working Days Charged287
Percent Time Used85
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0495-03-061
PANOLA SIGN & BARRICADE, INC. (0.81)
ISAACS CONSTRUCTION SERVICES, LLC. (0.97)
TEXOP CONSTRUCTION (1.28)
WEST TEXAS RUMBLE STRIP (0.08)
ODUM SERVICES, L.P. (0.66)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.26)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (1.44)
STRIPING TECHNOLOGY, L.P. (3.55)
JEFF WILSON BORING (0.02)
CARTHAGE DRILLING, INC. (0.31)
INDUS CONSTRUCTION, L.P. (0.54)
Contract #07163232
Totals4570487.36325224.074619912.8699.9

CountySMITH
HighwayIH 20
From0.79 MI W OF US 69 IN LINDALE, E
ToEND OF CONTROL SECTION
CSJ0495-04-067
Proj IDNH 2017(747)
Work TypeTBPFC&ACP SURF,PLG,BRG JNTS,TEXTURE
 
6.7902876796.852713790.7795.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-04-17
Work Began09-25-17
Work Completed
Time Computed00-00-00
Contract Working Days51
Addl Days Granted0
Working Days Charged78
Percent Time Used152
Contractor(s)
CLARK CONSTRUCTION OF TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0495-04-067
INTERSTATE BARRICADES & MARKINGS, INC. (0.82)
DUSTIN ALLEN, INC. (1.21)
CHEROKEE SERVICES (7.63)
WOLFE CONSTRUCTION GROUP, INC. (0.32)
TOTAL HIGHWAY MAINTENANCE, LLC (1.97)
STRIPE-A-ZONE, INC. (0.41)
R & G CONSTRUCTION (0.86)
Contract #02173003
Totals2876796.85106671.092713790.7795.0

CountyVAN ZANDT
HighwaySH 243
FromSH 198, E
ToSH 64 IN CANTON
CSJ0522-02-037
Proj IDSTP 1702(386)
Work TypeGR, STRS, WDNG, OCST, ACP, PVT MRKG
 
1.3216654770.061630653.2224.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-20-17
Work Began08-24-17
Work Completed
Time Computed00-00-00
Contract Working Days213
Addl Days Granted0
Working Days Charged39
Percent Time Used18
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0522-02-037
STRIPING TECHNOLOGY, L.P. (6.31)
PANOLA SIGN & BARRICADE, INC. (0.33)
SCOTT DERR PAINTING CO, LLC (0.11)
TEX OP CONSTRUCTION, LP (0.67)
ODUM SERVICES, L.P. (0.51)
USA SWPPP INSPECTIONS, INC.DBA USA EROSION (3.45)
MAC TRANSPORTATION, LTD, L.L.P. (1.76)
SOUTHWEST ENVIRONMENT SERIVES, LLC (0.50)
Contract #06173232
Totals6654770.06199848.761630653.2224.5

page 1 | page 2 | page 3