Monthly State Let Construction Report For Odessa District As Of Jan 10, 2018 Page 1 Of 2

Last Update: Wednesday, January 10, 2018
FTP Icon
page 1 | page 2

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyWARD
HighwayBI 20-D
FromAT SL 464.
To.
CSJ0004-03-049
Proj IDSTP 1702(023)HES
Work TypeINSTALL TRAFFIC SIGNALS
 
0.416562624.3095001.8816.8
Work Order07-06-17
Work Began00-00-00
Work Completed
Time Computed10-05-17
Contract Working Days180
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
WILLIS ELECTRIC CO., LP
SUBCONTRACTOR(S) FOR CCSJ: 0004-03-049
JONES BROTHERS, INC. (22.69)
BARRICADES UNLIMITED (6.19)
Contract #05173022
Totals562624.300.0095001.8816.8

CountyWARD ETC
HighwaySS 57 ETC
From0.1 MI EAST OF FM 1219
To0.1 MI WEST OF FM 1219
CSJ0004-03-050
Proj IDSTP 2017(144)HESG
Work TypeINSTALL FLASHING BEASON AND SIGNALS
 
164.082619319.30211808.8534.2
Work Order11-22-16
Work Began11-07-17
Work Completed
Time Computed02-21-17
Contract Working Days143
Addl Days Granted0
Working Days Charged12
Percent Time Used8
Contractor(s)
WILLIS ELECTRIC CO., LP
SUBCONTRACTOR(S) FOR CCSJ: 0004-03-050
DOUBLE A CONTRACTING, L.P. (2.32)
BARRICADES UNLIMITED (3.90)
DK CONTRACTING, LLC (7.41)
Contract #10163211
Totals619319.301725.00211808.8534.2

CountyWARD
HighwayIH 20
FromFM 1219
ToEAST BI 20-D
CSJ0004-04-086
Proj IDNH 2017(031)
Work TypeRECONSTRUCT PAVEMENT
 
10.72314274035.0113320517.3393.3
Work Order10-21-16
Work Began04-26-17
Work Completed
Time Computed01-20-17
Contract Working Days327
Addl Days Granted0
Working Days Charged232
Percent Time Used70
Contractor(s)
FNF CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0004-04-086
DUSTROL, INC. (2.85)
F & W ELECTRICAL CONTRACTORS, INC. (2.15)
CHEROKEE SERVICES (0.69)
DOUBLE A CONTRACTING, L.P. (1.52)
BARRICADES UNLIMITED (0.58)
RICE ENVIRONMENTAL SERVICES (2.16)
RPV CONSTRUCTION (2.60)
CI CONSTRUCTORS, INC. (0.12)
PENHALL COMPANY (0.15)
Contract #09163203
Totals14274035.01477282.1413320517.3393.3

CountyWARD
HighwayIH 20
From1.5 MILES WEST OF FM 1927
ToFM 1219
CSJ0004-04-087
Proj IDNH 2017(276)
Work TypeRECONSTRUCT PAVEMENT
 
9.02613195417.3313450249.5199.9
Work Order12-12-16
Work Began03-27-17
Work Completed
Time Computed03-13-17
Contract Working Days351
Addl Days Granted0
Working Days Charged204
Percent Time Used58
Contractor(s)
JONES BROS. DIRT & PAVING CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0004-04-087
BARRICADES UNLIMITED (1.69)
COX PAVING OF TEXAS, INC. (17.30)
DUSTROL, INC. (3.59)
AREA WIDE PROTECTIVE, INC. (0.68)
RPV CONSTRUCTION (0.81)
WILLIS ELECTRIC CO., LP (1.69)
REECE CONSTRUCTION CO., INC. (0.88)
DOUBLE A CONTRACTING, L.P. (1.07)
LPZ ENTERPRISES, LLC (2.76)
R.E.B. TRUCKING (5.50)
DK CONTRACTING, LLC (0.37)
DTM TRUCKING, INC. (0.41)
Contract #11163203
Totals13195417.3356791.9613450249.5199.9

CountyMARTIN ETC
HighwayIH 20 ETC
FromAT SH 137
To.
CSJ0005-04-069
Proj IDSTP 2016(650)HES
Work TypeINSTALL INTERSECTION FLASH BEACON
 
1.330759179.13450519.1559.3
Work Order03-14-16
Work Began08-28-17
Work Completed
Time Computed06-13-16
Contract Working Days260
Addl Days Granted0
Working Days Charged258
Percent Time Used99
Contractor(s)
WILLIS ELECTRIC CO., LP
SUBCONTRACTOR(S) FOR CCSJ: 0005-04-069
BARRICADES UNLIMITED (5.24)
DOUBLE A CONTRACTING, L.P. (1.20)
JOSH FRANKLIN DRILLING, LLC (1.93)
Contract #02163240
Totals759179.13123005.14450519.1559.3

CountyMARTIN
HighwayIH 20
FromWEST OF SH 137
ToEAST OF BI 20-F EAST INTERCHANGE
CSJ0005-04-071
Proj IDNH 2018(266)
Work TypePLANE,HOTMIX,MBGF & PAV MRKS
 
3.4915784004.910.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order12-14-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days137
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
PRICE CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0005-04-071
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11173215
Totals5784004.910.000.000.0

CountyMARTIN
HighwayIH 20
FromAT BI 20-F WEST
To.
CSJ0005-04-072
Proj IDNH 1702(494)
Work TypeBRIDGE REPAIR
 
0.9841987502.231965205.3198.8
Work Order08-11-17
Work Began09-25-17
Work Completed
Time Computed09-25-17
Contract Working Days88
Addl Days Granted0
Working Days Charged57
Percent Time Used64
Contractor(s)
GIBSON & ASSOCIATES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0005-04-072
BARRICADES UNLIMITED (3.10)
HJC FARMS, INC. (6.18)
JONES BROS. DIRT & PAVING CONTRACTORS, INC. (37.56)
R.E.B. TRUCKING (5.11)
REECE CONSTRUCTION CO, INC. (6.71)
CONTRACTORS SERVICE COMPANY (1.29)
Contract #07173043
Totals1987502.23377882.501965205.3198.8

CountyECTOR
HighwayIH 20
FromDIXIE BLVD
ToMONAHANS DRAW
CSJ0005-13-056
Proj IDBR 1702(495)
Work TypeUPGRADE BRIDGE AND APPROACH RAILING
 
4.1003958979.200.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-01-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days300
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
SCR CIVIL CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0005-13-056
JONES BROS. DIRT & PAVING CONTRACTORS, INC. (11.22)
R.E.B. TRUCKING (0.49)
DOUBLE A CONTRACTING, L.P. (2.12)
BARRICADES UNLIMITED (2.01)
RPV CONSTRUCTION (12.64)
Contract #07173212
Totals3958979.200.000.000.0

CountyMIDLAND
HighwayIH 20
FromWEST OF FM 1788
ToEAST OF FM 1788
CSJ0005-14-080
Proj IDIM 0201(189)
Work TypeEXTEND ON/OFF RAMPS
 
1.15411801426.9911964697.3899.9
Work Order06-11-15
Work Began08-09-16
Work Completed
Time Computed10-10-15
Contract Working Days210
Addl Days Granted131
Working Days Charged297
Percent Time Used87
Contractor(s)
JONES BROS. DIRT & PAVING CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0005-14-080
BARRICADES UNLIMITED (2.48)
DTM TRUCKING, INC. (0.24)
R.E.B. TRUCKING (1.44)
TEXOP CONSTRUCTION (0.28)
WILLIS ELECTRIC CO., LP (9.29)
WEST TEXAS RUMBLE STRIP (0.03)
DESERT PAVING, INC. (2.80)
ALTEX LANDSCAPE CONSTRUCTION, INC. (0.16)
REECE CONSTRUCTION CO., INC. (7.17)
BOLER EQUIPMENT (2.41)
JOSH FRANKLIN DRILLING, LLC (0.67)
RPV CONSTRUCTION (0.88)
Contract #04153049
Totals11801426.993450.0011964697.3899.9

CountyPECOS ETC
HighwayUS 67 ETC
From0.2 MI S OF CHANCELLOR RD
ToBREWSTER COUNTY LINE
CSJ0075-02-027
Proj IDSTP 1702(215)HESG
Work TypeEDGELINE & CENTERLINE RUMBLE STRIPS
 
420.5572345678.91525945.4222.4
Work Order06-14-17
Work Began10-24-17
Work Completed
Time Computed09-13-17
Contract Working Days160
Addl Days Granted0
Working Days Charged59
Percent Time Used36
Contractor(s)
STRIPE-A-ZONE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0075-02-027
RED SIXTEEN CONSTRUCTION, INC (2.82)
Contract #05173242
Totals2345678.91230768.57525945.4222.4

CountyPECOS
HighwayUS 67 ETC
From1.1 MI NORTH OF IH 10
To14.2 MI NORTH OF IH 10
CSJ0076-01-028
Proj IDSTP 1702(031)HES
Work TypeSAFETY TREAT FIXED OBJECTS
 
15.2435286212.00464250.008.7
Work Order06-14-17
Work Began10-09-17
Work Completed
Time Computed09-13-17
Contract Working Days288
Addl Days Granted0
Working Days Charged64
Percent Time Used22
Contractor(s)
VIZCAINO, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0076-01-028
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05173228
Totals5286212.0042200.00464250.008.7

CountyREEVES
HighwayUS 285
FromCR 232
ToSH 302
CSJ0139-03-039
Proj IDNH 1702(685)
Work TypeRECONSTRUCT AND WIDEN
 
10.04715005109.23986755.446.5
Work Order09-14-17
Work Began12-14-17
Work Completed
Time Computed12-14-17
Contract Working Days380
Addl Days Granted0
Working Days Charged6
Percent Time Used1
Contractor(s)
FNF CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0139-03-039
DOUBLE A CONTRACTING, L.P. (1.13)
DUSTROL, INC. (0.14)
HJC FARMS, INC. (0.77)
Contract #08173004
Totals15005109.23986755.44986755.446.5

CountyREEVES
HighwayUS 285
FromRM 652
ToCR 232
CSJ0139-03-040
Proj IDNH 1602(182)
Work TypeREHABILITATION OF EXISTING ROADWAY
 
10.80612525496.025000178.5839.9
Work Order08-19-16
Work Began02-14-17
Work Completed
Time Computed11-18-16
Contract Working Days332
Addl Days Granted0
Working Days Charged154
Percent Time Used46
Contractor(s)
CI CONSTRUCTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0139-03-040
BARRICADES UNLIMITED (0.67)
HJC FARMS, INC. (2.02)
PAVEMENT MARKINGS INC. (0.84)
W.S. CONSTRUCTION COMPANY (2.11)
Contract #06163203
Totals12525496.02927558.955000178.5839.9

CountyREEVES
HighwayUS 285
FromAT IH 20
To.
CSJ0139-05-044
Proj IDBR 1702(146)
Work TypeBRIDGE REPAIR
 
0.233936605.40941860.7999.9
Work Order05-09-17
Work Began08-14-17
Work Completed
Time Computed08-08-17
Contract Working Days75
Addl Days Granted0
Working Days Charged80
Percent Time Used106
Contractor(s)
SCR CIVIL CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0139-05-044
RPV CONSTRUCTION (11.47)
BARRICADES UNLIMITED (3.63)
PMI PAVEMENT MARKING, INC. (2.37)
Contract #04173041
Totals936605.40172821.27941860.7999.9

CountyPECOS
HighwayUS 285
From0.66 MILES NORTH OF IH 10
To1.72 MILES NORTH OF IH 10
CSJ0139-08-037
Proj IDNH 2017(474)
Work TypeROADWAY WIDENING
 
1.0601244957.001333946.7199.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-28-17
Work Began06-19-17
Work Completed
Time Computed06-19-17
Contract Working Days58
Addl Days Granted30
Working Days Charged82
Percent Time Used93
Contractor(s)
REECE ALBERT, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0139-08-037
BARRICADES UNLIMITED (1.21)
HJC FARMS, INC. (1.19)
DOUBLE A CONTRACTING, L.P. (2.41)
DELGADOS CONSTRUCTION, DBA ERNESTO A. DELGADO (8.68)
TITAN MILLING INC. (0.86)
Contract #03173214
Totals1244957.000.001333946.7199.9

CountyUPTON
HighwaySH 349
FromRM 2401
To6.6 MI SOUTH OF RM 2401
CSJ0380-11-025
Proj IDSTP 1502(619)
Work TypeREHABILITATION OF EXISTING ROAD
 
20.51217114217.0716322835.9095.3
Work Order09-22-15
Work Began05-04-16
Work Completed
Time Computed05-01-16
Contract Working Days374
Addl Days Granted0
Working Days Charged357
Percent Time Used95
Contractor(s)
DELHUR INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0380-11-025
BARRICADES UNLIMITED (3.10)
HJC FARMS, INC. (0.26)
LIPHAM ASPHALT AND PAVING COMPANY, LLC (5.61)
DTM TRUCKING, INC. (5.27)
ALL-IN CONSTRUCTION (0.50)
Contract #08153004
Totals17114217.07176746.1216322835.9095.3

CountyMIDLAND
HighwaySH 158
From4 MI SE OF IH 20
ToGLASSCOCK COUNTY LINE
CSJ0463-03-049
Proj IDNH 1702(332)
Work TypePAVEMENT OVERLAY
 
12.1273997554.79808946.0920.2
Work Order07-20-17
Work Began11-14-17
Work Completed
Time Computed08-20-17
Contract Working Days60
Addl Days Granted0
Working Days Charged57
Percent Time Used95
Contractor(s)
FNF CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0463-03-049
DOUBLE A CONTRACTING, L.P. (5.01)
HUDSON, INC. (0.39)
PMI PAVEMENT MARKING, INC. (0.34)
Contract #06173211
Totals3997554.792039.10808946.0920.2

CountyREEVES
HighwayRM 652
FromUS 285
ToPECOS RIVER
CSJ0493-01-013
Proj IDSTP 1702(333)
Work TypeROADWAY RESTORATION
 
5.6395983269.30618999.3210.3
Work Order07-21-17
Work Began10-23-17
Work Completed
Time Computed10-20-17
Contract Working Days107
Addl Days Granted0
Working Days Charged37
Percent Time Used34
Contractor(s)
CI CONSTRUCTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0493-01-013
DK CONTRACTING, LLC (0.43)
Z-TEK (7.75)
PMI PAVEMENT MARKING, INC. (2.61)
Contract #06173008
Totals5983269.30133309.12618999.3210.3

CountyANDREWS
HighwaySH 176
FromNM STATE LINE
To3.3 MI NORTH OF FM 1967
CSJ0548-05-048
Proj IDSTP 1602(296)
Work TypeWIDEN SUBGRADE,PASSING LANES
 
11.61610506607.749370005.3989.1
Work Order09-19-16
Work Began01-27-17
Work Completed
Time Computed12-19-16
Contract Working Days360
Addl Days Granted0
Working Days Charged206
Percent Time Used57
Contractor(s)
JONES BROS. DIRT & PAVING CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0548-05-048
CONTRACTORS SERVICE COMPANY (0.45)
REECE CONSTRUCTION CO., INC. (2.58)
WILLIS ELECTRIC CO., LP (0.57)
DTM TRUCKING, INC. (4.56)
R.E.B. TRUCKING (2.52)
DOUBLE A CONTRACTING, L.P. (2.05)
Contract #07163206
Totals10506607.7430156.909370005.3989.1

CountyECTOR
HighwayVA
FromDISTRICTWIDE
To.
CSJ0906-00-169
Proj IDC 906-00-169
Work TypeNON-SITE SPECIFIC TRAFFIC SIGNALS
 
0.0013256207.302367522.4672.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-22-15
Work Began05-12-16
Work Completed
Time Computed02-20-16
Contract Working Days240
Addl Days Granted100
Working Days Charged201
Percent Time Used59
Contractor(s)
WILLIS ELECTRIC CO., LP
SUBCONTRACTOR(S) FOR CCSJ: 0906-00-169
BARRICADES UNLIMITED (2.34)
DESERT PAVING, INC. (6.04)
MICA CORPORATION (6.28)
CONTRACTORS SERVICE COMPANY (2.19)
JONES BROS. DIRT & PAVING CONTRACTORS, INC. (1.68)
GESCH CONTRACTING, INC. (1.16)
WEST TEXAS CONTRACTORS (0.48)
JOSH FRANKLIN DRILLING, LLC (0.69)
BATTEN DRILLING, INC. (0.42)
Contract #07153220
Totals3256207.300.002367522.4672.7

page 1 | page 2