Monthly State Let Construction Report For Laredo District As Of Feb 09, 2018 Page 2 Of 2

Last Update: Friday, February 09, 2018
FTP Icon
page 1 | page 2

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyDIMMIT
HighwayUS 277
FromFM 393
ToSL 517
CSJ0300-03-066
Proj IDNH 2016(478)
Work TypePLANING, ACP, OVERLAY PAV MRK
 
30.5609546333.929176755.4996.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-29-16
Work Began06-27-16
Work Completed
Time Computed00-00-00
Contract Working Days205
Addl Days Granted0
Working Days Charged196
Percent Time Used95
Contractor(s)
H. L. ZUMWALT CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0300-03-066
CHEROKEE SERVICES (0.34)
FLASHER EQUIPMENT COMPANY (1.83)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (2.00)
DELGADO"S CONSTRUCTION (0.41)
FOUR J TRAFFIC CONTROLS, INC. (0.92)
ALL AMERICAN TRUCKING, INC. (1.29)
PIONEER UTILITIES, INC. (0.00)
Contract #01163217
Totals9546333.920.009176755.4996.1

CountyLASALLE
HighwaySH 97
FromFRIO RIVER BRIDGE
To.
CSJ0328-08-022
Proj IDBR 1502(514)
Work TypeREPLACEMENT OF EXISTING BRIDGE
 
0.1608315541.287539160.4291.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-30-15
Work Began07-06-16
Work Completed
Time Computed00-00-00
Contract Working Days373
Addl Days Granted70
Working Days Charged343
Percent Time Used113
Contractor(s)
ANDERSON COLUMBIA CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0328-08-022
FLASHER EQUIPMENT COMPANY (1.14)
D&S TEXAS ICON CONSTRUCTION (1.52)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (1.59)
AARON CONCRETE CONTRACTORS, L.P. (1.78)
PRIMATE CONSTRUCTION, INC. (0.32)
VOGES DRILLING CO. (4.79)
CUATRO T CONSTRUCTION, INC. (0.67)
RIO GRANDE REBAR RODBUSTERS, LLC. (0.50)
Contract #08153038
Totals8315541.28251009.797539160.4291.2

CountyWEBB
HighwayUS 59 ETC
FromCASA DEL SOL
ToIH 35
CSJ0542-01-083
Proj IDSTP 1602(512)HES
Work TypeIMPROVE TRAFFIC SIGNALS
 
16.1691680643.301724095.2799.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-14-16
Work Began05-08-17
Work Completed
Time Computed00-00-00
Contract Working Days145
Addl Days Granted0
Working Days Charged140
Percent Time Used96
Contractor(s)
TRAF-TEX, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0542-01-083
FLASHER EQUIPMENT COMPANY (10.05)
Contract #08163225
Totals1680643.30156341.681724095.2799.9

CountyWEBB
HighwayVA
FromDISTRICTWIDE
To.
CSJ0922-00-056
Proj IDSTP 1602(137)
Work TypeUPGRADE RAIL
 
1.3961498321.431391981.7093.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-08-16
Work Began09-19-16
Work Completed
Time Computed00-00-00
Contract Working Days281
Addl Days Granted0
Working Days Charged290
Percent Time Used103
Contractor(s)
CRG
SUBCONTRACTOR(S) FOR CCSJ: 0922-00-056
FLASHER EQUIPMENT COMPANY (0.64)
RPV CONSTRUCTION (22.55)
Contract #05163214
Totals1498321.4358935.111391981.7093.3

CountyWEBB
HighwayVA
FromAT VARIOUS LOCATIONS IN WEBB CNTY
To.
CSJ0922-00-062
Proj IDSTP 1502(256)
Work TypeCONSTRUCT CURB RAMPS
 
0.1001680038.501236264.0573.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-22-17
Work Began05-02-17
Work Completed
Time Computed00-00-00
Contract Working Days184
Addl Days Granted0
Working Days Charged177
Percent Time Used96
Contractor(s)
ENCINO LANDSCAPE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0922-00-062
FLASHER EQUIPMENT COMPANY (1.71)
CLASSIC TEJAS CONSTRUCTION, INC. (5.76)
PAVEMENT MARKINGS INC. (2.94)
Contract #01173008
Totals1680038.5035510.001236264.0573.5

CountyLASALLE
HighwayCS
FromVARIOUS LOCATIONS IN ENCINAL
To.
CSJ0922-20-019
Proj IDSTP 1602(372)TAPS
Work TypeSAFE PATH SIDEWALK PROJECT
 
0.100242635.10216605.4189.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-02-17
Work Began04-06-17
Work Completed
Time Computed00-00-00
Contract Working Days90
Addl Days Granted0
Working Days Charged90
Percent Time Used100
Contractor(s)
JESS CONTRACTING, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0922-20-019
FLASHER EQUIPMENT COMPANY (2.02)
PAVEMENT MARKINGS INC. (1.55)
Contract #01173214
Totals242635.1014909.31216605.4189.2

CountyDUVAL
HighwayVA
FromVARIOUS LOCATIONS IN SAN DIEGO TX
To.
CSJ0922-23-009
Proj IDSTP 2017(030)TAPS
Work TypeSAFE PATH SIDEWALK PROJECT
 
3.3331157974.501039657.4089.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-22-17
Work Began04-10-17
Work Completed
Time Computed00-00-00
Contract Working Days180
Addl Days Granted0
Working Days Charged156
Percent Time Used86
Contractor(s)
ENCINO LANDSCAPE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0922-23-009
CLASSIC TEJAS CONSTRUCTION, INC. (1.72)
HIGHWAY BARRICADES AND SERVICES, LLC (3.61)
Contract #01173208
Totals1157974.5011970.001039657.4089.7

CountyDIMMIT
HighwayFM 190
FromUS 83
ToSH 85
CSJ0963-01-032
Proj IDSSW 963-1-32
Work TypeBRIDGE REPLACEMENTS,BASE,SURFACING
 
11.4714902990.223015412.3261.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-08-17
Work Began04-17-17
Work Completed
Time Computed00-00-00
Contract Working Days228
Addl Days Granted16
Working Days Charged197
Percent Time Used80
Contractor(s)
IOC COMPANY LLC
SUBCONTRACTOR(S) FOR CCSJ: 0963-01-032
PAVEMENT MARKINGS INC. (1.96)
HOUSTON SAWING & DRILLING (0.11)
W. W. FOUNDATION DRILLING, LTD. (4.85)
CERTIFIED PLACERS LLC (0.65)
Contract #02173035
Totals4902990.22344596.283015412.3261.5

CountyZAVALA
HighwayFM 1025
FromUS 83
ToFM 117
CSJ1279-01-036
Proj IDSTP 1302(036)
Work TypeGRADE,WIDEN,STR,SURF TREAT,PAV MRKS
 
19.8557134438.217050414.6998.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-03-16
Work Began09-12-16
Work Completed
Time Computed00-00-00
Contract Working Days322
Addl Days Granted0
Working Days Charged291
Percent Time Used90
Contractor(s)
RAY FARIS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1279-01-036
MURRAY CONSTRUCTION (0.84)
D&S TEXAS ICON CONSTRUCTION (1.46)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (1.60)
MV HENKE COMPANY, LLC (2.01)
FLASHER EQUIPMENT COMPANY (2.56)
RELMCO, INC. (8.40)
Contract #06163208
Totals7134438.21101420.577050414.6998.8

CountyWEBB
HighwayFM 1472
From7.854 MI N OF FM 1472/SH 255 INT
To2.00 MILES NORTH
CSJ2150-03-025
Proj IDC 2150-3-25
Work TypeGRAD,BASE,STRUCTURES AND SURFACE
 
2.0002940497.26667299.8622.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-14-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days200
Addl Days Granted0
Working Days Charged38
Percent Time Used19
Contractor(s)
ANGEL BROTHERS HOLDINGS CORP.
SUBCONTRACTOR(S) FOR CCSJ: 2150-03-025
D&S TEXAS ICON CONSTRUCTION (5.41)
FLASHER EQUIPMENT COMPANY (1.48)
HIGHWAY BARRICADES AND SERVICES, LLC (2.38)
MV HENKE COMPANY, LLC (1.51)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (2.65)
THE LEVY COMPANY, INC. (0.47)
Contract #05173243
Totals2940497.26201056.75667299.8622.6

CountyVAL VERDE
HighwaySL 79
FromUS 277 SOUTH
To3.16 MILES NORTH OF US 277 SOUTH
CSJ3621-01-012
Proj IDSTP 1702(690)
Work TypeBASE,GRADE,ACP,PAVMRK,ILLUMINATION
 
3.1615023548.031310298.8726.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-20-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days115
Addl Days Granted0
Working Days Charged52
Percent Time Used45
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 3621-01-012
90 WEST CONTRACTOR"S, INC. (7.04)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (4.16)
F & W ELECTRICAL CONTRACTORS, INC. (6.89)
FLASHER EQUIPMENT COMPANY (0.91)
FUQUAY, INC. (7.86)
KL DURHAM CONSTRUCTION, LLC (1.82)
Contract #08173008
Totals5023548.03292601.151310298.8726.0