Monthly Local Let Maintenance Report For Laredo District As Of Jan 10, 2018 Page 2 Of 4

Last Update: Wednesday, January 10, 2018
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyWEBB
HighwayUS0083
FromUS 83
ToVARIOUS
CSJ6299-31-001
Proj IDRMC - 629931001
Work TypeCLEANING AND SWEEPING OF HIGHWAYS
 
66.010187777.74122379.3765.1
Work Order04-28-17
Work Began05-01-17
Work Completed
Time Computed05-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged242
Percent Time Used66
Contractor(s)
CTX SPECIAL SERVICES CO LLC
SUBCONTRACTOR(S) FOR CCSJ: 6299-31-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02172201
Totals187777.7415332.26122379.3765.1

CountyWEBB
HighwayIH0035
FromIH 35
ToVARIOUS
CSJ6299-42-001
Proj IDRMC - 629942001
Work TypeCLEANING AND SWEEPING OF HIGHWAYS
 
85.880299280.00180972.0060.4
Work Order04-01-17
Work Began04-03-17
Work Completed
Time Computed04-03-17
Contract Working Days365
Addl Days Granted0
Working Days Charged272
Percent Time Used74
Contractor(s)
RK POWER DRIVE SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6299-42-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02172202
Totals299280.0020108.00180972.0060.4

CountyWEBB
HighwayIH0035
FromIH 35
ToVARIOUS
CSJ6300-77-001
Proj IDRMC - 630077001
Work TypeMAINTENANCE OF ILLUMINATION SYSTEMS ALON
 
0.001120800.0080000.0066.2
Work Order07-29-16
Work Began08-01-16
Work Completed
Time Computed08-01-16
Contract Working Days730
Addl Days Granted0
Working Days Charged515
Percent Time Used70
Contractor(s)
TRIPLE H FIELD SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6300-77-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07162201
Totals120800.005000.0080000.0066.2

CountyVAL VERDE
HighwayUS0090
FromUS 277
ToVARIOUS
CSJ6301-03-001
Proj IDRMC - 630103001
Work TypeUPGRADE OF EXISTING MBGF, DOWNSTREAM ANC
 
0.001312383.64385796.6899.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-08-16
Work Began08-15-16
Work Completed
Time Computed08-15-16
Contract Working Days365
Addl Days Granted91
Working Days Charged456
Percent Time Used100
Contractor(s)
ELITE CASTLE RESOURCES LLC
SUBCONTRACTOR(S) FOR CCSJ: 6301-03-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05162203
Totals312383.640.00385796.6899.9

CountyVAL VERDE
HighwaySS0239
FromDEL RIO TXDOT COMPLEX
ToDEL RIO TXDOT COMPLEX
CSJ6301-67-001
Proj IDRMC - 630167001
Work TypeLANDSCAPE MAINTENANCE
 
0.00111200.008475.0075.6
Work Order12-01-16
Work Began12-15-16
Work Completed
Time Computed12-15-16
Contract Working Days365
Addl Days Granted0
Working Days Charged365
Percent Time Used100
Contractor(s)
DELGADO'S CONSTRUCTION
SUBCONTRACTOR(S) FOR CCSJ: 6301-67-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11162201
Totals11200.000.008475.0075.6

CountyKINNEY
HighwayUS0090
FromUS 90
ToVARIOUS
CSJ6302-58-001
Proj IDRMC - 630258001
Work TypeUPGRADE OF EXISTING BRIDGE RAIL
 
0.001194084.00232565.1799.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-23-17
Work Began01-23-17
Work Completed
Time Computed01-23-17
Contract Working Days60
Addl Days Granted0
Working Days Charged60
Percent Time Used100
Contractor(s)
DELGADO'S CONSTRUCTION
SUBCONTRACTOR(S) FOR CCSJ: 6302-58-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11162202
Totals194084.000.00232565.1799.9

CountyMAVERICK
HighwayUS0277
FromUS 277
ToVARIOUS
CSJ6305-28-001
Proj IDSUP - 630528001
Work TypePICNIC AREA MAINTENANCE
 
0.00160934.8044554.3073.1
Work Order06-28-16
Work Began07-01-16
Work Completed
Time Computed07-01-16
Contract Working Days730
Addl Days Granted0
Working Days Charged549
Percent Time Used75
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6305-28-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06162232
Totals60934.802079.0044554.3073.1

CountyDIMMIT
HighwayUS0083
FromUS 83
ToVARIOUS
CSJ6305-70-001
Proj IDRMC - 630570001
Work TypeMOWING OF HIGHWAYS RIGHT-OF-WAY
 
246.200271941.57186397.7068.5
Work Order10-18-16
Work Began10-24-16
Work Completed
Time Computed10-24-16
Contract Working Days365
Addl Days Granted365
Working Days Charged434
Percent Time Used59
Contractor(s)
R&M INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6305-70-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08162202
Totals271941.5767775.36186397.7068.5

CountyWEBB
HighwayIH0035
FromIH 35
ToVARIOUS
CSJ6307-45-001
Proj IDRMC - 630745001
Work TypeMAINTENANCE OF LARGE SIGNS ALONG IH 35
 
0.001219367.150.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
SAENZ UTILITY CONTRACTORS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6307-45-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11172201
Totals219367.150.000.000.0

CountyVAL VERDE
HighwayUS0277
FromUS 277
ToVARIOUS
CSJ6307-52-001
Proj IDRMC - 630752001
Work TypeINSTALL TRAFFIC SIG., FLASH BEACONS PVT
 
0.001168873.25206965.3999.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-22-16
Work Began11-22-16
Work Completed
Time Computed11-22-16
Contract Working Days365
Addl Days Granted0
Working Days Charged365
Percent Time Used100
Contractor(s)
TRIPLE H FIELD SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6307-52-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10162204
Totals168873.250.00206965.3999.9

CountyVAL VERDE
HighwaySL0025
FromVARIOUS
To.
CSJ6308-23-001
Proj IDSUP - 630823001
Work TypeJANITORIAL AND GROUNDS
 
0.001140119.2023158.5916.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-25-16
Work Began00-00-00
Work Completed
Time Computed09-01-16
Contract Working Days720
Addl Days Granted0
Working Days Charged122
Percent Time Used16
Contractor(s)
TIBH INDUSTRIES, INC.
E.Q.U.I.P. ENTERPRISES
SUBCONTRACTOR(S) FOR CCSJ: 6308-23-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08162203
Totals140119.200.0023158.5916.5

CountyZAVALA
HighwayUS0083
FromUS 83
ToVARIOUS
CSJ6309-73-001
Proj IDRMC - 630973001
Work TypeMOWING OF HIGHWAYS RIGHT-OF-WAY
 
0.001345279.80259136.4375.0
Work Order12-21-16
Work Began12-21-16
Work Completed
Time Computed12-21-16
Contract Working Days730
Addl Days Granted0
Working Days Charged396
Percent Time Used54
Contractor(s)
R&M INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6309-73-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11162203
Totals345279.8086378.81259136.4375.0

CountyVAL VERDE
HighwaySS0239
FromDEL RIO AREA/MAINTENANCE COMPLEX
ToDEL RIO AREA/MAINTENANCE COMPLEX
CSJ6310-71-001
Proj IDSUP - 631071001
Work TypeJANITORIAL MAINTENANCE @ DEL RIO COMPLEX
 
0.00137664.5216459.0843.6
Work Order12-01-16
Work Began12-01-16
Work Completed
Time Computed12-01-16
Contract Working Days730
Addl Days Granted0
Working Days Charged396
Percent Time Used54
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6310-71-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11162231
Totals37664.521364.0816459.0843.6

CountyDIMMIT
HighwayUS0083
FromUS 83
ToVARIOUS
CSJ6310-77-001
Proj IDRMC - 631077001
Work TypeCLEAN/SWEEP OF HIGHWAYS AND LITTER PICKU
 
57.000120951.56138603.3199.9
Work Order01-23-17
Work Began01-23-17
Work Completed
Time Computed01-23-17
Contract Working Days365
Addl Days Granted0
Working Days Charged340
Percent Time Used93
Contractor(s)
CTX SPECIAL SERVICES CO LLC
SUBCONTRACTOR(S) FOR CCSJ: 6310-77-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11162204
Totals120951.5615546.86138603.3199.9

CountyMAVERICK
HighwayUS0277
FromUS 277
ToVARIOUS
CSJ6311-22-001
Proj IDRMC - 631122001
Work TypeCLEANING/SWEEPING OF HIGHWAYS AND LITTER
 
0.001269060.54121841.4245.2
Work Order04-27-17
Work Began05-01-17
Work Completed
Time Computed05-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged245
Percent Time Used67
Contractor(s)
CROSBY RD CONSTRUCTION INC
SUBCONTRACTOR(S) FOR CCSJ: 6311-22-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03172201
Totals269060.5410734.14121841.4245.2

CountyKINNEY
HighwayUS0090
FromUS 90
ToUS 90
CSJ6313-05-001
Proj IDSUP - 631305001
Work TypePICNIC AREA MAINTENANCE
 
0.00176392.4031961.9641.8
Work Order02-01-17
Work Began02-01-17
Work Completed
Time Computed02-01-17
Contract Working Days730
Addl Days Granted0
Working Days Charged334
Percent Time Used45
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6313-05-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01172231
Totals76392.404156.1631961.9641.8

CountyVAL VERDE
HighwayUS0277
FromUS 277
ToVARIOUS
CSJ6313-10-001
Proj IDSUP - 631310001
Work TypePICNIC AREA MAINTENANCE
 
0.00175691.5835874.8547.3
Work Order02-01-17
Work Began02-01-17
Work Completed
Time Computed02-01-17
Contract Working Days730
Addl Days Granted0
Working Days Charged334
Percent Time Used45
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6313-10-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01172232
Totals75691.585452.1535874.8547.3

CountyWEBB
HighwayIH0035
FromIH 35
ToVARIOUS
CSJ6313-17-001
Proj IDRMC - 631317001
Work TypeMOWING OF HIGHWAYS RIGHT-OF-WAY
 
300.200174224.05219025.1699.9
Work Order06-05-17
Work Began06-05-17
Work Completed
Time Computed06-06-17
Contract Working Days365
Addl Days Granted0
Working Days Charged206
Percent Time Used56
Contractor(s)
SPARTAN DIRECT SOLUTIONS LLC
SUBCONTRACTOR(S) FOR CCSJ: 6313-17-001
R&M INCORPORATED (55.01)
Contract #04172201
Totals174224.0578346.68219025.1699.9

CountyWEBB
HighwayIH0035
FromIH 35
ToVARIOUS
CSJ6313-28-001
Proj IDRMC - 631328001
Work TypeTIRE RUBBER DEBRIS REMOVAL ON ROADWAYS
 
141.500273421.44148300.5654.2
Work Order06-01-17
Work Began06-01-17
Work Completed
Time Computed06-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged211
Percent Time Used57
Contractor(s)
M & M STRIPING & POWER WASHING, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6313-28-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04172202
Totals273421.4414126.76148300.5654.2

CountyWEBB
HighwaySL0020
FromLP 20
ToLP 20
CSJ6313-32-001
Proj IDSUP - 631332001
Work TypeLANDCAPE MAINT. SERVICE @ LRD DISTRICT C
 
0.00142902.0413563.6031.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began02-01-17
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged334
Percent Time Used45
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6313-32-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01172233
Totals42902.040.0013563.6031.6

page 1 | page 2 | page 3 | page 4