Monthly Local Let Maintenance Report For Lufkin District As Of Oct 16, 2017 Page 6 Of 7

Last Update: Monday, October 16, 2017
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountySAN JACINTO
HighwayUS0059
FromVARIOUS LOCATIONS IN THE SAN JACINTO
ToCOUNTY MAINTENANCE SECTION
CSJ6318-77-001
Proj IDRMC - 631877001
Work TypeCULVERT AND DITCH CLEANING
 
0.010222810.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days70
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
L&S EXCAVATION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6318-77-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09171107
Totals222810.000.000.000.0

CountyPOLK
HighwayUS0059
FromVARIOUS LOCATIONS IN THE POLK COUNTY
ToMAINTENANCE SECTION
CSJ6318-78-001
Proj IDRMC - 631878001
Work TypeHIGH EDGE REMOVAL
 
0.010201610.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days100
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
NEWMAN & KENG PAVING COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6318-78-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09171108
Totals201610.000.000.000.0

CountyTRINITY
HighwaySH0094
FromVARIOUS LOCATIONS IN TRINITY COUNTY
ToMAINTENANCE SECTION
CSJ6318-79-001
Proj IDRMC - 631879001
Work TypeDITCH CLEANING
 
0.010236475.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days80
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
L&S EXCAVATION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6318-79-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09171109
Totals236475.000.000.000.0

CountyHOUSTON
HighwaySL0304
FromHOUSTON COUNTY MAINTENANCE
ToOFFICE
CSJ6319-47-001
Proj IDSUP - 631947001
Work TypeJANITORIAL MAINTENANCE
 
0.01012144.001772.0014.5
Work Order08-28-17
Work Began09-01-17
Work Completed
Time Computed09-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged30
Percent Time Used8
Contractor(s)
TIBH INDUSTRIES, INC.
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6319-47-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08171104
Totals12144.001772.001772.0014.5

CountyTRINITY
HighwayUS0287
FromTRINITY COUNTY MAINTENANCE
ToOFFICE
CSJ6319-48-001
Proj IDSUP - 631948001
Work TypeJANITORIAL MAINTENANCE
 
0.01022423.541655.727.3
Work Order08-30-17
Work Began09-01-17
Work Completed
Time Computed09-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged30
Percent Time Used8
Contractor(s)
TIBH INDUSTRIES, INC.
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6319-48-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08171111
Totals22423.541655.721655.727.3

CountyANGELINA
HighwayUS0059
FromLUFKIN DISTRICT OFFICE AND NACOGDOCHES
ToMAINTENANCE/AREA OFFICE
CSJ6319-49-001
Proj IDSUP - 631949001
Work TypeJANITORIAL MAINTENANCE
 
0.01049288.324107.368.3
Work Order08-24-17
Work Began09-01-17
Work Completed
Time Computed09-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged30
Percent Time Used8
Contractor(s)
TIBH INDUSTRIES, INC.
OAK CREEK DAY HABILITATION/VOCATION CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6319-49-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08171101
Totals49288.324107.364107.368.3

CountySAN JACINTO
HighwayUS0059
FromSAN JACINTO COUNTY
ToMAINTENANCE OFFICE
CSJ6319-50-001
Proj IDSUP - 631950001
Work TypeJANITORIAL MAINTENANCE
 
0.01015775.741142.757.2
Work Order08-31-17
Work Began09-01-17
Work Completed
Time Computed09-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged30
Percent Time Used8
Contractor(s)
TIBH INDUSTRIES, INC.
WOODCREEK OUTREACH REHABILITATION DEVELOPMENT
SUBCONTRACTOR(S) FOR CCSJ: 6319-50-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08171112
Totals15775.741142.751142.757.2

CountyANGELINA
HighwayUS0059
FromLUFKIN DISTRICT
ToOFFICE
CSJ6319-51-001
Proj IDSUP - 631951001
Work TypeWASHING AND DETAILING VEHICLES
 
0.0106573.25215.543.2
Work Order08-28-17
Work Began09-01-17
Work Completed
Time Computed09-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged30
Percent Time Used8
Contractor(s)
TIBH INDUSTRIES, INC.
OAK CREEK DAY HABILITATION/VOCATION CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6319-51-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08171103
Totals6573.25215.54215.543.2

CountyANGELINA
HighwayUS0059
FromVARIOUS LOCATION IN ANGELINA COUNTY
ToMAINTENANCE SECTION
CSJ6319-52-001
Proj IDSUP - 631952001
Work TypeDELINEATOR, OBJ MRK, MAILBOX & SIGN STR
 
0.010100000.004842.004.8
Work Order08-30-17
Work Began09-01-17
Work Completed
Time Computed09-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged30
Percent Time Used8
Contractor(s)
TIBH INDUSTRIES, INC.
GATEWAY COMMUNITY PARTNERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6319-52-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08171109
Totals100000.004842.004842.004.8

CountyPOLK
HighwayUS0059
FromVARIOUS LOCATIONS IN POLK COUNTY
ToMAINTENANCE SECTION
CSJ6319-53-001
Proj IDSUP - 631953001
Work TypeDELINEATOR, OBJ MRKR, MAILBOX & SIGN
 
0.010200000.001832.000.9
Work Order08-28-17
Work Began09-01-17
Work Completed
Time Computed09-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged30
Percent Time Used8
Contractor(s)
TIBH INDUSTRIES, INC.
GATEWAY COMMUNITY PARTNERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6319-53-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08171106
Totals200000.001832.001832.000.9

CountySAN JACINTO
HighwayUS0059
FromVARIOUS LOCATIONS IN SAN JACINTO
ToCOUNTY MAINTENANCE SECTION
CSJ6319-54-001
Proj IDSUP - 631954001
Work TypeDELINEATOR, OBJ MARKER & MAILBOX MAINT
 
0.01070000.008053.0011.5
Work Order08-29-17
Work Began09-01-17
Work Completed
Time Computed09-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged30
Percent Time Used8
Contractor(s)
TIBH INDUSTRIES, INC.
GATEWAY COMMUNITY PARTNERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6319-54-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08171107
Totals70000.008053.008053.0011.5

CountySAN AUGUSTINE
HighwayUS0096
FromVARIOUS LOCATIONS IN SAN AUGUSTINE
ToCOUNTY MAINTENANCE SECTION
CSJ6319-55-001
Proj IDSUP - 631955001
Work TypeDELINEATOR, OBJ MRK & MAILBOX MAINT
 
0.010180000.0017806.009.8
Work Order08-30-17
Work Began09-01-17
Work Completed
Time Computed09-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged30
Percent Time Used8
Contractor(s)
TIBH INDUSTRIES, INC.
GATEWAY COMMUNITY PARTNERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6319-55-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08171110
Totals180000.0017806.0017806.009.8

CountySABINE
HighwayUS0096
FromVARIOUS LOCATION IN SABINE COUNTY
ToMAINTENANCE SECTION
CSJ6319-56-001
Proj IDSUP - 631956001
Work TypeDELINEATOR, OBJ MRK & MAILBOX MAINT
 
0.010182000.0014147.007.7
Work Order08-28-17
Work Began09-01-17
Work Completed
Time Computed09-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged30
Percent Time Used8
Contractor(s)
TIBH INDUSTRIES, INC.
GATEWAY COMMUNITY PARTNERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6319-56-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08171108
Totals182000.0014147.0014147.007.7

CountyNACOGDOCHES
HighwayUS0059
FromVARIOUS LOCATIONS IN NACOGDOCHES
ToCOUNTY
CSJ6319-57-001
Proj IDSUP - 631957001
Work TypeCURB AND GUTTER MAINTENANCE
 
0.01046744.323421.607.3
Work Order08-28-17
Work Began09-01-17
Work Completed
Time Computed09-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged30
Percent Time Used8
Contractor(s)
TIBH INDUSTRIES, INC.
GATEWAY COMMUNITY PARTNERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6319-57-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08171105
Totals46744.323421.603421.607.3

CountySHELBY
HighwaySH0007
FromVARIOUS LOCATIONS IN SHELBY COUNTY
ToMAINTENANCE SECTION
CSJ6321-56-001
Proj IDRMC - 632156001
Work TypeTREE & BRUSH REMOVAL AND TREE TRIMMING
 
0.010257604.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days200
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
CROSS PLUS CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6321-56-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09171110
Totals257604.000.000.000.0

CountyTRINITY
HighwaySH0019
FromVARIOUS LOCATIONS IN TRINITY COUNTY
ToMAINTENANCE SECTION
CSJ6321-57-001
Proj IDRMC - 632157001
Work TypeGUARD FENCE, ATTENUATOR, & MTL RAIL REP
 
0.010160600.200.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days200
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ACE CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6321-57-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09171111
Totals160600.200.000.000.0

CountyANGELINA
HighwayUS0059
FromVARIOUS LOCATIONS IN ANGELINA, SABINE,
ToSAN AUGUSTINE, & SHELBY COUNTY MAINT SEC
CSJ6322-98-001
Proj IDRMC - 632298001
Work TypeCRACK SEALING
 
0.01089949.940.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days40
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
AW&E CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 6322-98-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10171110
Totals89949.940.000.000.0

CountyHOUSTON
HighwayUS0287
FromVARIOUS LOCATIONS IN HOUSTON, POLK,
ToSAN JACINTO, & TRINITY COUNTY MAINT SEC
CSJ6322-99-001
Proj IDRMC - 632299001
Work TypeCRACK SEALING
 
0.01093890.380.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days40
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
D & M CONTRACTORS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6322-99-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10171111
Totals93890.380.000.000.0

CountyANGELINA
HighwayUS0059
FromANGELINA COUNTY MAINTENANCE
ToOFFICE
CSJ6323-23-001
Proj IDSUP - 632323001
Work TypeJANITORIAL MAINTENANCE
 
0.0107402.00585.007.9
Work Order08-25-17
Work Began09-01-17
Work Completed
Time Computed09-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged30
Percent Time Used8
Contractor(s)
TIBH INDUSTRIES, INC.
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6323-23-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08171102
Totals7402.00585.00585.007.9

CountyANGELINA
HighwayUS0059
From0.4 MI S OF FM 2021
ToCONC PVMT W OF FM 58
CSJ6323-39-001
Proj IDEMC - 632339001
Work TypeMILL & OVERLAY
 
4.3052629315.742314242.3288.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-06-17
Work Completed
Time Computed00-00-00
Contract Working Days21
Addl Days Granted0
Working Days Charged20
Percent Time Used95
Contractor(s)
DREWERY CONSTRUCTION COMPANY, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6323-39-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09171112
Totals2629315.742314242.322314242.3288.0